CN100440760C CNB2003101230958A CN200310123095A CN100440760C CN 100440760 C CN100440760 C CN 100440760C CN B2003101230958 A CNB2003101230958 A CN B2003101230958A CN 200310123095 A CN200310123095 A CN 200310123095A CN 100440760 C CN100440760 C CN 100440760C
Authority
CN
China
Prior art keywords
power control
control performance
performance monitoring
information
tpc
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CNB2003101230958A
Other languages
Chinese (zh)
Other versions
CN1633049A (en
Inventor
许胜洪
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shenzhen Shangge Intellectual Property Service Co ltd
Zhangjiagang Zhiying Electronic Technology Co ltd
Original Assignee
Huawei Technologies Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Huawei Technologies Co Ltd filed Critical Huawei Technologies Co Ltd
Priority to CNB2003101230958A priority Critical patent/CN100440760C/en
Publication of CN1633049A publication Critical patent/CN1633049A/en
Application granted granted Critical
Publication of CN100440760C publication Critical patent/CN100440760C/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Abstract

The present invention provides a method for monitoring the power control performance of a wideband code division multiple access system. A power control performance monitoring background is arranged at the side of Node B to make parameter curve information such as SIR/SIR <target> curves or BLER statistical result curves or down transmitting code domain power curves or RSSI curves which correspond to the power control and can only be observed at the side of RNC observed at the side of the Node B without the limitation of the RNC; simultaneously, the time accuracy of observed parameters can be accurate to any time slot, and the minimum unit of the parameter curves can be increased from the original second to 10 ms. In addition, a user can also observe monitoring results of up TPC and down TPC reported by the Node B so as to favorably track and position the problem of the WCDMA system.

Description

A kind of method that monitors the broadband CDMA system power control performance
Technical field
The present invention relates to the wireless monitoring technology field, be meant a kind of method that monitors the broadband CDMA system power control performance especially.
Background technology
The control of Wideband Code Division Multiple Access (WCDMA) (WCDMA) system power comprises closed power control and exterior ring power control.The control of WCDMA closed power is signal interference ratio (SIR) measured value and the signal interference ratio thresholding (SIR by receiving Target) compare, to determine transmitting power control (TPC) information, then TPC information is sent to transmitting terminal, regulate the size of transmitting power with this.WCDMA exterior ring power control technology then is by to receiving the calculating of Block Error Rate (BLER), determines the required SIR of closed power control Target
In order effectively to monitor WCDMA system power control performance, must specify the key message for the treatment of monitoring user to the WCDMA system, as SIR, SIR TargetBe used to control the up TPC of user terminal (UE) uplink transmission power, be used to control the descending TPC of base station (Node B) downlink transmission power, gross power (RTWP) and downlink dedicated channels sign indicating number territory transmitting power (TCP) etc. in BLER, the up receiving belt are carried out dynamic real-time and are observed.
In the WCDMA system, the existing method of designated user power control performance that monitors is that the backstage of safeguarding that radio network controller (RNC) side of application WCDMA provides monitors the power control performance of system.The specific implementation method is: safeguard that at RNC the backstage starts the designated user switching performance and follows the tracks of, RNC sends to Node B by Iub (Interface of RNC and Node B) interface and starts measuring command, require Node B with the sir measurement value, descending TCP, up RTWP reported by the Iub interface cycle, wherein, was 80ms according to the minimum report cycle of agreement regulation sir measurement value, RNC is local by RRM (RRM) module simultaneously, record SIR Target, and BLER information.The backstage of safeguarding of RNC side is with global positioning system (GPS with the reporting information of Node B and the information translation of RNC local record, Global Positioning System) time is the figure of abscissa, in different windows, show, thereby the purpose of the power control performance of WCDMA system designated user is observed in realization.
Said method have a following shortcoming:
1) because field testing need be specified the sir measurement value of the every 10ms radio frames of channel to be measured or each time slot (a 10ms radio frames is divided into 15 time slots according to the time interval) usually, and the cycle of Node B by Iub interface SI reporting R measured value is 80ms, and the least unit of the abscissa of observed parameter curve is second, therefore, this scheme precision under a lot of occasions such as field testing is not enough;
2) must notify Node B to start the sir measurement reporting functions by RNC, otherwise Node B can SI reporting R measured value, is restricted thereby this programme is used;
3) because in the prior art, all information is gathered by the RRM module of RNC inside, therefore, the information of up TPC and descending TPC can't be extracted observation;
Each information of 4) being gathered is presented in the different window interfaces, uses inconvenient.
Summary of the invention
In view of this, the object of the present invention is to provide a kind of method that monitors the broadband CDMA system power control performance, make the information of supervision more accurate more comprehensively.
For achieving the above object, technical scheme of the present invention is achieved in that
A kind of method that monitors the broadband CDMA system power control performance, this method may further comprise the steps:
A, power control performance monitoring backstage is set in the operation maintaining background of wide-band CDMA base station Node B;
B, Node B gather the monitor message of appointment in the monitor command after receiving and starting the order of power control performance monitoring, and the information of being gathered to power control performance monitoring backstage periodic report;
C, power control performance monitoring backstage are presented at the information that the Node B that receives reports in the window interface.
Preferably, described step b further comprises: Node B judges at first whether this order is legal, if illegal after receiving startup power control performance monitoring order from power control performance monitoring backstage, report the error message prompting then directly for power control performance monitoring backstage, otherwise carry out subsequent step.
Preferably, described step c further comprises: subsequent step is carried out after the reporting information from NodeB that receives is preserved again in power control performance monitoring backstage.
Preferably, the described power control performance monitoring of step a backstage directly links to each other with Node B by near-end network interface or the far-end Internet protocol IP OA based on asynchronous transfer mode.
Preferably, the order of the described power control performance monitoring of step b is directly sent by power control performance monitoring backstage, or is sent by Iub interface by radio network controller (RNC).
Preferably, comprise in the parameter of step b power control performance monitoring order: the call number of designated user, the abscissa of display graphics, and signal interference ratio sir measurement value and signal interference ratio thresholding SIR TargetThe enabler flags that reports that reports enabler flags and/or block error rate BLER statistics message that reports gross power RTWP message in enabler flags, the received signal band that reports enabler flags, downlink code domain power TCP message that reports enabler flags, uplink transmission power control TPC and downlink transmission power control TPC message of value message.
Preferably, the monitor message of appointment comprises in the described monitor command of step b: signal interference ratio sir measurement value, signal interference ratio thresholding SIR TargetGross power RTWP in value, uplink transmission power control TPC, downlink transmission power control TPC, block error rate BLER statistics, downlink code domain power TCP and the received signal band.
Preferably, for signal interference ratio sir measurement value and signal interference ratio thresholding SIR TargetValue, the minimum value in described monitor message cycle is a time slot; For gross power RTWP in uplink transmission power control TPC, downlink transmission power control TPC, block error rate BLER statistics, downlink code domain power TCP and the received signal band, the minimum value in described monitor message cycle is the 10ms radio frames.
Preferably, the method of the described collection of step b is: by the base station according to the enabler flags in the order of power control performance monitoring, send acquisition for each correlation module in the baseband subsystems, by each correlation module in the baseband subsystems gather and with the information that collected by the canonical form framing after the cycle report power control performance monitoring backstage.
Preferably, the Information Monitoring of each correlation module in the described baseband subsystems is: descending power weightings module is gathered descending TCP information, up Digital Down Converter Module is gathered up RTWP information, and up demodulation module is gathered up TPC, descending TPC, up SIR and up SIR TargetInformation, up decoding module is gathered up BLER information.
Preferably, this method further comprises: according to the enabler flags in the order of power control performance monitoring, send the order that stops to gather for each corresponding module in the baseband subsystems by the base station, each corresponding module in the notice baseband subsystems stops collection and reports.
What preferably, comprise 6 fixed positions that set in advance in the described window interface of step c is used to show the subwindow of measuring curve.
Use the present invention,, make and to control relevant parameter curve information with power in that the RNC side is observed, as SIR/SIR by power control performance monitoring backstage being set in Node B side TargetCurve, perhaps BLER statistics curve, perhaps downlink code domain power curve, perhaps RSSI curve, all can observe, and not be subjected to the restriction of RNC, simultaneously in Node B side, the time precision of observed parameter can be accurate to any time slot, the parameter curve least unit second can rise to 10ms by original.In addition, the user can also observe up TPC that Node B reports and the monitoring result of descending TPC, thereby helps more that the WCDMA system problem is followed the tracks of and the location.
Description of drawings
Figure 1 shows that power control performance monitoring backstage that the present invention is provided with and the connection diagram between the Node B;
Figure 2 shows that the schematic diagram of using observation power control performance window of the present invention.
Embodiment
Below in conjunction with drawings and the specific embodiments the present invention is described in further detail again.
Thinking of the present invention is: power control performance monitoring backstage is set in the operation maintaining background of Node B; After Node B receives and starts the order of power control performance monitoring, the monitor message of appointment in the acquisition monitoring order, and the information of being gathered to power control performance monitoring backstage periodic report; Power control performance monitoring backstage is presented at the information that the Node B that receives reports in the window interface.Concrete implementation procedure is as follows:
Safeguard at the WCDMA base station operation power control performance monitoring backstage is set in the backstage, this power control performance monitoring backstage is the executable program module on backstage, WCDMA base station, and operate in the WCDMA base station operation and safeguard on the background computer, this WCDMA base station operation safeguards that background computer passes through the near-end network interface or far-end IP OA (Internet Protocol over ATM) links to each other with the base station of WCDMA, as shown in Figure 1.
In the time need monitoring to the power control performance of designated user, at first obtain the call number UserId that waits to observe power control performance user, safeguard that by base station operation the power control performance monitoring backstage in the backstage directly sends the order that starts the power control performance monitoring to Node B again, or send the order that starts the power control performance monitoring by Iub interface to NodeB by RNC, parameter and value implication thereof in this order are as shown in table 1:
The command parameter title The value implication
The call number UserId of designated user User index number
SIR/SIR targetThe information reporting enabler flags Enable or do not enable
The descending TPC information reporting of up TPC/ enabler flags Enable or do not enable
Descending TCP information reporting enabler flags Enable or do not enable
RTWP reports enabler flags Enable or do not enable
BLER statistics information reporting enabler flags Enable or do not enable
The requirement of drawing abscissa Gps time or BFN
Table 1
The least unit of the Node B frame number (BFN) in the table 1 is to be 10ms, but for the ease of observing, gets 100ms usually.
After Node B receives the order of " starting the power control performance monitoring ", judge whether the parameter in this order is legal, if it is illegal, then directly report the error message prompting to power control performance monitoring backstage, otherwise notify the corresponding module in the baseband subsystems in it to carry out information gathering according to the parameter that enables of indicating in the monitor command, and be the timestamp that the information of being gathered is stamped GPS or BFN, the module of carrying out Information Monitoring with the information that collected according to the mode standard framing after, report to power control performance monitoring backstage according to the predefined cycle.For SIR/SIR Target, its minimum value that preestablishes the cycle can be a time slot, and for other Information Monitoring, its predefined minimum period is the 10ms radio frames.
The corresponding relation of the correlation module in the baseband subsystems and institute's Information Monitoring is as shown in table 2:
Module in the baseband subsystems Information Monitoring
Descending power weightings module Descending TCP
Up Digital Down Converter Module Up RTWP
Up demodulation module The up SIR of the up SIR of the descending TPC of up TPC target
Up decoding module Up BLER
Table 2
For example, if the SIR/SIR in the order of power control performance monitoring TargetMessage, the descending TPC message of up TPC/ and BLER message to report the enabler flags that reports in the enabler flags parameter be " enabling ", and abscissa is drawn and is required to be BFN, the corresponding module of the Information Monitoring in the baseband subsystems then, be uplink demodulation module and up decoding module, with the information that has the BFN timestamp that collected according to the mode standard framing after, according to the predefined cycle,, report to power control performance monitoring backstage as every 100ms radio frames.
The reporting message from Node B that power control performance monitoring backstage will receive at first is kept at this locality, and the form that then the message parameter content is converted to the graphical display requirement is presented in the rectangular coordinate system.For example, it is 100ms that power control performance monitoring backstage is plotted in BFN the Information Monitoring that receives for abscissa unit, with the measuring amount is in the rectangular coordinate system of ordinate, and the figure of all measured values all is presented in predefined the same window interface of being made up of an above subwindow.
Figure 2 shows that the schematic diagram of using observation power control performance window of the present invention.This window of observing the power control performance is made up of 6 sub-windows, each subwindow is used to show different monitor curves, and the position of each subwindow is according in advance the relative fixed that is provided with, as shown in Figure 2, subwindow 1 is used to show the BLER curve, and subwindow 2 is used to show up TPC curve, subwindow 3 is used to show descending TPC curve, subwindow 4 is used to show the RTWP curve, and subwindow 5 is used to show descending TCP curve, and subwindow 6 is used to show SIR and SIR TargetCurve, more than the abscissa of all subwindows can all be GPS or all be BFN according to the requirement of monitor command.
With reference to the example of front, if only require to monitor SIR, SIR in the monitor command Target, up TPC, descending TPC and BLER information, then observe in the window of power control performance at this, have only in the subwindow 1,2,3,6 curve display arranged, and in subwindow 4,5, do not show any content.
According to shown power control performance monitoring curve, system can analyze the power control performance of designated user, and monitors the communication quality of the used channel of this user.If Node B is a report cycle with each time slot, the sir measurement value of each time slot that system is preserved according to power control performance monitoring backstage, can also carry out the post processing operations operation, as accurately calculate sir measurement average and variance etc., thereby realize the purpose of the power control performance of further analytical system institute monitoring user.
The above only is preferred embodiment of the present invention, and is in order to restriction the present invention, within the spirit and principles in the present invention not all, any modification of being done, is equal to replacement, improvement etc., all should be included within protection scope of the present invention.

Claims (12)

1, a kind of method that monitors the broadband CDMA system power control performance is characterized in that, this method may further comprise the steps:
A, power control performance monitoring backstage is set in the operation maintaining background of wide-band CDMA base station Node B;
B, Node B gather the monitor message of appointment in the monitor command after receiving and starting the order of power control performance monitoring, and the information of being gathered to power control performance monitoring backstage periodic report;
C, power control performance monitoring backstage are presented at the information that the Node B that receives reports in the window interface.
2, method according to claim 1, it is characterized in that, described step b further comprises: after Node B receives startup power control performance monitoring order from power control performance monitoring backstage, judge at first whether this order is legal, if it is illegal, report the error message prompting then directly for power control performance monitoring backstage, otherwise carry out subsequent step.
3, method according to claim 1 is characterized in that, described step c further comprises: subsequent step is carried out after the reporting information from Node B that receives is preserved again in power control performance monitoring backstage.
According to claim 1,2 or 3 described methods, it is characterized in that 4, the described power control performance monitoring of step a backstage directly links to each other with NodeB by near-end network interface or the far-end Internet protocol IP OA based on asynchronous transfer mode.
According to claim 1,2 or 3 described methods, it is characterized in that 5, the order of the described power control performance monitoring of step b is directly sent by power control performance monitoring backstage, or is sent by Iub interface by radio network controller (RNC).
6, according to claim 1,2 or 3 described methods, it is characterized in that, comprise in the parameter of step b power control performance monitoring order: the call number of designated user, the abscissa of display graphics, and signal interference ratio sir measurement value and signal interference ratio thresholding SIR TargetThe enabler flags that reports that reports enabler flags and/or block error rate BLER statistics message that reports gross power RTWP message in enabler flags, the received signal band that reports enabler flags, downlink code domain power TCP message that reports enabler flags, uplink transmission power control TPC and downlink transmission power control TPC message of value message.
According to claim 1,2 or 3 described methods, it is characterized in that 7, the monitor message of appointment comprises in the described monitor command of step b: signal interference ratio sir measurement value, signal interference ratio thresholding SIR TargetGross power RTWP in value, uplink transmission power control TPC, downlink transmission power control TPC, block error rate BLER statistics, downlink code domain power TCP and the received signal band.
8, method according to claim 7 is characterized in that, for signal interference ratio sir measurement value and signal interference ratio thresholding SIR TargetValue, the minimum value in described monitor message cycle is a time slot; For gross power RTWP in uplink transmission power control TPC, downlink transmission power control TPC, block error rate BLER statistics, downlink code domain power TCP and the received signal band, the minimum value in described monitor message cycle is the 10ms radio frames.
9, according to claim 1,2 or 3 described methods, it is characterized in that, the method of the described collection of step b is: by the base station according to the enabler flags in the order of power control performance monitoring, send acquisition for each correlation module in the baseband subsystems, by each correlation module in the baseband subsystems gather and with the information that collected by the canonical form framing after the cycle report power control performance monitoring backstage.
10, method according to claim 9, it is characterized in that, the Information Monitoring of each correlation module in the described baseband subsystems is: descending power weightings module is gathered descending TCP information, up Digital Down Converter Module is gathered up RTWP information, and up demodulation module is gathered up TPC, descending TPC, up SIR and up SIR TargetInformation, up decoding module is gathered up BLER information.
11, method according to claim 9, it is characterized in that, this method further comprises: by the base station according to the enabler flags in the order of power control performance monitoring, send the order that stops to gather for each corresponding module in the baseband subsystems, each corresponding module in the notice baseband subsystems stops collection and reports.
12, method according to claim 1 is characterized in that, what comprise 6 fixed positions that set in advance in the described window interface of step c is used to show the subwindow of measuring curve.
CNB2003101230958A 2003-12-24 2003-12-24 A method for monitoring power control performance of WCDMA system Expired - Fee Related CN100440760C (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNB2003101230958A CN100440760C (en) 2003-12-24 2003-12-24 A method for monitoring power control performance of WCDMA system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNB2003101230958A CN100440760C (en) 2003-12-24 2003-12-24 A method for monitoring power control performance of WCDMA system

Publications (2)

Publication Number Publication Date
CN1633049A CN1633049A (en) 2005-06-29
CN100440760C true CN100440760C (en) 2008-12-03

Family

ID=34844734

Family Applications (1)

Application Number Title Priority Date Filing Date
CNB2003101230958A Expired - Fee Related CN100440760C (en) 2003-12-24 2003-12-24 A method for monitoring power control performance of WCDMA system

Country Status (1)

Country Link
CN (1) CN100440760C (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101719801B (en) * 2009-11-25 2013-01-16 中兴通讯股份有限公司 Method and system for realizing power detection
WO2011074008A1 (en) * 2009-12-16 2011-06-23 Nsg Networks Private Limited Integrated monitoring and control system
CN103974305A (en) * 2013-01-25 2014-08-06 中兴通讯股份有限公司 Method, system and base station for tracking user information
US10474216B2 (en) * 2015-12-16 2019-11-12 Intel Corporation Method and apparatus for providing power state information using in-band signaling
CN107343290B (en) * 2017-07-04 2019-12-03 中国联合网络通信集团有限公司 The expansion method and device of RRU cascade cell

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6094585A (en) * 1997-11-14 2000-07-25 Lucent Technologies Inc. CDMA forward link power overload control in a base station
US6144861A (en) * 1998-04-07 2000-11-07 Telefonaktiebolaget Lm Ericsson Downlink power control in a cellular mobile radio communications system
CN1321015A (en) * 2000-04-25 2001-11-07 日本电气株式会社 Code division multiple access mobile communication system and its transmission power control method
CN1387333A (en) * 2001-05-17 2002-12-25 深圳市中兴通讯股份有限公司 Method for measuring power control bit in CDMA system

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6094585A (en) * 1997-11-14 2000-07-25 Lucent Technologies Inc. CDMA forward link power overload control in a base station
US6144861A (en) * 1998-04-07 2000-11-07 Telefonaktiebolaget Lm Ericsson Downlink power control in a cellular mobile radio communications system
CN1321015A (en) * 2000-04-25 2001-11-07 日本电气株式会社 Code division multiple access mobile communication system and its transmission power control method
CN1387333A (en) * 2001-05-17 2002-12-25 深圳市中兴通讯股份有限公司 Method for measuring power control bit in CDMA system

Also Published As

Publication number Publication date
CN1633049A (en) 2005-06-29

Similar Documents

Publication Publication Date Title
CN101527923B (en) Access point configured for requesting and receiving measurement
US10142872B2 (en) Measurement method and device for wireless network communication system
US7453857B2 (en) Measuring medium activity patterns in wireless networks and deriving information from the activity patterns
US20090036116A1 (en) Method and system for measuring quality of wireless network
CN104780581B (en) The method for the adaptive cell detection activity level that event triggers in discontinuous reception and configuration
US8804555B2 (en) Interference detection in mobile telecommunications networks
EP2536197A1 (en) Method and system for reporting neighbor cell information
US20070099561A1 (en) System and method for tracking UMTS cell traffic
CN102740349B (en) Terminal measurement scheduling method and device
US7466682B1 (en) Forward and reverse link capacity determination
CN103906096B (en) The acquisition method and device of metrical information in a kind of measurement report
CN100440760C (en) A method for monitoring power control performance of WCDMA system
CN113132898B (en) 5G NR uplink energy measuring method
CN102082614B (en) Method and device for detecting quality of communication system based on sweep generator
CN103428730B (en) A kind of minimum drive test qos measurement result transmission method and device
WO1998052288A1 (en) Method and apparatus for estimating capacity in a communication system
KR100560989B1 (en) System and Method for Analyzing Radio Environment in Wideband Code Division Multiple Access Network
CN100542346C (en) The method and apparatus that shows measurement report in the mobile communication system
CN1422025A (en) Method for determining electric field state of mobile station and simultaneously considering up-link electric field status
US20070202918A1 (en) Apparatus and method for testing and analyzing base station with smart antenna, and protocol structure
EP1423925A1 (en) Moment decision for packet data transmission based on analysis of power control commands
US9398502B2 (en) Method for measuring adjacent areas
TWI520631B (en) Cellular mobile network dynamic communication quality analysis method
ZA200509028B (en) Measuring medium activity patterns in wireless networks and deriving information from the activity patterns
EP2101427A1 (en) Method and system for measuring geometry experienced by end users in a network in operation

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20200813

Address after: 518000 Baoan District Xin'an street, Shenzhen, Guangdong, No. 625, No. 625, Nuo platinum Plaza,

Patentee after: SHENZHEN SHANGGE INTELLECTUAL PROPERTY SERVICE Co.,Ltd.

Address before: 518129 Bantian HUAWEI headquarters office building, Longgang District, Guangdong, Shenzhen

Patentee before: HUAWEI TECHNOLOGIES Co.,Ltd.

Effective date of registration: 20200813

Address after: 215600 No. 2 Binhe Road, Yangshe Town, Zhangjiagang City, Suzhou City, Jiangsu Province (East China International Building) B405 Zhangjiagang Zhiying Electronic Technology Co., Ltd.

Patentee after: ZHANGJIAGANG ZHIYING ELECTRONIC TECHNOLOGY Co.,Ltd.

Address before: 518000 Baoan District Xin'an street, Shenzhen, Guangdong, No. 625, No. 625, Nuo platinum Plaza,

Patentee before: SHENZHEN SHANGGE INTELLECTUAL PROPERTY SERVICE Co.,Ltd.

CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20081203