CN101158993A - Civil construction engineering GPS-RTK measurement integrated PDA device - Google Patents

Civil construction engineering GPS-RTK measurement integrated PDA device Download PDF

Info

Publication number
CN101158993A
CN101158993A CNA2007100929319A CN200710092931A CN101158993A CN 101158993 A CN101158993 A CN 101158993A CN A2007100929319 A CNA2007100929319 A CN A2007100929319A CN 200710092931 A CN200710092931 A CN 200710092931A CN 101158993 A CN101158993 A CN 101158993A
Authority
CN
China
Prior art keywords
data
gps
rtk
module
engineering
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CNA2007100929319A
Other languages
Chinese (zh)
Other versions
CN100580679C (en
Inventor
冯晓
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CHONGQING LUGAO ROAD ENGINEERING TECHNOLOGY CONSULTATION Co Ltd
Original Assignee
CHONGQING LUGAO ROAD ENGINEERING TECHNOLOGY CONSULTATION Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CHONGQING LUGAO ROAD ENGINEERING TECHNOLOGY CONSULTATION Co Ltd filed Critical CHONGQING LUGAO ROAD ENGINEERING TECHNOLOGY CONSULTATION Co Ltd
Priority to CN200710092931A priority Critical patent/CN100580679C/en
Publication of CN101158993A publication Critical patent/CN101158993A/en
Application granted granted Critical
Publication of CN100580679C publication Critical patent/CN100580679C/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The invention discloses a PDA device of civil and architectural engineering GPS-RTK measurement integration, which is a PDA computer used for GPS-RTK data collection and processing and applied to civil and architectural engineering. The hardware in the PDA computer comprises a display, press keys and hanging parts, a host chip equipped inside the body with a dominant frequency above 400MHz, a bluetooth module and a GPRS module, a built-in data transmission antenna and a power supply; a built-in software system in the PDA computer integrates the data collection, processing, application and transmission of GPS-RTK, which greatly enhances operation efficiency and reliability, directly accomplishes the tasks like design and survey, construction survey, and geometric detection etc. of normal civil engineering (including highways, railways, port terminals, city roads and pipe network, hydropower project and so on), does not need the prior fractional work such as data downloading, indoor processing, outdoor surveying and designing etc., and obviously enhances the operation efficiency of civil engineering measurement.

Description

Civil construction engineering GPS-RTK measurement integrated PDA device
Technical field
The present invention relates to open-air engineering survey device, be specifically related to a kind of GPS-RTK and PDA integral system towards the civil construction project special use, this measurement mechanism is mainly used in and uses the GPS-RTK method to carry out the aspects such as quality testing of civil construction project survey and design, construction lofting and buildings.
Background technology
In the prior art, the GPS-RTK that open-air engineering survey is used (GPS one satellite navigation and location system, RTK-Real Time Kinematic, Real-time and Dynamic) system generally is made up of a base station and a plurality of rover station.Base station and rover station are by formations such as GPS mainboard, radio station, power supply, antenna and foot rests, and rover station also comprises PDA (palm PC) computer installation, and the base station sends its observed reading and survey station coordinate information to rover station together by data chainning; Rover station calculates the observation data of GPS-RTK simultaneously, and resolves the current coordinate of rover station by the data of data chainning reception from the base station.Present GPS-RTK system, all there is following deficiency in the brand product as Switzerland comes card company, U.S. Tian Bao company, southern china company etc.:
1, present product all belongs to the universal industrial product of no professional applications, is mainly used in the exploration of industries such as building, electric power, machinery and construction etc., and operating efficiency is low.
2, the PDA computing machine that it disposed is mainly used in according to the GPS observation data of gathering and resolves the current coordinate of rover station, and only the front end data of output application can not carry out various real-time engineerings and use processing.
3, the PDA computing machine of existing GPS-RTK measuring system rover station is off-gauge product, volume is bigger than normal, screen is little and do not have a graphical display function, need be fixed on the rover station sounding rod and use, no teledata passes device, processor calculating speed is slower, and low memory makes the speed and the efficient that run application lower.
4, the rover station PDA computer operating system of existing GPS-RTK measuring system is different, and user's secondary development is very difficult.Built-in Engineering Speciality application software function seldom makes that engineering application processing is very inconvenient.
5, the rover station PDA computing machine of existing GPS-RTK measuring system mostly is imported product, and cost is higher, and price is up to tens thousand of units.
In addition, Chinese patent CN1928586A disclosed " based on the height above sea level measuring equipment and the method for RTK-GPS technology " discloses a kind of longitude and latitude and height above sea level of measuring tested point, the output device sign is stored the mode of handling and draw the result by modelling, in real time and is handled in real time, and it can not handle in good time.
Summary of the invention
At the prior art above shortcomings, the purpose of this invention is to provide a kind of data acquisition, processing, application and the incorporate civil construction engineering GPS-RTK measurement integrated PDA device of transmission, and have higher processing speed, littler volume and lower use cost GPS-RTK.
The object of the present invention is achieved like this: civil construction engineering GPS-RTK measurement integrated PDA device, it is characterized in that, for being used for the PDA computing machine that GPS-RTK data acquisition, processing and civil construction project are used, the formation rover station combines with the GPS-RTK data acquisition system (DAS), receive data by data chainning, on rover station, finish remote transmission integrated of the collection of GPS observation data, processing, application and application data simultaneously from the base station.
Hardware in the described PDA computing machine, comprise display screen, be located at the display screen left and right sides button, be located at the suspension member of body top, and above host chip, bluetooth module and GPRS module, the built-in number of 400MHz dominant frequency of being located at body interior passes antennas and power supplys; Adopt whole-closed water-proof moisture-proof plastic-steel casing; The effective indication range of display screen is not less than 80 * 80 (mm).
Built-in software in the described PDA computing machine comprises Data Receiving and modular converter, origin coordinate system transform module, database management module, the module of controlling and measure the smashed parts, design mould shape management system, exploration and inquiry module, construction survey module and geometric relationship detection module;
Wherein, Data Receiving and modular converter: to receive and be converted to the data layout of native system standard from the carrier phase difference baseline increment data of GPS-RTK key plate and other data;
The origin coordinate system transform module: through the moonscope data of consolidation form, after obtaining a plurality of earth axes known control point coordinate, the coordinates computed conversion parameter, the WGS-84 coordinate conversion with rover station is the coordinate system coordinate at known control point place then;
Database management module: GPS-RTK coordinate survey data, field investigation, the data that design a model, authority data, system are provided with data etc., use file and ACCESS database mode to manage, quick retrieval modify feature is provided;
The control and the module of measuring the smashed parts: be used to use the GPS-RTK method to set up the inferior grade reference mark fast, measure the smashed parts and define pictorial information;
Design mould shape management system: be used to define, the three-dimensional geometric design model of modification and ground structure things such as management road, buildings, pipeline, railway and track engineering;
Exploration and inquiry module: be used to use the GPS-RTK instrument to carry out various engineering surveys and investigation;
Construction survey module: the surveying work that is used for various engineering constructions;
The geometric relationship detection module: use GPS-RTK equipment is finished the detection to any position geometric properties of engineering fast.
Compared to existing technology, the present invention has following beneficial effect:
1, the present invention utilizes the advantage of GPS-RTK and PDA computing machine, special development and Design forms at civil construction project is required, data acquisition, processing, application and the transmission of GPS-RTK is integrated, operating efficiency and reliability have not only been improved, and avoided the situation of the wasting of resources multiple, that repeatedly handle, thereby reduced application cost.
2, the designed special-purpose RTK of civil engineering measures PDA, adopts bigger display screen to make civil engineering measure and realizes that number figure contrasts fully; By the large screen display figure, can visual means any spatial design model of management civil construction facilities, make the geometry designs scheme directly enter work progress;
3, the multi-specialized application program of built-in civil construction forms the special-purpose RTK-PDA of civil engineering, cooperates with the RTK receiving equipment, can directly finish multi-specialized common measuring task, as survey and design, land investigation, construction lofting and quality control etc.The work that former needs 3~5 people finish can be finished by a people, be used common RTK instrument to do identical work, can save the field process time greatly, increase work efficiency more than one times.
4, PDA hardware internal bluetooth module of the present invention and multiple GPS-RTK mainboard data layout, can and multiple RTK receiver (GPS mainboard) between realize the transmission of blue teeth wireless data wireless, make this device can connect the output data of multiple GPS-RTK equipment, thereby enlarged usable range.
5, PDA hardware internal GPRS digital transmission module of the present invention can be realized the teledata real-time Transmission by wireless network; The location service information that also can receive the net issue of GPS Urban base station carries out real-time RTK location, thereby can realize the unit operation.
6, PDA hardware volume of the present invention is littler, is convenient to carry and deposit; Design simultaneously has the hanging hook of chest not account for hand, especially convenient open-air one-man service.
Description of drawings
Fig. 1 is the GPS-RTK system schematic that open-air engineering survey is used;
Fig. 2-the 1st, the profile front view of PDA device of the present invention;
Fig. 2-the 2nd, the vertical view of Fig. 2-1;
Fig. 2-the 3rd, the right view of Fig. 2-1;
Fig. 3 is the block scheme of computer software part of the present invention.
Embodiment
Below in conjunction with the drawings and specific embodiments the present invention is described in further detail.
Referring to Fig. 1, civil construction engineering GPS-RTK measurement integrated PDA device of the present invention, comprise and be used for the PDA computing machine that GPS-RTK data acquisition, processing and civil construction project are used, the formation rover station combines with the GPS-RTK data acquisition system (DAS), by the gps satellite data of data chainning reception from the base station, with the gps satellite data of rover station, on rover station, finish remote transmission integrated of the collection of GPS difference observation data, processing, application and application data simultaneously.
Shown in Fig. 2-1, Fig. 2-2 and Fig. 2-3, the GPS-RTK of civil construction project special use of the present invention and PDA integrated apparatus, by body 1, display screen 2, be located at the display screen left and right sides button 3, be located at the suspension member 4 of body top, and the above formations such as host chip, power supply and software of 400MHz dominant frequency of being located at body interior.Be designed to the bilateral key layout, but the bilateral operation; Described suspension member 4 is by hook and be linked with and form, and the protection leather sheath, and the person of being easy to use hangs over not only handled easily but also do not account for hand of front; And the present invention can adopt effective indication range to be not less than the ultra-thin touch black and white of the square-shaped patterns daylight display screen of 80 * 80 (mm) because the PDA computer installation is designed to hanging structure, and big screen display screen and left and right bilateral button use convenient.Cumulative volume is littler than the most of industrial PDA of external import, weight is lighter, adopts firm whole-closed water-proof moisture-proof plastic-steel casing, fully numeral and alphabetical Waterproof push-button, adopt bluetooth and GPRS module and built-in number to pass antenna, wireless mode is all used in the data turnover.Use special ultra-thin high capacity aluminum cell power supply, do not use the working time that number passes and high brightness shows to reach more than 3 days like this.
As shown in Figure 3, aspect software, the present invention has designed and developed civil engineering and has used the embedded software system, mainly by Data Receiving and modular converter, origin coordinate system transform module, database management module, and control and the module of measuring the smashed parts, design mould shape management system, exploration and inquiry module, construction survey module and geometric relationship detection module etc. are partly formed.Wherein,
1, Data Receiving and modular converter: to receive and be converted to the data layout of native system standard from the carrier phase difference baseline increment data of GPS-RTK key plate and other data.Be provided with the data layout of present double frequency and single-frequency GPS-RTK mainboard, only need to select the mainboard model just can receive the output data of this mainboard.These data generally comprise baseline increment of coordinate through resolving, ephemeris parameter, single-point locator data, survey sign indicating number differential data etc.
2, origin coordinate system transform module: through the moonscope data of consolidation form, after obtaining a plurality of earth axes known control point coordinate, just can pass through the automatic coordinates computed conversion parameter of this module software, the WGS-84 coordinate conversion with rover station is the coordinate system coordinate at known control point place then.Also can use the coordinate transformation parameter that presets of recommendation, after having selected coordinate system, can change in real time the observation coordinate of every each point automatically.
3, database management module: GPS-RTK coordinate survey data, field investigation, the data that design a model, authority data, system are provided with data etc., use file and ACCESS database mode to manage, quick retrieval modify feature is provided.
4, the module of controlling and measure the smashed parts: be used to use the GPS-RTK method to set up the inferior grade reference mark fast, measure the smashed parts and define pictorial information.The point position and the attribute key element that comprise record controls point, detail point, line and border attribute key element etc.Can be directly used in required digital topography map of various engineering designs and cadastre measures.
5, design mould shape management system: be used to define, the three-dimensional geometric design model of ground such as modification and management road, buildings, pipeline, railway and track engineering, tunnel and shaft sinking and drifting and underground structures.These design a model and can be made up of point, curve and curved surface key element.
6, exploration and inquiry module: be mainly used in and use the GPS-RTK instrument to carry out various engineering surveys and investigation.According to the operation needs, can select to install exploration enquiry procedures such as highway, railway, pipeline, channel.Can finish, feature dotted line (as the middle sideline) setting-out of design proposal, vertical and horizontal section is measured and land used, removal, the bank of engineering such as cut down at investigation etc.
7, construction survey module: be mainly used in the surveying work in the various engineering constructions.Can carry out plane setting-outs (being about to design proposal is provided with), earthwork measurement and construction project time management measurements etc. such as unique point, design axis, property-line, excavatoin line on the ground structure thing on the spot.
8, geometric relationship detection module: in work progress, need geometry quality often, comprise that position, direction and each position geometric scale detect, to compare with designing requirement to construction.The requirement of detected error and standard compares, and can in time estimate out the quality of construction quality.Native system can be selected corresponding geometric relationship detection module according to concrete engineering field, just can use GPS-RTK equipment to finish detection to any position geometric properties of engineering fast.
From the baseline increment of coordinate measurement data of GPS-RTK mainboard and other related datas, import the engineering special-purpose PDA computing machine supporting into GPS-RTK by blue-tooth device is wireless.
At first, carry out the format conversion and the bug check of observation data by the front end data handling procedure; Then, observation data according to known control point is carried out the accuracy checking of coordinate transformation parameter and the conversion and the output engineering coordinate system coordinate of coordinate system to the increment of coordinate data, the rover station terrestrial coordinate of trying to achieve, with field investigation, the data that design a model, authority data, system data etc. are set, all enter data file and database file on the mounting medium, manage by unified data management system.
Obtaining various data, particularly on the basis of GPS-RTK measurement data, can select the corresponding work program to carry out operation according to engineering kind (highway, railway etc.) and engineering phase (exploration, construction etc.).
All geometric datas, literal, data can be shown on than giant-screen special by display routine.
This device has and can contrast operation with figure, two kinds of input methods of touch screen operation and button operation, and two kinds of wireless two-way numbers pass mode, long-acting supplying cell, and the moistureproof shock resistance casing design that discharges water.Match with the GPS-RTK system of combination, can also match with multiple commercially available GPS-RTK receiver, can directly finish work such as the design exploration of (comprising highway, railway, port and pier, urban road and pipe network, hydroelectric project etc.) of common civil engineering, construction survey, geometrical detection, do not need that original data are downloaded, interior industry is handled, field operation surveys to establish etc. and works step by step, can significantly improve civil engineering and measure operating efficiency.

Claims (2)

1. civil construction engineering GPS-RTK measurement integrated PDA device, it is characterized in that, for being used for the PDA computing machine that GPS-RTK data acquisition, processing and civil construction project are used, the formation rover station combines with the GPS-RTK data acquisition system (DAS), receive data by data chainning, on rover station, finish remote transmission integrated of the collection of GPS observation data, processing, application and application data simultaneously from the base station;
Described PDA computer hardware, comprise display screen, be located at the display screen left and right sides button, be located at the suspension member of body top, and above host chip, bluetooth module and GPRS module, the built-in number of 400MHz dominant frequency of being located at body interior passes antennas and power supplys; Adopt whole-closed water-proof moisture-proof plastic-steel casing; The effective indication range of described display screen is not less than 80 * 80 (mm);
Described PDA built-in computer software comprises Data Receiving and modular converter, origin coordinate system transform module, database management module, the module of controlling and measure the smashed parts, design mould shape management system, exploration and inquiry module, construction survey module and geometric relationship detection module;
Wherein, Data Receiving and modular converter: to receive and be converted to the data layout of native system standard from the carrier phase difference baseline increment data of GPS-RTK mainboard and other data;
The origin coordinate system transform module: through the moonscope data of consolidation form, after obtaining a plurality of earth axes known control point coordinate, the coordinates computed conversion parameter, the WGS-84 coordinate conversion with rover station is the coordinate system coordinate at known control point place then;
Database management module: GPS-RTK coordinate survey data, field investigation, the data that design a model, authority data, system are provided with data etc., use file and ACCESS database mode to manage, quick retrieval modify feature is provided;
The control and the module of measuring the smashed parts: be used to use the GPS-RTK method to set up the inferior grade reference mark fast, measure the smashed parts and define pictorial information;
Design mould shape management system: be used to define, the three-dimensional geometric design model of modification and ground structure things such as management road, buildings, pipeline, railway and track engineering;
Exploration and inquiry module: be used to use the GPS-RTK instrument to carry out engineering survey and investigation;
Construction survey module: the surveying work that is used for engineering construction;
The geometric relationship detection module: use GPS-RTK equipment is finished the detection to any position geometric properties of engineering fast.
2. civil construction engineering GPS-RTK measurement integrated PDA device according to claim 1 is characterized in that: described suspension member is formed by linking up with and being linked with.
CN200710092931A 2007-10-31 2007-10-31 Civil construction engineering GPS-RTK measurement integrated PDA device Expired - Fee Related CN100580679C (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN200710092931A CN100580679C (en) 2007-10-31 2007-10-31 Civil construction engineering GPS-RTK measurement integrated PDA device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN200710092931A CN100580679C (en) 2007-10-31 2007-10-31 Civil construction engineering GPS-RTK measurement integrated PDA device

Publications (2)

Publication Number Publication Date
CN101158993A true CN101158993A (en) 2008-04-09
CN100580679C CN100580679C (en) 2010-01-13

Family

ID=39307094

Family Applications (1)

Application Number Title Priority Date Filing Date
CN200710092931A Expired - Fee Related CN100580679C (en) 2007-10-31 2007-10-31 Civil construction engineering GPS-RTK measurement integrated PDA device

Country Status (1)

Country Link
CN (1) CN100580679C (en)

Cited By (20)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101865664A (en) * 2010-05-18 2010-10-20 武汉大学 Portable dynamic deflection displacement measuring device and method
CN102168395A (en) * 2011-03-18 2011-08-31 中铁第一勘察设计院集团有限公司 Data integration processing method in designing and positioning-measurement of ballastless track layout
CN102235858A (en) * 2011-03-24 2011-11-09 广东省电力设计研究院 Coded real-time kinematic global positioning system (RTK-GPS) plane section measuring method and system
CN103162613A (en) * 2013-03-20 2013-06-19 中铁西南科学研究院有限公司 Personal digital assistant (PDA) tunnel convergence measuring system
CN103488156A (en) * 2013-10-11 2014-01-01 广州南方测绘仪器有限公司 Novel measurement controller and measurement control system
CN103926607A (en) * 2014-04-30 2014-07-16 内蒙古师范大学 Assigned distance locating, measuring and navigating method and device
CN104236522A (en) * 2014-09-01 2014-12-24 中国十七冶集团有限公司 Three-dimensional visualization measuring system
CN104536305A (en) * 2014-10-31 2015-04-22 广州市中海达测绘仪器有限公司 Control method and system of RTK measuring device
CN104849736A (en) * 2014-02-13 2015-08-19 黑龙江省水利科学研究院 Dam piping leakage inlet detection system with RTK technology
CN105375953A (en) * 2015-11-18 2016-03-02 深圳市华信天线技术有限公司 Wireless data transmission radio station and real-time kinematic (RTK) equipment
CN105544323A (en) * 2015-12-30 2016-05-04 中铁第四勘察设计院集团有限公司 Integrated processing method for designing, manufacturing and constructing track skeletons of medium and low speed magnetic aviation track
CN105973209A (en) * 2016-04-27 2016-09-28 西安科技大学 RTK lofting display device
CN107016064A (en) * 2017-03-16 2017-08-04 黎万恩 Global positioning satellite coordinate transformation system
CN107277847A (en) * 2017-08-11 2017-10-20 中邮科通信技术股份有限公司 A kind of antenna attitude measuring system and method based on NB IoT transmission modes
CN107992653A (en) * 2017-11-20 2018-05-04 上海华测导航技术股份有限公司 A kind of side slope setting-out system and side slope setting out method
CN109541644A (en) * 2018-11-16 2019-03-29 西安科技大学 A kind of RTK field operation synchronization skeletonizing method
CN109992558A (en) * 2019-03-26 2019-07-09 天水金思路工程咨询有限公司 A kind of device, method and calculator that highway engineering setting out data obtains
CN110398713A (en) * 2019-07-29 2019-11-01 相维(北京)科技有限公司 A method of receiver motion state is detected using wireless signal
CN110412631A (en) * 2019-08-13 2019-11-05 中电建十一局工程有限公司 A kind of linear engineering GPS speedy lofting construction method
CN113091716A (en) * 2021-04-25 2021-07-09 吴振华 Land planning equipment based on remote sensing and use method thereof

Cited By (27)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101865664A (en) * 2010-05-18 2010-10-20 武汉大学 Portable dynamic deflection displacement measuring device and method
CN101865664B (en) * 2010-05-18 2012-05-30 武汉大学 Portable dynamic deflection displacement measuring device and method
CN102168395A (en) * 2011-03-18 2011-08-31 中铁第一勘察设计院集团有限公司 Data integration processing method in designing and positioning-measurement of ballastless track layout
CN102168395B (en) * 2011-03-18 2012-11-07 中铁第一勘察设计院集团有限公司 Data integration processing method in designing and positioning-measurement of ballastless track layout
CN102235858A (en) * 2011-03-24 2011-11-09 广东省电力设计研究院 Coded real-time kinematic global positioning system (RTK-GPS) plane section measuring method and system
CN103162613A (en) * 2013-03-20 2013-06-19 中铁西南科学研究院有限公司 Personal digital assistant (PDA) tunnel convergence measuring system
CN103488156A (en) * 2013-10-11 2014-01-01 广州南方测绘仪器有限公司 Novel measurement controller and measurement control system
CN103488156B (en) * 2013-10-11 2017-02-01 广州南方测绘仪器有限公司 Novel measurement controller and measurement control system
CN104849736A (en) * 2014-02-13 2015-08-19 黑龙江省水利科学研究院 Dam piping leakage inlet detection system with RTK technology
CN103926607A (en) * 2014-04-30 2014-07-16 内蒙古师范大学 Assigned distance locating, measuring and navigating method and device
CN103926607B (en) * 2014-04-30 2017-06-16 内蒙古师范大学 Distance to a declared goal positioning measurement air navigation aid and device
CN104236522A (en) * 2014-09-01 2014-12-24 中国十七冶集团有限公司 Three-dimensional visualization measuring system
CN104236522B (en) * 2014-09-01 2016-08-17 中国十七冶集团有限公司 Three-dimensional visualization measures system
CN104536305A (en) * 2014-10-31 2015-04-22 广州市中海达测绘仪器有限公司 Control method and system of RTK measuring device
CN105375953A (en) * 2015-11-18 2016-03-02 深圳市华信天线技术有限公司 Wireless data transmission radio station and real-time kinematic (RTK) equipment
CN105544323A (en) * 2015-12-30 2016-05-04 中铁第四勘察设计院集团有限公司 Integrated processing method for designing, manufacturing and constructing track skeletons of medium and low speed magnetic aviation track
CN105544323B (en) * 2015-12-30 2017-09-26 中铁第四勘察设计院集团有限公司 The integral treatment method that the medium-and low-speed maglev track section of track manufactures and designs and constructed
CN105973209A (en) * 2016-04-27 2016-09-28 西安科技大学 RTK lofting display device
CN107016064A (en) * 2017-03-16 2017-08-04 黎万恩 Global positioning satellite coordinate transformation system
CN107277847A (en) * 2017-08-11 2017-10-20 中邮科通信技术股份有限公司 A kind of antenna attitude measuring system and method based on NB IoT transmission modes
CN107992653A (en) * 2017-11-20 2018-05-04 上海华测导航技术股份有限公司 A kind of side slope setting-out system and side slope setting out method
CN107992653B (en) * 2017-11-20 2021-12-31 上海华测导航技术股份有限公司 Slope lofting system and slope lofting method
CN109541644A (en) * 2018-11-16 2019-03-29 西安科技大学 A kind of RTK field operation synchronization skeletonizing method
CN109992558A (en) * 2019-03-26 2019-07-09 天水金思路工程咨询有限公司 A kind of device, method and calculator that highway engineering setting out data obtains
CN110398713A (en) * 2019-07-29 2019-11-01 相维(北京)科技有限公司 A method of receiver motion state is detected using wireless signal
CN110412631A (en) * 2019-08-13 2019-11-05 中电建十一局工程有限公司 A kind of linear engineering GPS speedy lofting construction method
CN113091716A (en) * 2021-04-25 2021-07-09 吴振华 Land planning equipment based on remote sensing and use method thereof

Also Published As

Publication number Publication date
CN100580679C (en) 2010-01-13

Similar Documents

Publication Publication Date Title
CN100580679C (en) Civil construction engineering GPS-RTK measurement integrated PDA device
CN101901244B (en) Geological geographic information system processing method
Pan et al. 3D scene and geological modeling using integrated multi-source spatial data: Methodology, challenges, and suggestions
CN109871648B (en) The construction method of groundwater resources three-dimensional visualization dynamic monitoring structural model
CN103234519A (en) Land subsidence monitoring and early warning system based on global position system (GPS) and hydrostatic leveling
CN103699634A (en) Database creation method and database creation system for one-stop pipeline detection
CN106703086A (en) Online security monitoring system for foundation pit
CN103021137B (en) Surface displacement method high slope stability remote three-dimensional digital warning method and system
CN101906771A (en) Three-dimensional soil texture analyzing method for assisting survey, design and construction of dredging engineering
CN107514022A (en) A kind of bull-dozer guides system
CN113989431A (en) Construction method of three-dimensional visual dynamic monitoring structure model of underground water resource
CN113513052A (en) BDS + BIM-based intelligent foundation pit monitoring system and method
KR100877073B1 (en) Device for surveying pipe and method for surveying pipe using the same and system for surveying pipe using the same
Fengyun et al. Status and development trend of 3D laser scanning technology in the mining field
CN201622567U (en) Geological and geographic information system
CN217845170U (en) Automatic settlement monitoring system
CN116429070A (en) Water resource investigation method and system for coal mining subsidence water accumulation area
CN110717233A (en) Rainwater pipe network flow calculation method and system based on GIS underlying surface analysis
CN206726211U (en) A kind of GIS data harvester
KR100481066B1 (en) Method and apparatus for managing a facility using electronic signal
CN105717517A (en) Vehicle-mounted Beidou multi-mode GNSS high-precision road basic data collection method
CN101806591A (en) Three-dimensional displacement monitoring method for landslide mass
KR101591285B1 (en) Geological survey system using personal portable device and geological survey method using thereof
Yu et al. Research on the automatic monitoring system for coal mining subsidence
CN101515283A (en) Oil field geographical information system

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20100113

Termination date: 20101031