CN103887682A - Clamp for realizing slotted center conductor precision centering closing and closing method - Google Patents

Clamp for realizing slotted center conductor precision centering closing and closing method Download PDF

Info

Publication number
CN103887682A
CN103887682A CN201310669738.2A CN201310669738A CN103887682A CN 103887682 A CN103887682 A CN 103887682A CN 201310669738 A CN201310669738 A CN 201310669738A CN 103887682 A CN103887682 A CN 103887682A
Authority
CN
China
Prior art keywords
closing
shaping cover
center conductor
centring means
shaping
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201310669738.2A
Other languages
Chinese (zh)
Other versions
CN103887682B (en
Inventor
霍建东
路波
赵秉玉
郑如松
张强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CETC 41 Institute
Original Assignee
CETC 41 Institute
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CETC 41 Institute filed Critical CETC 41 Institute
Priority to CN201310669738.2A priority Critical patent/CN103887682B/en
Publication of CN103887682A publication Critical patent/CN103887682A/en
Application granted granted Critical
Publication of CN103887682B publication Critical patent/CN103887682B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The invention provides a clamp for realizing slotted center conductor precision centering closing and a closing method. The method comprises the following steps: step 101: a modeling sleeve and a centering device are processed; step 102: centering closing is performed on a slotted center conductor by using the modeling sleeve and the centering device; step 103: aging heat treatment modeling is performed on the combined modeling sleeve, the centering device and the slotted center conductor; and step 104: the modeling sleeve and the centering device are removed and a final component is acquired. With adoption of the aforementioned scheme, centering and precision closing are completed simultaneously so that closing precision, roundness and coaxiality are ensured to meet design requirements. Meanwhile, consistency of closing quality is enhanced and production efficiency is enhanced.

Description

A kind of fixture and closing method of realizing the accurate centering closing in of fluting center conductor
Technical field
The invention belongs to microwave coaxial transmission line manufacture technology field, in particular a kind of fixture and closing method of realizing the accurate centering closing in of fluting center conductor.
Background technology
The center conductor of microwave signal transmission channel is generally divided into a sun center conductor and a cloudy center conductor (center conductor of slotting), along with the development of technology, frequency test signal improves constantly, require the center conductor size in connector more and more less, required precision is also more and more higher, and the closing in of fluting center conductor and setting process are the key process technology of producing the high-performance fluting center conductor that meets designing requirement, closing in precision, axiality and the out of roundness of closing in conductor directly have influence on the core capabilities index of product.
The bottling technique of the cloudy center conductor of existing fluting, what mostly adopt is the manual mode closing up, to be operating personnel directly act on fluting center conductor with the instrument such as tweezers, steel wire makes its distortion reach closing in, then part is placed in to equipment for Heating Processing and carries out ageing strengthening sizing.
Except manual closing in mode, also there is in recent years utilizing mould the close up technical scheme of sizing of center conductor of slotting, the cross sectional shape of mould is bellmouth, when closing in, directly fluting center conductor is directly pressed into bellmouth, after utilizing the closing in of inner surface cross-notching center conductor of bellmouth, profile positions setting, carries out afterwards timeliness heat treatment.
The subject matter that manual closing method exists is: center conductor size is less, manual operations trouble, and production efficiency is low; Easily cause hole lobe distortion, product yields is low; Closing in low precision, after closing up, cross section out of roundness and axiality are difficult to ensure; Product quality is affected by people's destabilizing factor to be difficult to there is good consistency, to cause performance index and poor stability.
Existing utilize mould slot center conductor close up sizing technical scheme in, when fluting center conductor is directly pressed into bellmouth, must guarantee that four hole lobes of jack contact just, formation a sealing annular.But in existing scheme, do not have any measure to ensure this effect, ensure equally by operating personnel's experience, in actual production, normal appearance causes part hole lobe excessive to internal strain because being pressed into tension, causes fluting conductor to scrap; Or conductor is pressed into out of plumb and causes contracting eccentric, directly affect connector axiality and out of roundness index; Or fluting conductor is pressed into quantity not sufficient and causes in poor harvestly mouthful, and then cause contact engaging and separating force and connect-disconnect life not to meet design requirement.
Therefore, there is defect in prior art, needs to improve.
Summary of the invention
Technical problem to be solved by this invention is for the deficiencies in the prior art, and a kind of fixture and closing method that the accurate centering of fluting center conductor is closed up of realizing is provided.
Technical scheme of the present invention is as follows:
Realize fixture and a closing method that the accurate centering of fluting center conductor is closed up, wherein, comprise the following steps:
Step 101: Precision Machining shaping cover and centring means;
Step 102: use the closing in of feeling relieved of shaping cover and centring means cross-notching center conductor;
Step 103: shaping cover, centring means and fluting center conductor after combination are carried out to timeliness heat treatment shaping;
Step 104: take off shaping cover and centring means, obtain final part.
Fixture and closing method that the described accurate centering of realization fluting center conductor is closed up, wherein, in described step 101, Precision Machining shaping cover and centring means comprise: select metal material to process; Shaping cover and centring means size cooperatively interact, centring means entirety can closely be encased in shaping cover, the final size of internal diameter after conductor closing in centered by centring means outside dimension, the final size of external diameter after conductor closing in centered by the conical lower portion internal diameter size of shaping cover;
Fixture and closing method that the described accurate centering of realization fluting center conductor is closed up, wherein, in described step 102, use the feel relieved method of closing in of shaping cover and centring means cross-notching center conductor to be: centring means and shaping cover are fitted together to formation built-up jig, then steadily pack vertically fluting center conductor into built-up jig, while packing center conductor into, can under the prerequisite of not destroying workpiece, try one's best to strengthen and press-fit dynamics, can not cause hole lobe distortion or eccentric, and be precision centering and closing in state while packing shaping cover conical lower portion into;
Fixture and closing method that the described accurate centering of realization fluting center conductor is closed up, wherein, in described step 103, shaping cover, centring means and fluting center conductor after combination are heat-treated as the three after combination is positioned over and in vacuum heat treatment equipment, carried out 320 degrees Celsius and be incubated the ageing strengthening heat treatment shaping of 2 hours.;
Fixture and closing method that the described accurate centering of realization fluting center conductor is closed up, wherein, in described step 104, the method of taking off shaping cover and centring means is, heat treated assembly is naturally cooled to normal temperature, then part is taken off from built-up jig, built-up jig is reusable.
Adopt such scheme, the technological means that can improve at present open and application is without centering means and lack the present situation of the indicatory device that is press-fit into place, then solve the problem that closing in precision is low, axiality out of roundness is poor and closing in quality conformance is poor that existing method causes, realized centering completes with accurate closing in simultaneously, ensure that closing in precision, out of roundness and axiality meet designing requirement, improve the consistency of closing in quality simultaneously, and enhance productivity, built-up jig apparatus structure is simply easy to produce and can repeatedly reuse, and economic and social benefit is obvious.
Brief description of the drawings
Fig. 1 is closing method flow chart of the present invention.
Fig. 2 is the shaping cover process schematic representation in the inventive method step 101.
Fig. 3 is the shaping equipment process schematic representation in the inventive method step 101.
Fig. 4 is the fluting center conductor process schematic representation before closing up in the inventive method step 102.
Fig. 5 realizes the process schematic representation that centering is closed up in the inventive method step 102.
Fig. 6 is the process schematic representation of the inventive method step 103.
Fig. 7 is the process schematic representation of the inventive method step 104.
Embodiment
Below in conjunction with the drawings and specific embodiments, the present invention is described in detail.
Embodiment 1
As shown in Figure 1, a kind of fixture and closing method flow chart that the accurate centering of fluting center conductor is closed up of realizing provided by the invention, the method comprises the following steps:
Step 101: Precision Machining shaping cover and centring means;
Step 102: use the closing in of feeling relieved of shaping cover and centring means cross-notching center conductor;
Step 103: shaping cover, centring means and fluting center conductor after combination are carried out to timeliness heat treatment shaping;
Step 104: take off shaping cover and centring means, obtain final part.
In above-mentioned steps 101, Precision Machining shaping cover and centring means comprise: select metal material to process; Shaping cover and centring means size cooperatively interact, centring means entirety can closely be encased in shaping cover, the final size of internal diameter after conductor closing in centered by centring means outside dimension, the final size of external diameter after conductor closing in centered by the conical lower portion internal diameter size of shaping cover;
In above-mentioned steps 102, use the feel relieved method of closing in of shaping cover and centring means cross-notching center conductor to be: centring means and shaping cover are fitted together to formation built-up jig, then steadily pack vertically fluting center conductor into built-up jig, while packing center conductor into, can under the prerequisite of not destroying workpiece, try one's best to strengthen and press-fit dynamics, can not cause hole lobe distortion or eccentric, and be precision centering and closing in state while packing shaping cover conical lower portion into;
In above-mentioned steps 103, shaping cover, centring means and fluting center conductor after combination are heat-treated as the three after combination is positioned over and in vacuum heat treatment equipment, carried out 320 degrees Celsius and be incubated the ageing strengthening heat treatment shaping of 2 hours;
In above-mentioned steps 104, the method for taking off shaping cover and centring means is, heat treated assembly is naturally cooled to normal temperature, then part taken off from built-up jig, and built-up jig is reusable.
Based on of the present invention a kind of fixture and the closing method flow chart of realizing the accurate centering closing in of fluting center conductor described in Fig. 1, below in conjunction with specific embodiment, the present invention is described in further detail.
In the present embodiment, a kind of fixture and closing method of realizing the accurate centering closing in of fluting center conductor, further illustrate detailed process method of the present invention and step below in conjunction with concrete process schematic representation, Fig. 2-Fig. 7 is a kind of fixture and closing method process chart that the accurate centering of fluting center conductor is closed up of realizing provided by the invention.
As shown in Figure 2 and Figure 3, be precision machined shaping cover 5 and centring means 6, both cooperatively interact at size, and centring means 6 entirety can closely be encased in shaping cover 5; The final size of internal diameter after conductor closing in centered by centring means 6 outside dimension Φ D, the final size of external diameter after conductor closing in centered by the conical lower portion internal diameter Φ B of shaping cover 5.
As shown in Figure 4, be the fluting center conductor 7 before closing up, Φ E is the outside dimension before closing up, size Φ E is slightly less than size Φ C.
As shown in Figure 5, for centring means 6 is pressed into formation built-up jig from the right-hand member of shaping cover 5, the fluting center conductor 7 before closing up steadily packed into and is press-fit into place from the left end of shaping cover 5, realizing centering and close up.
As shown in Figure 6, carry out timeliness heat treatment for the three after assembling is put into equipment for Heating Processing 8, the sizing of center conductor closing in position makes to slot.
As shown in Figure 7, for taking off the fluting center conductor 9 of the final form of acquisition after naturally cooling to shaping cover 5 and centring means 6, Φ B is the outside dimension after closing up, and shaping cover 5 is reusable with centring means 6.
Should be understood that, for those of ordinary skills, can be improved according to the above description or convert, and all these improvement and conversion all should belong to the protection range of claims of the present invention.

Claims (6)

1. realize the fixture that the accurate centering of fluting center conductor is closed up, it is characterized in that, fixture is made up of shaping cover and centring means two parts; Described centring means entirety can closely be encased in shaping cover; The final size of internal diameter after conductor closing in centered by described centring means outside dimension, the final size of external diameter after conductor closing in centered by the conical lower portion internal diameter size of shaping cover.
2. realize the closing method that the accurate centering of fluting center conductor is closed up, it is characterized in that, comprise the following steps:
Step 101: processing shaping cover and centring means;
Step 102: use the closing in of feeling relieved of shaping cover and centring means cross-notching center conductor;
Step 103: shaping cover, centring means and fluting center conductor after combination are carried out to timeliness heat treatment shaping;
Step 104: take off shaping cover and centring means, obtain final part.
3. closing method as claimed in claim 2, is characterized in that, the concrete steps of described step 101 are: select metal material to process, shaping cover size and centring means size cooperatively interact; Described centring means entirety can closely be encased in shaping cover; The final size of internal diameter after conductor closing in centered by described centring means outside dimension, the final size of external diameter after conductor closing in centered by the conical lower portion internal diameter size of shaping cover.
4. closing method as claimed in claim 2, it is characterized in that, the concrete steps of described step 102 are: centring means and shaping cover are fitted together to formation built-up jig, fluting center conductor before closing up is steadily packed into and is press-fit into place from the left end of shaping cover, realize centering and close up, and pack shaping cover conical lower portion into.
5. closing method as claimed in claim 2, it is characterized in that, the concrete steps of described step 103 are: shaping cover, centring means and fluting center conductor after combination are positioned over and in vacuum heat treatment equipment, carry out 320 degrees Celsius and be incubated the ageing strengthening heat treatment shaping of 2 hours.
6. closing method as claimed in claim 2, is characterized in that, the concrete steps of described step 104 are: heat treated assembly is naturally cooled to normal temperature, then part is taken off from built-up jig.
CN201310669738.2A 2013-12-10 2013-12-10 A kind of fixture and closing method of realizing the accurate centering closing in of fluting center conductor Expired - Fee Related CN103887682B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310669738.2A CN103887682B (en) 2013-12-10 2013-12-10 A kind of fixture and closing method of realizing the accurate centering closing in of fluting center conductor

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310669738.2A CN103887682B (en) 2013-12-10 2013-12-10 A kind of fixture and closing method of realizing the accurate centering closing in of fluting center conductor

Publications (2)

Publication Number Publication Date
CN103887682A true CN103887682A (en) 2014-06-25
CN103887682B CN103887682B (en) 2016-05-25

Family

ID=50956464

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310669738.2A Expired - Fee Related CN103887682B (en) 2013-12-10 2013-12-10 A kind of fixture and closing method of realizing the accurate centering closing in of fluting center conductor

Country Status (1)

Country Link
CN (1) CN103887682B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104979670A (en) * 2015-07-14 2015-10-14 乐清市神创电气科技有限公司 Cylindrical plug bush and production method
CN112421343A (en) * 2020-11-09 2021-02-26 中国电子科技集团公司第四十研究所 Closing-in clamp for conductor in slotted groove of radio frequency coaxial connector

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4614029A (en) * 1984-04-05 1986-09-30 Otto Dunkel Gmbh Fabrik Fur Elektrontechnische Gerate Method of manufacturing contact spring sockets
CN201355743Y (en) * 2008-10-16 2009-12-02 上海华伦仪表电子有限公司 Forming mold of jacks of connector
CN102347581A (en) * 2011-09-16 2012-02-08 贵州航天电子科技有限公司 Heat treatment process for jack of electric connector
CN202977951U (en) * 2012-08-07 2013-06-05 贵州航天电子科技有限公司 Hot shell nosing tool for electric connector jack

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4614029A (en) * 1984-04-05 1986-09-30 Otto Dunkel Gmbh Fabrik Fur Elektrontechnische Gerate Method of manufacturing contact spring sockets
CN201355743Y (en) * 2008-10-16 2009-12-02 上海华伦仪表电子有限公司 Forming mold of jacks of connector
CN102347581A (en) * 2011-09-16 2012-02-08 贵州航天电子科技有限公司 Heat treatment process for jack of electric connector
CN202977951U (en) * 2012-08-07 2013-06-05 贵州航天电子科技有限公司 Hot shell nosing tool for electric connector jack

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104979670A (en) * 2015-07-14 2015-10-14 乐清市神创电气科技有限公司 Cylindrical plug bush and production method
CN112421343A (en) * 2020-11-09 2021-02-26 中国电子科技集团公司第四十研究所 Closing-in clamp for conductor in slotted groove of radio frequency coaxial connector

Also Published As

Publication number Publication date
CN103887682B (en) 2016-05-25

Similar Documents

Publication Publication Date Title
CN103624497A (en) Method for machining large-radius thin-wall semi-annular part
CN103894539B (en) A kind of method preparing monocrystalline spiral crystal selector wax-pattern
MY159030A (en) Green compact, method of manufacturing the same, and core for reactor
CN103887682A (en) Clamp for realizing slotted center conductor precision centering closing and closing method
CN103214191B (en) Microsphere lens pipe cap manufacture craft and this microsphere lens pipe cap
CN205519648U (en) Production mould of E -shaped magnetic cores blank
CN204981590U (en) Sulphur is glass mould pressing mould
CN103736895A (en) Steel tube opening right-angle flanging die and forging and forming method thereof
CN103350328A (en) Fragmentation processing and manufacturing process for end socket
CN116344186A (en) Method for manufacturing integrated patch type power inductor
CN103682946B (en) A kind of two groove center conductor precision centering closing in fixtures
CN202268786U (en) Final shaping die of motor stator
CN205266790U (en) Mooncake die
CN203931744U (en) A kind of big column metal magnetic powder core
CN203674930U (en) Drill jig for motor support end cap
CN203932432U (en) A kind of low cost radio frequency coaxial cable connector housing
CN204088716U (en) A kind of low cost radio frequency coaxial cable connector housing
CN204844640U (en) Major diameter cluster parachute silicon rubber moulding mould
CN102360800B (en) Winding method and structure for transformer, and transformer
CN103885124A (en) Machining technology of optical collimator
CN105127432A (en) Preparation method of graded cemented carbide
CN203711842U (en) Powder metallurgy die
CN103878289A (en) Die forging method of horizontal H-shaped step shaft
CN204747424U (en) Strainer valve psammitolite
CN104174651A (en) Stainless steel pipe thickening process

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20160525

Termination date: 20171210