CN105629935A - Dispatching voice reporting system for power plant - Google Patents

Dispatching voice reporting system for power plant Download PDF

Info

Publication number
CN105629935A
CN105629935A CN201610081826.4A CN201610081826A CN105629935A CN 105629935 A CN105629935 A CN 105629935A CN 201610081826 A CN201610081826 A CN 201610081826A CN 105629935 A CN105629935 A CN 105629935A
Authority
CN
China
Prior art keywords
power
power plant
field data
user
data
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610081826.4A
Other languages
Chinese (zh)
Other versions
CN105629935B (en
Inventor
娄亮
董林
王强
王文刚
于立涛
罗鲁东
吴文涛
汤元超
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Qingdao Power Supply Co of State Grid Shandong Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
Qingdao Power Supply Co of State Grid Shandong Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, Qingdao Power Supply Co of State Grid Shandong Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201610081826.4A priority Critical patent/CN105629935B/en
Publication of CN105629935A publication Critical patent/CN105629935A/en
Application granted granted Critical
Publication of CN105629935B publication Critical patent/CN105629935B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G05CONTROLLING; REGULATING
    • G05BCONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS
    • G05B19/00Programme-control systems
    • G05B19/02Programme-control systems electric
    • G05B19/418Total factory control, i.e. centrally controlling a plurality of machines, e.g. direct or distributed numerical control [DNC], flexible manufacturing systems [FMS], integrated manufacturing systems [IMS], computer integrated manufacturing [CIM]
    • G05B19/41865Total factory control, i.e. centrally controlling a plurality of machines, e.g. direct or distributed numerical control [DNC], flexible manufacturing systems [FMS], integrated manufacturing systems [IMS], computer integrated manufacturing [CIM] characterised by job scheduling, process planning, material flow
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/02Total factory control, e.g. smart factories, flexible manufacturing systems [FMS] or integrated manufacturing systems [IMS]
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S10/00Systems supporting electrical power generation, transmission or distribution
    • Y04S10/50Systems or methods supporting the power network operation or management, involving a certain degree of interaction with the load-side end user applications

Abstract

The invention discloses a dispatching voice reporting method and system for a power plant, and the method comprises the steps: 1, receiving an access request of a user, verifying a user serial number and a log password and then enabling the user to log; 2, carrying out the voice reminding of the user of inputting onsite data of the power plant; 3, judging whether the onsite data of the power plant accords with a preset locking condition or not: carrying out the voice reminding of the user of returning to step 2 to input the onsite data of the power plant again if the onsite data of the power plant does not accord with the preset locking condition; 4, carrying out the voice reminding of the user of confirming the onsite data of the power plant according with the preset locking condition or returning to step 2 to input the onsite data of the power plant again; 5, enabling the above confirmed onsite data of the power plant to be stored. The method and system solves technical problems that a power plant without being covered by an enterprise Intranet cannot achieve the reporting of onsite data timely and accurately in the prior art.

Description

Power plant's schedule voice declaration system
The application is divisional application, and parent application number is 201410351712.8, and the applying date is 2014-7-23.
Technical field
The present invention relates to power scheduling technical field, particularly relate to power plant's schedule voice declaration method and system.
Background technology
The upper proposition of State Grid Corporation of China's 2010 " two Conferences " " three collection five are big " (human resources, finance, material intensive management, huge construction program, greatly construction, big operation, big production, big marketing system construction). " adjust, join, control integration ", as the important embodiment of " running greatly ", is a kind of Regulation pattern carried out energetically in current national grid system. Integration management and running embody emphatically the efficient of intelligent grid, and it relates to the longitudinal direction interconnection of the standardization of control centre and specialized management, lean and indexing management and control centre, are control centre's windows of externally providing types of functionality and data, services.
" adjust, join, control integration " relates to two class business, namely the emergency processing to the properly functioning control of electrical network with to accident improve control room to power system operating mode, equipment running status, send out power supply plan and the control ability of electrical network overall process, specialty comprehensive, complete; Improve the disposal ability to accidents such as anomalous weather, external force destruction, system fluctuations.
" adjust, join, control integration " system achieves the centralization of management and running height, and automated system proposes new requirement simultaneously. Along with the deep propelling of " running greatly " System Construction, in order to ensure that new system runs well, it is necessary to the informatization platform of electrical network is improved. The little thermoelectricity of part (little thermoelectricity typically refers to 50,000 kilowatts and following thermoelectricity is main oil burning boiler and generating set) enterprise is because enterprise's existing network condition limits without the covering realizing Intranet, it is impossible to carries out data by inner-mesh network and reports in real time
It is thus desirable to set up the information system of a set of intelligence, declare in time realizing little thermoelectricity field data, promote regulation and control operation level, and then improve power grid security and stability. Traditional information system can not prevent little thermoelectricity field data from declaring user misoperation in process, thus it is inaccurate to cause related data to declare, these inaccurate data store in data base, it is necessary to undertaken auditing and revising by manual type, waste time and energy, affect power plant's traffic control efficiency.
Summary of the invention
For this, the technical problem to be solved is in that prior art cannot be implemented without the power plant that corporate intranet covers and field data is declared accurately and in time, thus proposing a kind of power plant's schedule voice declaration method and system to solve this problem.
For solving above-mentioned technical problem, the present invention by the following technical solutions:
A kind of power plant schedule voice declaration method, comprises the following steps: step 1, receive the access request of user, and checking Customs Assigned Number and login password are followed by access customer; Step 2, voice message user input power plant's field data; Step 3, judge whether described power plant field data meets the barring condition of setting, do not meet barring condition then voice message user and return step 2 and re-enter power plant's field data; The power plant's field data meeting barring condition is confirmed or returns step 2 to re-enter power plant's field data by step 4, voice message user; Step 5, by above-mentioned through user confirm power plant's field data store.
As the further improvement of power plant's schedule voice declaration method of the present invention, described power plant field data includes: power minimum load, power maximum load, start power capacity, generated energy and electricity volume.
Further improvement as power plant's schedule voice declaration method of the present invention, described barring condition is: electricity volume generated energy, and power minimum load < power maximum load start power capacity, and 2.4 times power minimum load < generated energy < 2.4 times power maximum loads.
As the further improvement of power plant's schedule voice declaration method of the present invention, described barring condition is: 2.4 times power minimum load < generated energy < 2.4 times power maximum loads.
As the further improvement of power plant's schedule voice declaration method of the present invention, described barring condition is: electricity volume generated energy.
As the further improvement of power plant's schedule voice declaration method of the present invention, described barring condition is: power minimum load < power maximum load start power capacity.
As the further improvement of power plant's schedule voice declaration method of the present invention, further comprising the steps of after step 5: power plant's field data of storage is audited.
As the further improvement of power plant's schedule voice declaration method of the present invention, also the power plant's field data after examination & verification is reported higher level's thread.
As the further improvement of power plant's schedule voice declaration method of the present invention, further comprising the steps of after step 5: power plant's field data of storage is collected displaying.
Based on same inventive concept, the present invention also proposes a kind of power plant schedule voice declaration system, including: user's access unit, for receiving the access request of user, checking Customs Assigned Number and login password are followed by access customer; Input block, inputs power plant's field data for voice message user; Locking unit, for judging whether described power plant field data meets the barring condition of setting, does not meet barring condition then voice message user and returns input block and re-enter power plant's field data; Confirmation unit, confirms or returns input block to re-enter power plant's field data to the power plant's field data meeting barring condition for voice message user; Memory element, for storing the above-mentioned power plant's field data confirmed through user.
As the further improvement of power plant's schedule voice declaration system of the present invention, described power plant field data includes: power minimum load, power maximum load, start power capacity, generated energy and electricity volume.
As the further improvement of power plant's schedule voice declaration system of the present invention, described barring condition is: power minimum load < power maximum load start power capacity.
As the further improvement of power plant's schedule voice declaration system of the present invention, described barring condition is: 2.4 times power minimum load < generated energy < 2.4 times power maximum loads.
As the further improvement of power plant's schedule voice declaration system of the present invention, described barring condition is: electricity volume generated energy.
Further improvement as power plant's schedule voice declaration system of the present invention, described barring condition is: electricity volume generated energy, and, power minimum load < power maximum load start power capacity, and 2.4 times power minimum load < generated energy < 2.4 times power maximum loads.
As the further improvement of power plant's schedule voice declaration system of the present invention, also include examination & verification unit, for power plant's field data of storage is audited.
As the further improvement of power plant's schedule voice declaration system of the present invention, also include reporting element, for the power plant's field data after examination & verification is reported higher level's thread.
As the further improvement of power plant's schedule voice declaration system of the present invention, also include collection unit, for power plant's field data of storage is collected displaying.
The technique scheme of the present invention has the advantage that compared to existing technology
1, a kind of power plant schedule voice declaration method of the present invention and system, owing to comprising the following steps: step 1, receive the access request of user, checking Customs Assigned Number and login password are followed by access customer; Step 2, voice message user input power plant's field data; Step 3, judge whether described power plant field data meets the barring condition of setting, do not meet barring condition then voice message user and return step 2 and re-enter power plant's field data; The power plant's field data meeting barring condition is confirmed or returns step 2 to re-enter power plant's field data by step 4, voice message user; Step 5, by above-mentioned through user confirm power plant's field data store. The barring condition set is possible to prevent little thermoelectricity field data to declare user misoperation in process, it is ensured that data declaration is accurate, it is to avoid inaccurate data store in data base, thus improving power plant's traffic control efficiency.
2, a kind of power plant schedule voice declaration method of the present invention and system, described power plant field data includes: power minimum load, power maximum load, start power capacity, generated energy and electricity volume, described barring condition is: electricity volume generated energy, and power minimum load < power maximum load start power capacity, and 2.4 times power minimum load < generated energy < 2.4 times power maximum loads. So can be prevented effectively from declares in process in power plant's field data, the electricity volume of appearance > generated energy, power minimum load >=power maximum load, power minimum load >=start power capacity, power maximum load > apparent error that causes of power capacity and the data unit mistake etc. of starting shooting data declaration person's maloperation. Data error rate is reduced to less than 5.12% by 21.33%. Simultaneously, when power plant's field data of input meets 2.4 times power minimum load < generated energy < 2.4 times power maximum load barring condition simultaneously, other are not that the data error rate that artificial origin causes is significantly reduced, such as, the wrong data caused due to reasons such as electric instruments when checking meter at the scene significantly reduces. By long-time statistical observation, data error rate is 0, achieves unexpected technique effect.
Accompanying drawing explanation
In order to make present disclosure be more likely to be clearly understood, below according to specific embodiments of the invention and in conjunction with accompanying drawing, the present invention is further detailed explanation, wherein
Fig. 1 is a kind of power plant schedule voice declaration method schematic diagram of the embodiment of the present invention 1;
Fig. 2 is a kind of small coal power plants schedule voice declaration method flow chart of the embodiment of the present invention 2.
Detailed description of the invention
Embodiment 1
Fig. 1 illustrates a kind of power plant schedule voice declaration method of the embodiment of the present invention, comprises the following steps:
Step 1, access user. Receiving the access request of user, checking Customs Assigned Number and login password are followed by access customer.
Step 2, input power plant field data. Power plant's field data is inputted by voice message user. Described power plant field data includes: power minimum load, power maximum load, start power capacity, generated energy and electricity volume.
Step 3, judge whether data meet barring condition. Judge whether described power plant field data meets the barring condition of setting, described barring condition is: electricity volume generated energy, and power minimum load < power maximum load start power capacity, and 2.4 times power minimum load < generated energy < 2.4 times power maximum loads. Meet barring condition and then perform step 4; Do not meet barring condition then voice message user to return step 2 and re-enter power plant's field data.
So can be prevented effectively from declares in process in power plant's field data, the electricity volume of appearance > generated energy, power minimum load >=power maximum load, power minimum load >=start power capacity, power maximum load > apparent error that causes of power capacity and the data unit mistake etc. of starting shooting data declaration person's maloperation. Data error rate is reduced to less than 5.12% by 21.33%. Simultaneously, when power plant's field data of input meets 2.4 times power minimum load < generated energy < 2.4 times power maximum load barring condition simultaneously, other are not that the data error rate that artificial origin causes is significantly reduced, such as, the wrong data caused due to reasons such as electric instruments when checking meter at the scene significantly reduces. By long-time statistical observation, data error rate is 0, achieves unexpected technique effect.
As other embodiment, described barring condition is: power minimum load < power maximum load start power capacity.
As other embodiment, described barring condition is: 2.4 times power minimum load < generated energy < 2.4 times power maximum loads.
As other embodiment, described barring condition is: electricity volume generated energy.
Step 4, confirmation data. The power plant's field data meeting barring condition is confirmed by voice message user, confirms then to carry out step 5; Re-enter, return step 2 and re-enter power plant's field data.
Step 5, storage power plant field data. The above-mentioned power plant's field data confirmed through user is stored.
As the preferred implementation of a kind of power plant schedule voice declaration method of the embodiment of the present invention, further comprising the steps of after step 5: power plant's field data of storage is audited, and the power plant's field data after examination & verification is reported higher level's thread.
As the preferred implementation of a kind of power plant schedule voice declaration method of the embodiment of the present invention, further comprising the steps of after step 5: power plant's field data of storage is collected displaying.
Embodiment 2
Fig. 2 illustrates a kind of small coal power plants schedule voice declaration method of the embodiment of the present invention.
First, the data declaration person of small coal power plants dials and declares telephone number, and voice message after connection " welcomes to use little thermoelectricity Data-phone declaration system, please input Customs Assigned Number, terminate with # key ". Such as, data declaration person inputs Customs Assigned Number " 001# ", if this numbering is absent from, voice message " you are absent from by the Customs Assigned Number of input; please re-enter Customs Assigned Number; terminate with # key ", if numbering exists, voice message " login password please be input, terminate with # key " further. Such as, data declaration person inputs login password " * * * * * * # ", if code error, voice message " Password Input mistake please be re-entered, terminate with # key ", if Password Input is correct, then logins successfully.
After logining successfully, voice message " declaration data please by 1, exits, please hang up ", after data declaration person's input " 1 ", voice message " please input generated energy, terminate with # key ", for instance data declaration person inputs " 1036.28 ".
Judge whether the generated energy of input meets the barring condition of setting: electricity volume generated energy, and power minimum load < power maximum load start power capacity, and 2.4 times power minimum load < generated energy < 2.4 times power maximum loads. If do not met, then " sorry, your input is wrong in voice message! Please re-enter ", data declaration person returns and re-enters generated energy.
If met, then further voice message " your typing is: 1036.28, confirms, please by 1, re-enters, please by 2 ", if to input generated energy incorrect for data declaration person, then by 2 returns, re-enter; If it is correct that data declaration person inputs generated energy, then confirm by 1. After data declaration person presses 1, voice message " please input electricity volume, terminate with # key ", for instance data declaration person inputs " 964.14 ".
Judge whether the electricity volume of input meets the barring condition of setting: electricity volume generated energy, and power minimum load < power maximum load start power capacity, and 2.4 times power minimum load < generated energy < 2.4 times power maximum loads. If do not met, then " sorry, your input is wrong in voice message! Please re-enter ", data declaration person returns and re-enters electricity volume.
If met, then further voice message " your typing is: 964.14, confirms, please by 1, re-enters, please by 2 ", if to input electricity volume incorrect for data declaration person, then by 2 returns, re-enter; If it is correct that data declaration person inputs electricity volume, then confirm by 1. After data declaration person presses 1, voice message " asks input power minimum load, terminate with # key ", for instance data declaration person inputs " 102.56 ".
Judge whether the power minimum load of input meets the barring condition of setting: electricity volume generated energy, and power minimum load < power maximum load start power capacity, and 2.4 times power minimum load < generated energy < 2.4 times power maximum loads. If do not met, then " sorry, your input is wrong in voice message! Please re-enter ", data declaration person returns and re-enters power minimum load.
If met, then voice message further " your typing is: 102.56, confirms, please by 1, re-enters, please by 2 ", if data declaration person's input power minimum load is incorrect, then by 2 returns, re-enter; If data declaration person's input power minimum load is correct, then confirm by 1. After data declaration person presses 1, voice message " asks input power maximum load, terminate with # key ", for instance data declaration person inputs " 505.43 ".
Judge whether the power maximum load of input meets the barring condition of setting: electricity volume generated energy, and power minimum load < power maximum load start power capacity, and 2.4 times power minimum load < generated energy < 2.4 times power maximum loads. If do not met, then " sorry, your input is wrong in voice message! Please re-enter ", data declaration person returns and re-enters power maximum load.
If met, then voice message further " your typing is: 505.43, confirms, please by 1, re-enters, please by 2 ", if data declaration person's input power maximum load is incorrect, then by 2 returns, re-enter; If data declaration person's input power maximum load is correct, then confirm by 1. After data declaration person presses 1, voice message " please input start power capacity, terminate with # key ", for instance data declaration person inputs " 665.64 "
Judge whether the start power capacity of input meets the barring condition of setting: electricity volume generated energy, and power minimum load < power maximum load start power capacity, and 2.4 times power minimum load < generated energy < 2.4 times power maximum loads. If do not met, then " sorry, your input is wrong in voice message! Please re-enter ", data declaration person returns and re-enters start power capacity.
If met, then voice message further " your typing is: 505.43, confirms, please by 1, re-enters, please by 2 ", if data declaration person inputs start, power capacity is incorrect, then by 2 returns, re-enter; If data declaration person inputs start, power capacity is correct, then confirm by 1.
After data declaration person presses 1, enter operating database flow process, the above-mentioned small coal power plants field data confirmed through data declaration person stored, and voice message " operates successful! Generated energy: 1036.28, electricity volume: 964.16, power minimum load 102.56, power maximum load: 505.43, power capacity of starting shooting: 665.64, as also needed other to service, please by 0, exit and please hang up ".
As the preferred implementation of a kind of small coal power plants schedule voice declaration method of the embodiment of the present invention, the above-mentioned small coal power plants field data of storage can be audited by dispatcher, and the small coal power plants field data after examination & verification is reported higher level's thread.
As the preferred implementation of a kind of small coal power plants schedule voice declaration method of the embodiment of the present invention, the above-mentioned small coal power plants field data of storage can be collected displaying by dispatcher.
Embodiment 3
A kind of power plant schedule voice declaration system of the embodiment of the present invention, including user's access unit, input block, locking unit, confirmation unit and memory element.
Described user's access unit is for receiving the access request of user, and checking Customs Assigned Number and login password are followed by access customer.
Described input block is for inputting power plant's field data by voice message user. Described power plant field data includes: power minimum load, power maximum load, start power capacity, generated energy and electricity volume.
Described locking unit is for judging whether described power plant field data meets the barring condition of setting, described barring condition is: electricity volume generated energy, and power minimum load < power maximum load start power capacity, and 2.4 times power minimum load < generated energy < 2.4 times power maximum loads. Meet barring condition and then perform step 4; Do not meet barring condition then voice message user to return step 2 and re-enter power plant's field data.
As other embodiment, described barring condition is: power minimum load < power maximum load start power capacity.
As other embodiment, described barring condition is: 2.4 times power minimum load < generated energy < 2.4 times power maximum loads.
As other embodiment, described barring condition is: electricity volume generated energy.
The power plant's field data meeting barring condition is confirmed by described confirmation unit for voice message user, confirms then to carry out step 5; Re-enter, return step 2 and re-enter power plant's field data.
Described memory element is for storing the above-mentioned power plant's field data confirmed through user.
A kind of power plant schedule voice declaration system of the embodiment of the present invention also includes examination & verification unit, reporting element and collection unit.
Described examination & verification unit is for auditing power plant's field data of storage.
Described reporting element is for reporting higher level's thread by the power plant's field data after examination & verification.
Described collection unit is for collecting displaying to power plant's field data of storage.
Preferred implementation as a kind of power plant schedule voice declaration system of the embodiment of the present invention, voice server, integrated above-mentioned user's access unit, input block, locking unit, confirmation unit and memory element in described voice server can be developed based on Dialogic sound card. Further, WEB server, integrated above-mentioned examination & verification unit, reporting element and collection unit in described voice server are built. The technology of voice server is developed based on Dialogic voice, and the technology building WEB server belongs to the art technology known technology, by the functional requirement provided in conjunction with a kind of power plant schedule voice declaration system of the embodiment of the present invention, technical field for the art can be implemented when not paying creative work, thus repeats no more.
Obviously, above-described embodiment is only for clearly demonstrating example, and is not the restriction to embodiment. For those of ordinary skill in the field, can also make other changes in different forms on the basis of the above description. Here without also cannot all of embodiment be given exhaustive. And the apparent change thus extended out or variation are still among the protection domain of the invention.

Claims (2)

1. power plant's schedule voice declaration system, it is characterised in that including:
User's access unit, for receiving the access request of user, checking Customs Assigned Number and login password are followed by access customer;
Input block, inputs power plant's field data for voice message user;
Locking unit, for judging whether described power plant field data meets the barring condition of setting, does not meet barring condition then voice message user and returns input block and re-enter power plant's field data;
Wherein, described barring condition is: electricity volume generated energy, and power minimum load < power maximum load start power capacity, and 2.4 times power minimum load < generated energy < 2.4 times power maximum loads; Or
Described barring condition is: 2.4 times power minimum load < generated energy < 2.4 times power maximum loads; Or
Described barring condition is: electricity volume generated energy; Or
Described barring condition is: power minimum load < power maximum load start power capacity;
Confirmation unit, carries out the power plant's field data confirming acquisition through user's confirmation for voice message user to the power plant's field data meeting barring condition, or return input block re-enters power plant's field data;
Memory element, for storing the above-mentioned power plant's field data confirmed through user.
2. system according to claim 1, it is characterised in that described power plant field data includes: power minimum load, power maximum load, start power capacity, generated energy and electricity volume.
CN201610081826.4A 2014-07-23 2014-07-23 Power plant's schedule voice declaration system Active CN105629935B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610081826.4A CN105629935B (en) 2014-07-23 2014-07-23 Power plant's schedule voice declaration system

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN201410351712.8A CN104166894B (en) 2014-07-23 2014-07-23 Power plant's schedule voice declaration method and system
CN201610081826.4A CN105629935B (en) 2014-07-23 2014-07-23 Power plant's schedule voice declaration system

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
CN201410351712.8A Division CN104166894B (en) 2014-07-23 2014-07-23 Power plant's schedule voice declaration method and system

Publications (2)

Publication Number Publication Date
CN105629935A true CN105629935A (en) 2016-06-01
CN105629935B CN105629935B (en) 2018-03-30

Family

ID=51910691

Family Applications (2)

Application Number Title Priority Date Filing Date
CN201610081826.4A Active CN105629935B (en) 2014-07-23 2014-07-23 Power plant's schedule voice declaration system
CN201410351712.8A Active CN104166894B (en) 2014-07-23 2014-07-23 Power plant's schedule voice declaration method and system

Family Applications After (1)

Application Number Title Priority Date Filing Date
CN201410351712.8A Active CN104166894B (en) 2014-07-23 2014-07-23 Power plant's schedule voice declaration method and system

Country Status (1)

Country Link
CN (2) CN105629935B (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1256465A (en) * 1999-12-06 2000-06-14 欧阳永熙 Control of power output from one generator set to power network and corresponding settlement method in power market
US6393332B1 (en) * 1999-04-02 2002-05-21 American Standard Inc. Method and system for providing sufficient availability of manufacturing resources to meet unanticipated demand
CN1704945A (en) * 2004-06-01 2005-12-07 上海市电力公司市东供电公司 Dangerous point safety precontrol method for power network dispatch
CN1752958A (en) * 2004-09-26 2006-03-29 福建省电力试验研究院 Evaluation system of electrical network operation state and dispatch decision system
CN103198420A (en) * 2013-03-29 2013-07-10 山东电力集团公司 Real-time interactive long-distance fee-control management system and method

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2685328Y (en) * 2003-12-29 2005-03-16 刘临杰 Efficient combined water purifier
CN100485558C (en) * 2007-12-19 2009-05-06 田一鸣 Electrical power system safety operation intelligent monitoring device and monitoring method thereof
CN101458502A (en) * 2008-12-30 2009-06-17 湖南省电力公司湘潭电业局 Electrical power system standardized work intelligent control method and special equipment
EP2685328B1 (en) * 2012-07-10 2016-10-05 Siemens Aktiengesellschaft User interface of an automation system and a method

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6393332B1 (en) * 1999-04-02 2002-05-21 American Standard Inc. Method and system for providing sufficient availability of manufacturing resources to meet unanticipated demand
CN1256465A (en) * 1999-12-06 2000-06-14 欧阳永熙 Control of power output from one generator set to power network and corresponding settlement method in power market
CN1704945A (en) * 2004-06-01 2005-12-07 上海市电力公司市东供电公司 Dangerous point safety precontrol method for power network dispatch
CN1752958A (en) * 2004-09-26 2006-03-29 福建省电力试验研究院 Evaluation system of electrical network operation state and dispatch decision system
CN103198420A (en) * 2013-03-29 2013-07-10 山东电力集团公司 Real-time interactive long-distance fee-control management system and method

Also Published As

Publication number Publication date
CN104166894B (en) 2016-08-24
CN104166894A (en) 2014-11-26
CN105629935B (en) 2018-03-30

Similar Documents

Publication Publication Date Title
CN110647567B (en) Power failure plan auxiliary decision system based on end data fusion
CN103578039B (en) A kind of power networks risk prewarning analysis system
CN105427039A (en) Efficient processing method of distribution network repair work orders based on responsibility areas
CN104915750A (en) Intelligent operation ticket management method and system for achieving integration with an EMS and an OMS
CN104463696A (en) Power grid operating risk recognition and prevention method and system
CN104933535A (en) An intelligent monitoring operation ticket management method and a system thereof
CN107844880A (en) A kind of electric network fault grade automatic identifying method based on multisource data fusion
CN110310053A (en) A kind of automation of distribution line can turn power supply capacity statistical method and system
CN102496088A (en) Method for improving executive force of power communication overhaul core flow
CN112134310B (en) Big data-based artificial intelligent power grid regulation and control operation method and system
CN113258669B (en) Networked intelligent scheduling method and terminal based on distribution network maintenance
CN110765112A (en) Energy equipment data association method and system based on Internet of things identification technology
CN106296127A (en) A kind of dynamic construction system and method for intelligent substation operation flow
CN105978147A (en) File interaction based remote constant value amending system for automatic safety devices
CN116308139A (en) Intelligent misoperation prevention and networked command issuing platform for regulation and control
CN113361970B (en) Virtual dispatcher system and dispatching method based on power intelligent dispatching engine
CN109523422A (en) A kind of method for digging of distribution network failure influence factor
CN109002901A (en) A kind of province ground county&#39;s integration electric network information total management system and device
CN104318739B (en) Electric power safety, quality In-site supervision main website-wireless data terminal management system
CN105629935A (en) Dispatching voice reporting system for power plant
CN105809369A (en) Day-ahead plan safety checking method considering power distribution nondeterminacy of new energy
CN116128270A (en) Power grid operation plan management method and device for multi-source data fusion
CN101615361B (en) Method for designing dispatcher training architecture based on service drive
Bukhsh et al. Enhanced, risk-based system development process: a case study from the Belgian transmission network
CN107565579B (en) Multi-source cooperative management and control system and method for improving reactive voltage control level

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant