US2533852A - Process and apparatus for preparing concrete - Google Patents

Process and apparatus for preparing concrete Download PDF

Info

Publication number
US2533852A
US2533852A US609176A US60917645A US2533852A US 2533852 A US2533852 A US 2533852A US 609176 A US609176 A US 609176A US 60917645 A US60917645 A US 60917645A US 2533852 A US2533852 A US 2533852A
Authority
US
United States
Prior art keywords
chute
concrete
water
excess
cement
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
US609176A
Inventor
Tietig Chester
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to US609176A priority Critical patent/US2533852A/en
Application granted granted Critical
Publication of US2533852A publication Critical patent/US2533852A/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28CPREPARING CLAY; PRODUCING MIXTURES CONTAINING CLAY OR CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28C9/00General arrangement or layout of plant

Definitions

  • This invention relates to a method and apparatus for making concrete. It is well known that workmen have a tendency to mix too much water with concrete so that it may be handled and poured more easily. It is also well known that concrete which is so wet that it is sloppy when poured, does not make a strong structure. For best results the concrete should be fairl stiff, i. e., like a stiff mud, when it is poured into the forms.
  • Concrete as stiif as this may give trouble in chuting. It may demand an excessivelv vertical chute and segregation may occur in ohuting if the fall is too near vertical. If the slope is too gentle, the concrete may not slide, i. e., the chute may become clogged. This is especially true when the concrete must be poured under freezing conditions. If whole concrete is poured it may encrust the chute. If any falls over the side of the chute, cement values are lost.
  • I chute sand, gravel (hereinafter either individually or collectively termed the aggregate and an excess of water (sufficient to promote easy chuting) to the place where the concrete is to be laid or thereabout.
  • I dewater the sand and gravel At the lower end of the chute or flume, I dewater the sand and gravel, not completely, but to an extent that when well mixed with the customary amount of cement, the result will be a good stiff mix of concrete.
  • the operator can readily control the degree of dewatering by regulating the speed of the dewatering means or by lengthening or shortening the time during which the sand and gravel are de-watered.
  • Figure 1 is a plan view partly in section of my apparatus
  • Figure 2 is a section on line 2-2 of Figure 1;
  • Figure 3 is a section through the dewatering cyli der on line 3--3 of Figure l.
  • I0 is a high point from which the chuting is to be done.
  • H is a chute which is not flatter than 1 to 4 (25% grade) nor steeper than 1 to 2 (50% grade).
  • I2 is an orifice that delivers water substantiall at the top of the chute onto the chute at a uniform or nearly uniform rate.
  • a hopper i3 which has an outlet 54 which is at an angle to the hopper.
  • a de-watering cylinder l5 Arran ed to receive material from the outlet I4 is a de-watering cylinder l5 which is made of perforated metal and which rot tes.
  • the motor l6 has, preferably, a variable speed drive ll.
  • a concrete mixer Hi At the end of the dewaterer from which the sand and gravel are to be discharged, there is a concrete mixer Hi. The cement may be added in proper proportion to the tie-watered sand and gravel to form a settable concrete at any point between the dewatering device and the concrete mixer, the mixer serving to thoroughly admix the ingredients in the usual manner.
  • a volumetric gaging bin I9 which may alternatively be a scale bin and which is arranged with a valved bottom discharge 20 to the mixer. For continuous operation a poidometer may be substituted for the gaging bin.
  • I deliver to the chute H at its topmost point a stream of gravel and a stream of sand, or alternatively an already mixed stream of the two in correct proportions for the particular concrete mix to be made, and in both cases a sufficiently large stream of water to promote easy sliding down the chute.
  • These streams are each preferably, but not necessarily, metered by a poidorneter.
  • the chute delivers the mixed material into the hopper 13 from which it makes its exit from outlet l4 into the de-watering cylinder l5. The latter rotates at from 5 to revolutions per minute. although this invention is not limited to any particular number of revolutions.
  • perforations have substantially from 50% to of the area of the inner surface of the cylinder, but here likewise there is no definite limitation on the area of perforation.
  • the perforations should be sufficient merely to rid the mix of as much water as will drain freely therefrom and should not be so large as to cause an excessive loss of sand.
  • the de-watered mix is dumped from the lower end of the cylinder into the volumetric gaging bin l9 under the influence of the incline of the cylinder and its rotation.
  • the slope of the cylinder may be from to 20 percent, and here again the amount of slope is not critical. Steeper slopes may be used if spiral bafiles( not shown) are employed within the cylinder to prevent too fast a delivery of material.
  • Optional equipment is an open tank 2
  • I may chute the complete concrete mix with an excess of water, de-water the mixture in cylinde to the desired and correct degree of stiffness, and then use the stiffened mixture directly in construction.
  • the water recovered from the cylinder I5 is preferably returned to the top of the chute, since it carries cement values which should not be wasted.
  • I provide the chute II with a multiplicity of angled baffles 25 arranged as shown, so that the material descending the chute istossed from side to side, i. e., from one baflie to another so that there is a continuous rebound. Mixing is promoted by this construction.
  • I feed separate streams of cement, sand, gravel and water, the latter being in sufficient excess to promote chuting.
  • the baffle construction of the chute mixes the concrete on the way down.
  • I de-water the mix by any suitable means, say the de-watering cylinder I 5 or a centrifugal extractor (not shown), vacuum filter, Dorr-type thickener or similar machines.
  • the water, which bears cement values is preferably recycled to the top of the chute.
  • one or more poidometers may be substituted by other forms of continuous weighing or weighing-and-proportioning equipment.
  • a proportional feeder can be used to feed a proportioned mixture of sand and gravel or the proportional feeder can supply a proportioned mixture of sand and cement while a weighed stream of gravel enter the top of the chute from another source.
  • Such operation i. e., that in which cement is fed at the top of the chute is limited to use when angle bailies 25 are employed on the chute.
  • the process of preparing concrete which comprises delivering all of the constituents of concrete down an inclined chute in which mixing conditions prevail, said delivery being performed in the presence of a suflicient excess of water to facilitate the flow of the materials down the incline and then bringing the materials to rest under conditions favoring the draining off of water for a suflicient length of time to reduce the water content of the concrete to the range of proportions which should occur in a proper mix.
  • a chute for delivering the constituents of concrete extending from a high point to a lower point near where concrete is to be laid, a de-watering device arranged to largely de- Water material delivered thereto by the chute and a concrete mixer arranged to receive material which has passed through the de-watering means.
  • a chute for delivering con crete or the constituents thereof extending from a high point to a lower point, receiving and dewatering devices operatively arranged in series at the bottom of the chute to receive material therefrom which is wet with an excess of water and arranged to remove said excess from said material, means for gaging the de-watered material, said means being located adjacent the exit end of the de-watering device and a concrete mixer arranged to receive gaged material from the gaging device.
  • a chute for delivering concrete or the constituents thereof, said chute extending from a high point to a lower point, a multiplicity of bafiles attached to the upper surface of said chute so as to promote mixing of the material descending the chute, receiving and dewatering devices operatively arranged in series at the bottom of the chute to receive material therefrom, which is wet with an excess of water and arranged to remove said excess from said material.
  • a chute for delivering-concrete or the constituents thereof, said chute ex-- tending from a high point to a lower point, said chute having a grade inclination not flatter than 25% nor steeper than 50%, the end of said chute being adjacent a place at which concrete is to be laid, receiving and de-watering devices operatively arranged in series in the order named at the bottom of the chute to receive material therefrom which is wet with an excess of water, said devices being arranged to remove said excess from said material, means for gaging the de-watered material, said means being located adjacent the exit end of the de-watering devices and a concrete mixer arranged to receive gaged material from the gaging device.
  • a chute for delivering concrete or the constituents thereof said chute extending froma high point to a lower point and having a grade inclination not flatter than 25% nor steeper than 50%, one of more poidometers arranged at the high end of the chute to deliver streams of material thereto, including water for making concrete, receiving and de-watering devices at the lower end of the chute operatively arranged in series in the order named to receive material from said chute which is wet with an excess of water for the purpose of making concrete, said devices being arranged to remove said excess from said material.
  • a chute for delivering concrete or the constituents thereof said jchute extending from a high point to a lower point, said chute having a grade inclination not flatter than t 25% nor steeper than 50%, a plurality of concrete constituent feeding devices adjacent to top of said chute and arranged to deliver concretemaking materials thereto, so that a complete number of concrete-making materials is supplied to the top of the chute, a multiplicity of mixing devices operatively arranged along the length of said chute and a de-watering device arranged at the lower point of said chute to receive material therefrom, said de-watering device being operative to eliminate an excess of water above that necessary to make good concrete from the material received from said chute.
  • the process of preparing concrete including cement and an aggregate which comprises chuting the aggregate mixed with an excess of water to render the mass freely flowable along the chute, removing excess water from the mass adjacent the discharge end of the chute and thence mixing cement therewith in proper proportion to form a settable concrete.
  • An apparatus for preparing concrete comprising in combination an inclined chute extending from a higher to a lower elevation, a dewatering device arranged adjacent the lower end of the chute and adapted to receive material discharged from the chute and a mixer located adjacent the de-watering device and arranged to receive material discharged from the de-watering device.
  • An apparatus for preparing concrete as set forth in claim 14 including a volumetric gaging device located intermediate the de-watering device and mixer and adapted to transfer material therebetween.
  • An apparatus for preparing concrete as set forth in claim 14 including a pipe extending from the de-watering device to a point adjacent the elevated end of the chute and a pump for returning water recovered from the de-watering device to the chute.
  • An apparatus for preparing concrete as set forth in claim 14 including means for feeding water and aggregate in controlled quantities into the elevated end of the chute.

Description

Filed. Aug. 6,, 1945 C TIETIG PROCESS AND APPARATUS FOR PREPARING CONCRETE wuSmm wzEwEE $.2
IN VEN TOR.
Patented Dec. 12, 1950 PROCESS AND APPARATUS FOR PREPARING CONCRETE Chester Tietlg, Park Hills, Ky.
Application August 6, 1945, Serial No. 609,176
This invention relates to a method and apparatus for making concrete. It is well known that workmen have a tendency to mix too much water with concrete so that it may be handled and poured more easily. It is also well known that concrete which is so wet that it is sloppy when poured, does not make a strong structure. For best results the concrete should be fairl stiff, i. e., like a stiff mud, when it is poured into the forms.
Concrete as stiif as this may give trouble in chuting. It may demand an excessivelv vertical chute and segregation may occur in ohuting if the fall is too near vertical. If the slope is too gentle, the concrete may not slide, i. e., the chute may become clogged. This is especially true when the concrete must be poured under freezing conditions. If whole concrete is poured it may encrust the chute. If any falls over the side of the chute, cement values are lost.
According to the present invention. I take full advantage of the lubricating and washing action that water has in chuting sand and gravel. I use an excess of water during chuting, but I remove or otherwise adjust the excess before it can do any harm. I remove or adjust the water content without hindering the mixing operation in any way, so that continuous mixing may be practiced if desired. The stiffness of the final mix is under the control of the operator at all times. Further, in the preferred modification of my process. I save chuting the cement, i. e., I chute only sand, gravel and water. This procedure saves the cement that otherwise may fall to the side of the chute. The chute cannot encrust and the water may be re-cycled. The process is therefore highly economical as well as a guarantee of good stiff mixes.
In my preferred process, I chute sand, gravel (hereinafter either individually or collectively termed the aggregate and an excess of water (sufficient to promote easy chuting) to the place where the concrete is to be laid or thereabout. At the lower end of the chute or flume, I dewater the sand and gravel, not completely, but to an extent that when well mixed with the customary amount of cement, the result will be a good stiff mix of concrete. The operator can readily control the degree of dewatering by regulating the speed of the dewatering means or by lengthening or shortening the time during which the sand and gravel are de-watered.
Figure 1 is a plan view partly in section of my apparatus;
Figure 2 is a section on line 2-2 of Figure 1; and
18 Claims. (01. 259-146) Figure 3 is a section through the dewatering cyli der on line 3--3 of Figure l. Referring to the accompanying drawing, I0 is a high point from which the chuting is to be done. H is a chute which is not flatter than 1 to 4 (25% grade) nor steeper than 1 to 2 (50% grade). I2 is an orifice that delivers water substantiall at the top of the chute onto the chute at a uniform or nearly uniform rate. At the bottom of the chute is a hopper i3 which has an outlet 54 which is at an angle to the hopper. Arran ed to receive material from the outlet I4 is a de-watering cylinder l5 which is made of perforated metal and which rot tes. It is positioned at a gentle downward slope toward its outlet. It may be driven by an electric motor l6, oil engine or other means. The motor l6 has, preferably, a variable speed drive ll. At the end of the dewaterer from which the sand and gravel are to be discharged, there is a concrete mixer Hi. The cement may be added in proper proportion to the tie-watered sand and gravel to form a settable concrete at any point between the dewatering device and the concrete mixer, the mixer serving to thoroughly admix the ingredients in the usual manner. Between the mixer l8 and the dewaterer 15 there is a volumetric gaging bin I9 which may alternatively be a scale bin and which is arranged with a valved bottom discharge 20 to the mixer. For continuous operation a poidometer may be substituted for the gaging bin.
To operate this apparatus according to m invention, I deliver to the chute H at its topmost point a stream of gravel and a stream of sand, or alternatively an already mixed stream of the two in correct proportions for the particular concrete mix to be made, and in both cases a sufficiently large stream of water to promote easy sliding down the chute. These streams are each preferably, but not necessarily, metered by a poidorneter. The chute delivers the mixed material into the hopper 13 from which it makes its exit from outlet l4 into the de-watering cylinder l5. The latter rotates at from 5 to revolutions per minute. although this invention is not limited to any particular number of revolutions. Its perforations have substantially from 50% to of the area of the inner surface of the cylinder, but here likewise there is no definite limitation on the area of perforation. The perforations should be sufficient merely to rid the mix of as much water as will drain freely therefrom and should not be so large as to cause an excessive loss of sand.
The de-watered mix is dumped from the lower end of the cylinder into the volumetric gaging bin l9 under the influence of the incline of the cylinder and its rotation. The slope of the cylinder may be from to 20 percent, and here again the amount of slope is not critical. Steeper slopes may be used if spiral bafiles( not shown) are employed within the cylinder to prevent too fast a delivery of material.
Optional equipment is an open tank 2| under the cylinder for the purpose of catching water eliminated therefrom. This water may be returned to the top of the chute by means of a pipe 22 and a centrifugal pump 23. Such equipment is useful both to cut down the consumption of water and to keep the working places around the bottom of the chute reasonably dry. If poidometers 24 have been used at the top of the chute, and a poidometer is used to feed cement to the concrete mixer l8, the volumetric gaging bin or scale bin 19 may be dispensed with.
In an alternative process, I may chute the complete concrete mix with an excess of water, de-water the mixture in cylinde to the desired and correct degree of stiffness, and then use the stiffened mixture directly in construction. In this modification, the water recovered from the cylinder I5 is preferably returned to the top of the chute, since it carries cement values which should not be wasted.
In a third modification, I provide the chute II with a multiplicity of angled baffles 25 arranged as shown, so that the material descending the chute istossed from side to side, i. e., from one baflie to another so that there is a continuous rebound. Mixing is promoted by this construction. I feed separate streams of cement, sand, gravel and water, the latter being in sufficient excess to promote chuting. The baffle construction of the chute mixes the concrete on the way down. At the bottom of the chute, i. e., a place near where the concrete is to be laid, I de-water the mix by any suitable means, say the de-watering cylinder I 5 or a centrifugal extractor (not shown), vacuum filter, Dorr-type thickener or similar machines. The water, which bears cement values is preferably recycled to the top of the chute.
It is to be understood that one or more poidometers may be substituted by other forms of continuous weighing or weighing-and-proportioning equipment. For example, a proportional feeder can be used to feed a proportioned mixture of sand and gravel or the proportional feeder can supply a proportioned mixture of sand and cement while a weighed stream of gravel enter the top of the chute from another source. Such operation, i. e., that in which cement is fed at the top of the chute is limited to use when angle bailies 25 are employed on the chute.
I claim as my invention:
1. The process which comprises admixing the non-cement constituents of concrete with a sufficient excess of Water over what they require in a normal concrete mix to render them freely flowing, conveying the said mixture by gravity to the immediate neighborhood of the place where the concrete is to be prepared and used, adding cement sufficient to make a normal concrete mixture in respect to all other constituents except that water is in excess, then mixing said cement with the other constituents under efficient de-watering conditions until a normally well-mixed and normally wet mix is obtained.
2. The process of making concrete which comprises conveying by gravity a stream of sand and ravel under the influence of a substantial steam of water directed thereon, continuously adding to saidstream of sand, gravel and water, a stream of cement suflicient to establish the proper proportion thereof in the concrete to be made, said cement, gravel, sand and water, being conveyed under conditions favoring mixing, eliminating the excess of water at the end of the conveying operation, and discharging the finished mixture as concrete.
3. The process which'comprises delivering sand and gravel together in the proportion in which they are to be used in concrete, said delivery being made down a long inclined chute with the assistag e of an excess of water over that required to ake good concrete mix, said water being added at the top of the chute in sufficient quantity to facilitate delivery, said delivery being made under conditions prevalent on the chute that promote mixing, then draining off the excess of water until the sand and gravel is no more than saturated, and then mixing a proper proportion of cement to make concrete.
4. The process of preparing concrete which comprises delivering all of the constituents of concrete down an inclined chute in which mixing conditions prevail, said delivery being performed in the presence of a suflicient excess of water to facilitate the flow of the materials down the incline and then bringing the materials to rest under conditions favoring the draining off of water for a suflicient length of time to reduce the water content of the concrete to the range of proportions which should occur in a proper mix.
5. A process according to claim 4 in which the water which bears cement values is recovered and returned to the top of the incline for re-use in mixing the additional amounts of sand, gravel and cement.
6. In combination, a chute for delivering the constituents of concrete, extending from a high point to a lower point near where concrete is to be laid, a de-watering device arranged to largely de- Water material delivered thereto by the chute and a concrete mixer arranged to receive material which has passed through the de-watering means.
'7. In combination, a chute for delivering con crete or the constituents thereof, extending from a high point to a lower point, receiving and dewatering devices operatively arranged in series at the bottom of the chute to receive material therefrom which is wet with an excess of water and arranged to remove said excess from said material, means for gaging the de-watered material, said means being located adjacent the exit end of the de-watering device and a concrete mixer arranged to receive gaged material from the gaging device.
8. In combination, a chute for delivering concrete or the constituents thereof, said chute extending from a high point to a lower point, a multiplicity of bafiles attached to the upper surface of said chute so as to promote mixing of the material descending the chute, receiving and dewatering devices operatively arranged in series at the bottom of the chute to receive material therefrom, which is wet with an excess of water and arranged to remove said excess from said material.
9. In combination, a chute for delivering-concrete or the constituents thereof, said chute ex-- tending from a high point to a lower point, said chute having a grade inclination not flatter than 25% nor steeper than 50%, the end of said chute being adjacent a place at which concrete is to be laid, receiving and de-watering devices operatively arranged in series in the order named at the bottom of the chute to receive material therefrom which is wet with an excess of water, said devices being arranged to remove said excess from said material, means for gaging the de-watered material, said means being located adjacent the exit end of the de-watering devices and a concrete mixer arranged to receive gaged material from the gaging device.
10. In combination; a chute for delivering concrete or the constituents thereof, said chute extending froma high point to a lower point and having a grade inclination not flatter than 25% nor steeper than 50%, one of more poidometers arranged at the high end of the chute to deliver streams of material thereto, including water for making concrete, receiving and de-watering devices at the lower end of the chute operatively arranged in series in the order named to receive material from said chute which is wet with an excess of water for the purpose of making concrete, said devices being arranged to remove said excess from said material.
11. In combination, a chute for delivering concrete or the constituents thereof, said jchute extending from a high point to a lower point, said chute having a grade inclination not flatter than t 25% nor steeper than 50%, a plurality of concrete constituent feeding devices adjacent to top of said chute and arranged to deliver concretemaking materials thereto, so that a complete number of concrete-making materials is supplied to the top of the chute, a multiplicity of mixing devices operatively arranged along the length of said chute and a de-watering device arranged at the lower point of said chute to receive material therefrom, said de-watering device being operative to eliminate an excess of water above that necessary to make good concrete from the material received from said chute.
12. The process of preparing concrete including cement and an aggregate which comprises chuting the aggregate mixed with an excess of water to render the mass freely flowable along the chute, removing excess water from the mass adjacent the discharge end of the chute and thence mixing cement therewith in proper proportion to form a settable concrete.
13. The process of preparing concrete including cement and an aggregate which comprises gravitationally chuting from a higher to a lower elevation the aggregate mixed with an excess of water to render the mass freely flowable down the chute, removing excess water from the mess adjacent the lower elevation and thence mixing cement therewith in proper proportion to form a settable concrete.
14. An apparatus for preparing concrete comprising in combination an inclined chute extending from a higher to a lower elevation, a dewatering device arranged adjacent the lower end of the chute and adapted to receive material discharged from the chute and a mixer located adjacent the de-watering device and arranged to receive material discharged from the de-watering device.
15. An apparatus for preparing concrete as set forth in claim 14 including a volumetric gaging device located intermediate the de-watering device and mixer and adapted to transfer material therebetween.
16. An apparatus for preparing concrete as set forth in claim 14 including a pipe extending from the de-watering device to a point adjacent the elevated end of the chute and a pump for returning water recovered from the de-watering device to the chute.
17. An apparatus for preparing concrete as set forth in claim 14 including means for feeding water and aggregate in controlled quantities into the elevated end of the chute.
18. The process of making concrete which comprises chuting the aggregate constituents of concrete from a height to the place at a lower elevation where the concrete is to be used, adding an excess of water to said constituents adjacent to said height to materially increase the ease with which they are chuted and the proportion of said water after addition to said constituents REFERENCES CITED The following references are of record in the file of this patent:
UNITED STATES PATENTS Number Name Date 833,014 West et al. Oct. 9, 1906. 1,046,437 Butler Dec. 10, 1912 1,270,332 Schafier June 25, 1918 1,304,619 Stamp May 27, 1919 1,916,417 Coulson July 4, 1933 1,969,533 Pipes et al Aug. 4, 1934 2,218 533 Huebotter Oct. 22, 1940
US609176A 1945-08-06 1945-08-06 Process and apparatus for preparing concrete Expired - Lifetime US2533852A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
US609176A US2533852A (en) 1945-08-06 1945-08-06 Process and apparatus for preparing concrete

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
US609176A US2533852A (en) 1945-08-06 1945-08-06 Process and apparatus for preparing concrete

Publications (1)

Publication Number Publication Date
US2533852A true US2533852A (en) 1950-12-12

Family

ID=24439655

Family Applications (1)

Application Number Title Priority Date Filing Date
US609176A Expired - Lifetime US2533852A (en) 1945-08-06 1945-08-06 Process and apparatus for preparing concrete

Country Status (1)

Country Link
US (1) US2533852A (en)

Cited By (20)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US2595631A (en) * 1950-07-01 1952-05-06 Volkart Geb Method and apparatus for cooling concrete mixture components
US2743911A (en) * 1952-10-22 1956-05-01 Lejmark Karl Robert Method and apparatus of producing filling materials to be used together with hydraulic cements
US2748951A (en) * 1951-05-04 1956-06-05 Dubach Max Device for separating solid particles from liquids
US2767926A (en) * 1948-12-15 1956-10-23 Trief Leon Method of and apparatus for automatically proportioning granulated material to be fed to a grinding mill
US2779575A (en) * 1952-09-18 1957-01-29 Intrusion Prepakt Inc Continuous grout strainer
US3090501A (en) * 1959-03-23 1963-05-21 Erie Strayer Company Cement mixing plant
US3094289A (en) * 1959-10-29 1963-06-18 Bolidens Gruv Ab Rock grinding system
US3123386A (en) * 1964-03-03 Sander
US3167307A (en) * 1963-04-23 1965-01-26 Koehring Co Self-batching mixer
US3212672A (en) * 1962-08-20 1965-10-19 Elgin Softener Inc Dry diatomaceous earth feeder
US3304064A (en) * 1965-10-11 1967-02-14 Westinghouse Air Brake Co Shaker mixing conveyor
US3482824A (en) * 1967-08-02 1969-12-09 Billy D Meade Preparation of asphalt paving material
US3568886A (en) * 1969-03-18 1971-03-09 Merrick Scale Mfg Co Low capacity weigher and feeder
US3942772A (en) * 1974-04-05 1976-03-09 Mid-Continent Pipeline Equipment Company Technique for mixing granular materials
US4003431A (en) * 1972-09-20 1977-01-18 Byron Jackson, Inc. Process of cementing wells
US4023779A (en) * 1976-08-09 1977-05-17 Caterpillar Tractor Co. Fibrous concrete mixing system
US4050864A (en) * 1975-09-03 1977-09-27 Saiji Komaki Apparatus for manufacturing concrete panels with surface pattern decorations
US5397177A (en) * 1992-02-03 1995-03-14 Swisher, Jr.; George W. Asphalt production plant having a two-burner dryer with increased exhaust capacity
US9963318B1 (en) 2017-08-14 2018-05-08 Mark D. Robbins Concrete fiber injector
US10118314B1 (en) 2018-03-03 2018-11-06 Mark D. Robbins Fiber boxes for a concrete fiber injector

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US833014A (en) * 1906-03-15 1906-10-09 James F West Mixing-machine.
US1046437A (en) * 1912-03-27 1912-12-10 Guy R Elliott Feed-regulator for concrete-machines.
US1270332A (en) * 1915-04-26 1918-06-25 John C Schaffer Feeding device.
US1304619A (en) * 1919-05-27 Method fob conveying concrete aggregate
US1916417A (en) * 1928-06-29 1933-07-04 Oliver United Filters Inc Apparatus and process for making cement
US1969533A (en) * 1934-01-30 1934-08-07 Southwest Cementing Corp Well cement mixer
US2218533A (en) * 1939-02-06 1940-10-22 Nat Lead Co Method and apparatus for filtering and dehydrating drilling mud

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US1304619A (en) * 1919-05-27 Method fob conveying concrete aggregate
US833014A (en) * 1906-03-15 1906-10-09 James F West Mixing-machine.
US1046437A (en) * 1912-03-27 1912-12-10 Guy R Elliott Feed-regulator for concrete-machines.
US1270332A (en) * 1915-04-26 1918-06-25 John C Schaffer Feeding device.
US1916417A (en) * 1928-06-29 1933-07-04 Oliver United Filters Inc Apparatus and process for making cement
US1969533A (en) * 1934-01-30 1934-08-07 Southwest Cementing Corp Well cement mixer
US2218533A (en) * 1939-02-06 1940-10-22 Nat Lead Co Method and apparatus for filtering and dehydrating drilling mud

Cited By (20)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3123386A (en) * 1964-03-03 Sander
US2767926A (en) * 1948-12-15 1956-10-23 Trief Leon Method of and apparatus for automatically proportioning granulated material to be fed to a grinding mill
US2595631A (en) * 1950-07-01 1952-05-06 Volkart Geb Method and apparatus for cooling concrete mixture components
US2748951A (en) * 1951-05-04 1956-06-05 Dubach Max Device for separating solid particles from liquids
US2779575A (en) * 1952-09-18 1957-01-29 Intrusion Prepakt Inc Continuous grout strainer
US2743911A (en) * 1952-10-22 1956-05-01 Lejmark Karl Robert Method and apparatus of producing filling materials to be used together with hydraulic cements
US3090501A (en) * 1959-03-23 1963-05-21 Erie Strayer Company Cement mixing plant
US3094289A (en) * 1959-10-29 1963-06-18 Bolidens Gruv Ab Rock grinding system
US3212672A (en) * 1962-08-20 1965-10-19 Elgin Softener Inc Dry diatomaceous earth feeder
US3167307A (en) * 1963-04-23 1965-01-26 Koehring Co Self-batching mixer
US3304064A (en) * 1965-10-11 1967-02-14 Westinghouse Air Brake Co Shaker mixing conveyor
US3482824A (en) * 1967-08-02 1969-12-09 Billy D Meade Preparation of asphalt paving material
US3568886A (en) * 1969-03-18 1971-03-09 Merrick Scale Mfg Co Low capacity weigher and feeder
US4003431A (en) * 1972-09-20 1977-01-18 Byron Jackson, Inc. Process of cementing wells
US3942772A (en) * 1974-04-05 1976-03-09 Mid-Continent Pipeline Equipment Company Technique for mixing granular materials
US4050864A (en) * 1975-09-03 1977-09-27 Saiji Komaki Apparatus for manufacturing concrete panels with surface pattern decorations
US4023779A (en) * 1976-08-09 1977-05-17 Caterpillar Tractor Co. Fibrous concrete mixing system
US5397177A (en) * 1992-02-03 1995-03-14 Swisher, Jr.; George W. Asphalt production plant having a two-burner dryer with increased exhaust capacity
US9963318B1 (en) 2017-08-14 2018-05-08 Mark D. Robbins Concrete fiber injector
US10118314B1 (en) 2018-03-03 2018-11-06 Mark D. Robbins Fiber boxes for a concrete fiber injector

Similar Documents

Publication Publication Date Title
US2533852A (en) Process and apparatus for preparing concrete
EP0120812B1 (en) Process and device for the production and direct application of ready-to-use building material preparations
US3206174A (en) Methods of forming and applying mixtures
WO1987003317A1 (en) A method and an apparatus for mixing gravel and bitumen
US1996082A (en) Mineral wool product and method of making same
US1947345A (en) Concrete mixing method
PL124781B1 (en) Method of continuously mixing together pulverized solids and liquids and vertical mixer therefor
US2068164A (en) Method of preparing road paving compositions
CN208343133U (en) Full-automatic concrete charging molding equipment
US1964523A (en) Apparatus for producing paving material
DE2741059A1 (en) CLEANING MACHINE
US1819756A (en) Machine for mixing concrete and the like
DE824169C (en) Mixer
US2083767A (en) Apparatus for mixing concrete
CN206899521U (en) It is a kind of to prepare the curable native complete set of equipments of fluidised form
CN201221362Y (en) Concrete injecting machine agitator
FI57157C (en) MASKIN FOER YTBELAEGGNING AV VAEGAR
AT313805B (en) Drying or drainage system for sand, gravel or the like.
CN210336414U (en) Concrete processing equipment
SU1650450A1 (en) Method for manufacturing polymeric cement pieces
CN207105282U (en) A kind of dicang formula batching plant
US3011414A (en) Method and apparatus for moving cementitious compositions
US2684267A (en) Asphalt pressure injection system and mechanism for asphalt mixing plants
US2981414A (en) Method and apparatus for separating fine material from coarse material
CN220075076U (en) Mortar stirring device convenient for feeding