US3582138A - Toroid excavation system - Google Patents

Toroid excavation system Download PDF

Info

Publication number
US3582138A
US3582138A US818986A US3582138DA US3582138A US 3582138 A US3582138 A US 3582138A US 818986 A US818986 A US 818986A US 3582138D A US3582138D A US 3582138DA US 3582138 A US3582138 A US 3582138A
Authority
US
United States
Prior art keywords
excavation
shaft
rock
haulageways
further characterized
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
US818986A
Inventor
Robert L Loofbourow
William Vaananen
William G Wood
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Application granted granted Critical
Publication of US3582138A publication Critical patent/US3582138A/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03FSEWERS; CESSPOOLS
    • E03F9/00Arrangements or fixed installations methods or devices for cleaning or clearing sewer pipes, e.g. by flushing
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21CMINING OR QUARRYING
    • E21C41/00Methods of underground or surface mining; Layouts therefor
    • E21C41/16Methods of underground mining; Layouts therefor

Definitions

  • This invention relates to a system for forming an excavation in rock in the form of a generally cylindrical annulus or toroid having a core of substantial size within which are located one or more access shafts.
  • the objective of the system is the making of large stable underground openings in rock it! the least time and at the lowest possible cost. It is the objective of the system to make available high grade crushed rock aggregate at a minimum cost while providing an excavation suitable for storage, waste disposal, and the like.
  • the invention is illustrated in the accompanying drawings in which corresponding parts are identified by the same numerals and in which:
  • FIG. I is a schematic vertical cross section through a typical planned excavation after completion of final preparation and prior to production
  • FIG. 2 is a horizontal section taken generally along the line 2-2 of FIG. l and in the direction of the arrows, this being a plan of the top drill level;
  • FIG. 3 is a horizontal section taken generally along the line 3-3 of FIG. 1 and in the direction of the arrows, this being a plan of a middrill level;
  • FIG. 4 is a horizontal section on the line 4-4 of FIG. I and in the direction of the arrows, this being a plan of the haulage level;
  • FIG. 5 is a fragmentary vertical section on an enlarged scale showing the excavation system ingreater detail
  • FIG. 6 is a horizontal section generally on the line 6-6 of FIG. 5 and in the direction ofthe arrows;
  • FIG. 7 is a horizontal section generally on the line 7-7 of FIGS and in the direction of the arrows;
  • FIG. 8 is a schematic vertical section showing a layout for a second unit which may be excavated using the accessways of the first; and i FIG. 9 is a plan of such a layout for a second unit.
  • a large rock mass 10 underlying the ground surface 11 at some Substantial depth ranging between about 100 and several thousands of feet depending upon the conditions present and objectives sought.
  • the excavation 12 to be made is in the form of a generally cylindrical annulus or toroid having a core 13 of substantial size of diameter sufficient to support a substantial part of the stress increment which results from the excavation.
  • the situs is preferably at a convenient location near a place where there is large demand for low-cost stone or rock aggregate and-for large capacity storage or waste disposal space, such as near a large city.
  • one or more vertical or inclined access shafts such as hoisting shaft 14 and man shaft 15 are located near the center of core 13. These shafts, for example, may be of the order of 6 to 12 feet in diameter and adapted to provide access for skips for hoisting of rock and transport of men and equipment suspended from suitable hoist means at the ground surface, not shown but well understood in the art.
  • an inclined entrance lying outside of the excavation annulus may be pro vided.
  • an inclined conveyor way from a central loading point for a belt conveyor or similar means may be used for removal of rock from the excavation.
  • the entrances may be vertical or inclined or helical or zigzagged in a vertical plane or a combination of these. They may be prepared by any suitable drilling or mining techniques well known in the art.
  • a plurality of horizontal accessways or headings 16, 16A are formed through the rock extending generally radially outwardly from the center of the core to the edges of the excavation to be formed.
  • a plurality of concentric spaced apart horizontal inner drill drives 17, 17A and outer drill drives 18, 18A intersect the accessways 16, 16A.
  • the drill drives and haulageways are generally circular, the pattern in a horizontal is actually polygonal.
  • headings are run a specified distance on a given bearing and then turned by a given angle. Typical distances would be 75 to 150 feet and angles about 20.
  • a further advantage of this pattern is the greater ease of setting up long-hole drills to work on parallel rings of holes or holes in parallel planes, than to have each ring on a very slightly different bearing as would be true if the pattern were a true circle.
  • the drill drives are spaced apart both horizontally and vertically defining the perimeters of the excavation at their respective levels.
  • the excavation levels are interconnected by at least one generally vertical slot raise 19 extending between the inner and outer drill drives.
  • the excavation may require only one drill level, or more than two, depending upon the height of the excavation.
  • the drill drives are generally concentric but where more than on drill level is provided they need not be in vertical alignment. Instead it may be preferred that the excavation wall slope inwardly from the top to bottom.
  • the topmost drill drive may take the form of a pilot heading of shallow height, such that the miners may reach the ceiling for removal of loose rock installation of rock bolts, etc., and of width corresponding to the projected width of the toroidal excavation. At least one slot extends from this drill drive to a lower haulageway. The long holes are drilled from above, and for toroids of lesser height only radial haulageways are provided, the rock being loaded through the to roid itself. I
  • long-hole drilling and haulage may be from a single level, the same generally circular passages serving both as drill drives and haulageways.
  • the long holes are drilled from below and the rock is loaded and hauled through the toroid.
  • two or more slots may be prepared and a production face advanced in each direction from each slot.
  • a pocket 20 is developed at, or sometimes below, the lowermost haulage level.
  • Passways 21 are developed from the upper levels as needed so that all rock broken in preparatory workings can be loaded in bulk from a single loading station at the bottom of that shaft and removed.
  • a plurality of haulageways 22 extend from near the bottom of the hoist shaft at the haulage level to a peripheral ring 23 at the bottom of the excavation which has a plurality of draw points 24 as needed.
  • Bulk excavation proceeds by drilling and blasting holes on one or both sides of the slot 19. Broken rock is loaded on and hauled from the bottom of the slot to the loading station at the bottom of the hoisting shaft and raised to the surface.
  • apron feeder 25 to a crusher 26 in one of the haulage level accessways 22 located as close to the production area as feasible.
  • the crushed rock is desirably moved by conveyor 27 through an upwardly inclined conveyor way 28 to a surge bin 29 above the loading pocket 20 from which it is hoisted to the surface.
  • the apron feeder, belt conveyor and crusher installations are uniform so that the units can be moved readily and used at successive locations as the excavation proceeds. This limits the amount of large machinery that has to be taken underground and requires a minimum of labor After primary crushing the rock can be efficiently moved by belt conveyors.
  • the rock may be removed to the surface by hoisting, or by conveyor through an inclined entryway, or mixed with water and pumped.
  • Excavation is advanced in a generally circular pattern by blasting rings of long holes toward the slot 19 and drawing broken rock from drawpoints 24 starting with that drawpoint which underlies the slot. Mining is continued from either one or both sides of the slot which, of course, increases in size as mining proceeds until the cylindrical annulus is generally complete.
  • the general layout of long-hole drilling is shown schematically in lfig. where the lines identified by numeral 30 indicate the general pattern of drill holes.
  • An appropriate charge in each drill hole is detonated to break the rock, working initially from the circular haulageway 23 and then from drill drives 17A and 18A and finally from drill drives 17 and 18.
  • This mining method is known variously as sublevel stoping, sublevel stoping with long holes or simply long-hole stoping.
  • a general description of blast hole drilling is found in the Canadian Mining and Metallurgical Bulletin for Oct. 1953, pages 622-633.
  • Appropriate sumps 31 are provided as needed and sump pumps 32 remove unwanted water from the excavation.
  • Fresh air is circulated from a downcast shaft, preferably the smaller man shaft 15, through the working places and thence to an upcast shaft, preferably the larger hoisting shaft 14.
  • the long-hole drilling method of mining is utilized so as to minimize the amount of preproduction work and the distance through which rock, supplies, equipment and men must be moved while maintaining high standards of safety, ventilation and efficiency.
  • Excavation is accomplished with a minimum of undercutting, raising and other preparation.
  • the excavation is sufficiently stable that use can be made of the space, as well as of the rock produced. Preproduction time and costs are minimized and ultimate costs of producing rock and space are minimized.
  • the excavation system is adaptable to a range of moderate and high rate of production.
  • the excavation is readily adaptable to fast low-cost production of stone or rock from a mass of strong rock which does not appear at the surface but is covered by marsh or even shallow water, by weak or saturated strata or other cover through which the sinking and operation of conventional shafts is slow, costly or hazardous.
  • Large volumes of low-cost stone can be produced at many convenient locations without any appreciable permanent change of surface topography without preempting any large area of the surface even during production.
  • the excavation is intended to be made in strong compact tight rock, the system is adaptable to use in many localities where rock is less than ideal in these respects.
  • the accessways which have been provided for the first may be used for a second unit or a number of successive similar units.
  • the first stope, indicated generally at 33 is nearly completed except for a pillar 34 which is left in place until the second stope, indicated generally at 35, is complete.
  • the slot raise 36 in the second excavation is located on the far side, as indicated.
  • An interconnecting accessway 37 is provided for circulation of fresh air to the second excavation and a passage 38 is provided to exhaust air.
  • An interconnecting haulageway 39 is provided for removing rock from the second excavation to the bottom of the hoisting shaft 14 of the first excavation.
  • Some uses of the underground toroid space are compatible with continued mining. In such cases, one completed segment of the toroid is put to use while excavation of other segments continues. Where separation is needed, mining can be stopped at any point of circumference, a vertical pillar left and mining resumed beyond a new slot.
  • a typical 10,000,000 ton toroid of the general configuration shown in FIGS. 1 through 4 may have an outside diameter of about 950 feet, a height of about 375 feet and a maximum thickness of about I40 feet.
  • the top drill level is about feet from the top of the excavation.
  • the middrill level is about 165 feet below the top drill level and about feet above the haulage level.
  • the core of the annular excavation has a diameter of about 675 feet sufficient to support a substantial part of the stress increment which results from the excavation.
  • a system of excavation deep in the'earth which comprises the steps of:
  • a system according to claim 1 further characterized in that said entranceway includes a first shaft utilized as a hoisting shaft and a second smaller diameter man shaft is sunk generally parallel to the first and spaced therefrom.
  • a system according to claim 2 further characterized in that air is forced down said smaller shaft past working places on each level and returned to the surface through said hoisting shaft.
  • a system according to claim 1 further characterized in that a haulageway is developed at the bottom of the excavation connecting with the generally radial haulageways and extending in a generally circular ring around but spaced from said shaft.
  • a system according to claim 4 further characterized in that a pair of concentric circular inner and outer drill drives are developed at each drill level, each connected by generally radial accessways to said shaft, said accessways being spaced upwardly from said haulageways.
  • a system according to claim 5 further characterized in that at least two vertically spaced apart drill levels are established.
  • a system according to claim 5 further characterized in that passways are developed from said accessways to the loading station for removal of rock from preparatory workings.
  • a system according to claim 1 further characterized in that crushing means are provided in said haulageways adjacent the production area for subsurface crushing of rock before delivery to said loading point.
  • a system according to claim 1 further characterized in that the excavation is advanced by progressively drilling and blasting on both .sides of said slot.
  • a system according to claim 1 further characterized in that upon substantial completion of the excavation:
  • A. interconnecting accessways and haulageways are prepared extending from the first excavation to a nearby site for a second excavation
  • At least one vertical slot raise is developed from said drill drives and connecting with one of said haulageways of said second excavation, and
  • a system according to claim 10 further characterized in that said second excavation is formed concentric with the first excavation.

Abstract

A system for excavating space deep in the earth in the form of a doughnut-shaped generally cylindrical annulus or toroid having a core of substantial diameter within which there is usually at least one central shaft for access to the workings and removal of rock from the excavation. The generally circular configuration of the excavation minimizes distances for access of men and equipment to the workings and removal of the rock and introduces efficiencies and cost savings resulting from minimum preparation, minimum travel distances, loading from a single station at the bottom of the shaft and is conducive to excellent working conditions.

Description

VII-Irv uwuvuu .l Dblllv TOROID EXCAVATION SYSTEM 1 1 Claims, 9 Drawing Figs.
US. Cl 299/13, 299/18, 299/19 Field of Search 299/1 1, 13, 18,19;61/0.5
H 13,5s2,13s
Primary Examiner-Ernest R. Purser Attorney-Burd, Braddock & Bartz ABSTRACT: A system for excavating space deep in the earth in the form of a doughnut-shaped generally cylindrical annulus or toroid having a core of substantial diameter within which there is usually at least one central shaft for access to the workings and removal of rock from the excavation. The generally circular configuration of the excavation minimizes distances for access of men and equipment to the workings and removal of the rock and introduces efficiencies and cost savings resulting from minimum preparation, minimum travel distances, loading from a single station at the bottom of the shaft and is conducive to excellent working conditions.
Pmmmu Inn 3582.138
' sum 1 or 4 lNVliN'l'O/U ROBERT L. LOOFBOUROW WILLIAM VAANANEN BY WILLIAM G. WOOD Mada/Maw ATTORNEYS PATENTED JUN 1 l97| SHEET 2 [IF 4 S R V m ROBERT L. LOOFBOUROW WILLIAM VAANANEN WILLIAM G. WOOD ATTORNEYS SHEET 3 [IF 4 I N VENI 0R9 ROBERT L. LOOFBOUROW BY WILLIAM VAANANEN WILLIAM G. WOOD AT TORNE-YS PATENTED JUN 1 I971 n W n y F /7 v 1 a a 7/50 W 0 7//// A? r 2 f H 5 7 PATENIEDJUN nan 3,582,138
SHEET I 0F 4 f 7-\34 A} m I [131%] .F'Jca.5'
' INVliNI'ORS ROBERT L. LOOFBOUROW WILLIAM VAANANEN BY WILLIAM 6. W000 MWJW ATTORNEYS TOROID EXCAVATION SYSTEM This invention relates to a system for forming an excavation in rock in the form of a generally cylindrical annulus or toroid having a core of substantial size within which are located one or more access shafts. The objective of the system is the making of large stable underground openings in rock it! the least time and at the lowest possible cost. It is the objective of the system to make available high grade crushed rock aggregate at a minimum cost while providing an excavation suitable for storage, waste disposal, and the like. The invention is illustrated in the accompanying drawings in which corresponding parts are identified by the same numerals and in which:
FIG. I is a schematic vertical cross section through a typical planned excavation after completion of final preparation and prior to production;
FIG. 2 is a horizontal section taken generally along the line 2-2 of FIG. l and in the direction of the arrows, this being a plan of the top drill level;
FIG. 3 is a horizontal section taken generally along the line 3-3 of FIG. 1 and in the direction of the arrows, this being a plan of a middrill level;
FIG. 4 is a horizontal section on the line 4-4 of FIG. I and in the direction of the arrows, this being a plan of the haulage level;
' FIG. 5 is a fragmentary vertical section on an enlarged scale showing the excavation system ingreater detail;
FIG. 6 is a horizontal section generally on the line 6-6 of FIG. 5 and in the direction ofthe arrows;
FIG. 7 is a horizontal section generally on the line 7-7 of FIGS and in the direction of the arrows;
FlG. 8 is a schematic vertical section showing a layout for a second unit which may be excavated using the accessways of the first; and i FIG. 9 is a plan of such a layout for a second unit. Referring to the drawings, there is shown schematically a large rock mass 10 underlying the ground surface 11 at some Substantial depth ranging between about 100 and several thousands of feet depending upon the conditions present and objectives sought. The excavation 12 to be made is in the form of a generally cylindrical annulus or toroid having a core 13 of substantial size of diameter sufficient to support a substantial part of the stress increment which results from the excavation.
The situs is preferably at a convenient location near a place where there is large demand for low-cost stone or rock aggregate and-for large capacity storage or waste disposal space, such as near a large city. As shown, one or more vertical or inclined access shafts such as hoisting shaft 14 and man shaft 15 are located near the center of core 13. These shafts, for example, may be of the order of 6 to 12 feet in diameter and adapted to provide access for skips for hoisting of rock and transport of men and equipment suspended from suitable hoist means at the ground surface, not shown but well understood in the art.
While the entrance to the excavation will in most instances extend through the central core, in some instances an inclined entrance lying outside of the excavation annulus may be pro vided. For example, an inclined conveyor way from a central loading point for a belt conveyor or similar means may be used for removal of rock from the excavation. Depending upon the particular site and the conditions encountered there, the entrances may be vertical or inclined or helical or zigzagged in a vertical plane or a combination of these. They may be prepared by any suitable drilling or mining techniques well known in the art. In some instances it may be essential or preferred to extend the hoisting shaft or incline several hundred'feet below the main toroid excavation. For example, where the toroid excavation is to be used as a pumped storage reservoir, a powerhouse excavation is needed below the reservoir.
Preparatory to beginning excavation, a plurality of horizontal accessways or headings 16, 16A are formed through the rock extending generally radially outwardly from the center of the core to the edges of the excavation to be formed. A plurality of concentric spaced apart horizontal inner drill drives 17, 17A and outer drill drives 18, 18A intersect the accessways 16, 16A. Although the drill drives and haulageways are generally circular, the pattern in a horizontal is actually polygonal. For convenience, in opening these passageways, headings are run a specified distance on a given bearing and then turned by a given angle. Typical distances would be 75 to 150 feet and angles about 20. A further advantage of this pattern is the greater ease of setting up long-hole drills to work on parallel rings of holes or holes in parallel planes, than to have each ring on a very slightly different bearing as would be true if the pattern were a true circle. The drill drives are spaced apart both horizontally and vertically defining the perimeters of the excavation at their respective levels. The excavation levels are interconnected by at least one generally vertical slot raise 19 extending between the inner and outer drill drives.
Although illustrated with two spaced apart drill levels, the excavation may require only one drill level, or more than two, depending upon the height of the excavation. The drill drives are generally concentric but where more than on drill level is provided they need not be in vertical alignment. Instead it may be preferred that the excavation wall slope inwardly from the top to bottom. The topmost drill drive may take the form of a pilot heading of shallow height, such that the miners may reach the ceiling for removal of loose rock installation of rock bolts, etc., and of width corresponding to the projected width of the toroidal excavation. At least one slot extends from this drill drive to a lower haulageway. The long holes are drilled from above, and for toroids of lesser height only radial haulageways are provided, the rock being loaded through the to roid itself. I
Where excavations of lesser height are preferred, as, for example, where the toroid is to be used for pumped storage, long-hole drilling and haulage may be from a single level, the same generally circular passages serving both as drill drives and haulageways. Here the long holes are drilled from below and the rock is loaded and hauled through the toroid. In any of the variations described, where rapid excavation is an objective, two or more slots may be prepared and a production face advanced in each direction from each slot.
After the hoisting shaft 14 has been completed a pocket 20 is developed at, or sometimes below, the lowermost haulage level. Passways 21 are developed from the upper levels as needed so that all rock broken in preparatory workings can be loaded in bulk from a single loading station at the bottom of that shaft and removed. A plurality of haulageways 22 extend from near the bottom of the hoist shaft at the haulage level to a peripheral ring 23 at the bottom of the excavation which has a plurality of draw points 24 as needed. Bulk excavation proceeds by drilling and blasting holes on one or both sides of the slot 19. Broken rock is loaded on and hauled from the bottom of the slot to the loading station at the bottom of the hoisting shaft and raised to the surface.
Because of the location of the hoisting and man shafts in the central core within the annular excavation, the length of accessways leading from the shafts for movement of supplies, equipment and men to the working places is minimized. Similarly, the distance through which the broken rock is moved is minimized. The greatest planned haulage distance between drawpoint and apron feeder is about 200 feet and the average is only about feet. This permits efficient use of front end load, load-haul units which are operated independently by one man and are effective in cleaning their own roadways as well as in pushing aside oversize chunks for later blasting.
As the broken rock is withdrawn from each drawpoint 24, it
. is desirably loaded onto an apron feeder 25 to a crusher 26 in one of the haulage level accessways 22 located as close to the production area as feasible. From the crusher the crushed rock is desirably moved by conveyor 27 through an upwardly inclined conveyor way 28 to a surge bin 29 above the loading pocket 20 from which it is hoisted to the surface. The apron feeder, belt conveyor and crusher installations are uniform so that the units can be moved readily and used at successive locations as the excavation proceeds. This limits the amount of large machinery that has to be taken underground and requires a minimum of labor After primary crushing the rock can be efficiently moved by belt conveyors. The rock may be removed to the surface by hoisting, or by conveyor through an inclined entryway, or mixed with water and pumped.
Excavation is advanced in a generally circular pattern by blasting rings of long holes toward the slot 19 and drawing broken rock from drawpoints 24 starting with that drawpoint which underlies the slot. Mining is continued from either one or both sides of the slot which, of course, increases in size as mining proceeds until the cylindrical annulus is generally complete. The general layout of long-hole drilling is shown schematically in lfig. where the lines identified by numeral 30 indicate the general pattern of drill holes. An appropriate charge in each drill hole is detonated to break the rock, working initially from the circular haulageway 23 and then from drill drives 17A and 18A and finally from drill drives 17 and 18. This mining method is known variously as sublevel stoping, sublevel stoping with long holes or simply long-hole stoping. A general description of blast hole drilling is found in the Canadian Mining and Metallurgical Bulletin for Oct. 1953, pages 622-633.
Appropriate sumps 31 are provided as needed and sump pumps 32 remove unwanted water from the excavation. Fresh air is circulated from a downcast shaft, preferably the smaller man shaft 15, through the working places and thence to an upcast shaft, preferably the larger hoisting shaft 14.
It will be seen that the generally circular configuration of the excavation minimizes the distance over which broken rock must be moved between the bottom of the excavation and the bottom of the hoisting shaft. Similarly the length of accessways leading from the shaft to the working places is minimized. A maximum tonnage of rock can be excavated to create the greatest possible volume of space by mining from one or both sides'of one or more slots.
The long-hole drilling method of mining is utilized so as to minimize the amount of preproduction work and the distance through which rock, supplies, equipment and men must be moved while maintaining high standards of safety, ventilation and efficiency. Excavation is accomplished with a minimum of undercutting, raising and other preparation. The excavation is sufficiently stable that use can be made of the space, as well as of the rock produced. Preproduction time and costs are minimized and ultimate costs of producing rock and space are minimized. The excavation system is adaptable to a range of moderate and high rate of production. Because access can be provided through shafts bored and cased from the surface, the excavation is readily adaptable to fast low-cost production of stone or rock from a mass of strong rock which does not appear at the surface but is covered by marsh or even shallow water, by weak or saturated strata or other cover through which the sinking and operation of conventional shafts is slow, costly or hazardous. Large volumes of low-cost stone can be produced at many convenient locations without any appreciable permanent change of surface topography without preempting any large area of the surface even during production. Even though the excavation is intended to be made in strong compact tight rock, the system is adaptable to use in many localities where rock is less than ideal in these respects.
As best seen in FIGS. 8 and 9, after one unit excavation has been nearly completed, the accessways which have been provided for the first may be used for a second unit or a number of successive similar units. The first stope, indicated generally at 33, is nearly completed except for a pillar 34 which is left in place until the second stope, indicated generally at 35, is complete. The slot raise 36 in the second excavation is located on the far side, as indicated. An interconnecting accessway 37 is provided for circulation of fresh air to the second excavation and a passage 38 is provided to exhaust air. An interconnecting haulageway 39 is provided for removing rock from the second excavation to the bottom of the hoisting shaft 14 of the first excavation.
Alternatively for excavations of lesser height, several concentric toroids may be executed to get the required volume. This may be done by extending the radial accessways and haulageways, in which event a pillar is left unexcavated in the first stope until the second stope is completed. Or better, a second toroid is excavated inside the first. This becomes more practicable as the height is reduced because, to be in good proportion, the pillar between the concentric excavations would not have to be so thick.
Some uses of the underground toroid space, such as disposal of solid wastes, are compatible with continued mining. In such cases, one completed segment of the toroid is put to use while excavation of other segments continues. Where separation is needed, mining can be stopped at any point of circumference, a vertical pillar left and mining resumed beyond a new slot.
A typical 10,000,000 ton toroid of the general configuration shown in FIGS. 1 through 4, may have an outside diameter of about 950 feet, a height of about 375 feet and a maximum thickness of about I40 feet. The top drill level is about feet from the top of the excavation. The middrill level is about 165 feet below the top drill level and about feet above the haulage level. The core of the annular excavation has a diameter of about 675 feet sufficient to support a substantial part of the stress increment which results from the excavation.
The embodiments of the invention in which we claim an exclusive property or privilege are defined as follows:
1. A system of excavation deep in the'earth which comprises the steps of:
A. providing an entranceway at least to the lowermost level of the excavation,
B. providing a shaft lying generally near the vertical axis of the excavation,
C. developing haulageways extending generally radially from said shaft adjacent the bottom of the excavation,
D. providing a rock-loading station at the bottom of said en tranceway,
E. developing at least one generally circular drill drive around but spaced from said shaft and accessible from said shaft,
F. developing at least one vertical slot raise from said drill drive and connecting with one of said haulageways,
G. blasting rings of long holes toward said slot and drawing the resulting broken rock from the haulageway from the bottom of said slot, and
H. advancing the excavation in a generally circular pattern by continued blasting and withdrawal of rock to form a toroidal excavation spaced from sand surrounding said axis.
2. A system according to claim 1 further characterized in that said entranceway includes a first shaft utilized as a hoisting shaft and a second smaller diameter man shaft is sunk generally parallel to the first and spaced therefrom.
3. A system according to claim 2 further characterized in that air is forced down said smaller shaft past working places on each level and returned to the surface through said hoisting shaft.
4. A system according to claim 1 further characterized in that a haulageway is developed at the bottom of the excavation connecting with the generally radial haulageways and extending in a generally circular ring around but spaced from said shaft.
5. A system according to claim 4 further characterized in that a pair of concentric circular inner and outer drill drives are developed at each drill level, each connected by generally radial accessways to said shaft, said accessways being spaced upwardly from said haulageways.
6. A system according to claim 5 further characterized in that at least two vertically spaced apart drill levels are established.
7. A system according to claim 5 further characterized in that passways are developed from said accessways to the loading station for removal of rock from preparatory workings.
8. A system according to claim 1 further characterized in that crushing means are provided in said haulageways adjacent the production area for subsurface crushing of rock before delivery to said loading point.
9. A system according to claim 1 further characterized in that the excavation is advanced by progressively drilling and blasting on both .sides of said slot.
10. A system according to claim 1 further characterized in that upon substantial completion of the excavation:
A. interconnecting accessways and haulageways are prepared extending from the first excavation to a nearby site for a second excavation,
B. accessways, drill drives and haulageways are developed for said second excavation,
C. at least one vertical slot raise is developed from said drill drives and connecting with one of said haulageways of said second excavation, and
D. excavation of the second excavation is advanced by progressively drilling and blasting adjacent said slot, drawing the broken rock from the bottom of the slot through the haulageways to the loading station at the bottom of the first excavation.
11. A system according to claim 10 further characterized in that said second excavation is formed concentric with the first excavation.

Claims (11)

1. A system of excavation deep in the earth which comprises the steps of: A. providing an entranceway at least to the lowermost level of the excavation, B. providing a shaft lying generally near the vertical axis of the excavation, C. developing haulageways extending generally radially from said shaft adjacent the bottom of the excavation, D. providing a rock-loading station at the bottom of said entranceway, E. developing at least one generally circular drill drive around but spaced from said shaft and accessible from said shaft, F. developing at least one vertical slot raise from said drill drive and connecting with one of said haulageways, G. blasting rings of long holes toward said slot and drawing the resulting broken rock from the haulageway from the bottom of said slot, and H. advancing the excavation in a generally circular pattern by continued blasting and withdrawal of rock to form a toroidal excavation spaced from sand surrounding said axis.
2. A system according to claim 1 further characterized in that said entranceway includes a first shaft utilized as a hoisting shaft and a second smaller diameter man shaft is sunk generally parallel to the first and spaced therefrom.
3. A system according to claim 2 further characterized in that air is forced down said smaller shaft past working places on each level and returned to the surface through said hoisting shaft.
4. A system according to claim 1 further characterized in that a haulageway is developed at the bottom of the excavation connecting with the generally radial haulageways and extending in a generally circular ring around but spaced from said shaft.
5. A system according to claim 4 further characterized in that a pair of concentric circular inner and outer drill drives are developed at each drill level, each connected by generally radial accessways to said shaft, said accessways being spaced upwardly from said haulageways.
6. A system according to claim 5 further characterized in that at least two vertically spaced apart drill levels are established.
7. A system according to claim 5 further characterized in that passways are developed from said accessways to the loading station for removal of rock from preparatory workings.
8. A system according to claim 1 further characterized in that crushing means are provided in said haulageways adjacent the production area for subsurface crushing of rock before delivery to said loading point.
9. A system according to claim 1 further characterized in that the excavation is advanced by progressively drilling and blasting on both sides of said slot.
10. A system according to claim 1 further characterized in that upon substantial completion of the excavation: A. interconnecting accessways and haulageways are prepared extending from the first excavation to a nearby site for a second excavation, B. accessways, drill drives and haulageways are developed for said second excavation, C. at least one vertical slot raise is developed from said drill drives and connecting with one of said haulageways of said second excavation, and D. excavation of the second excavation is advanced by progressively drilling and blasting adjacent said slot, drawing the broken rock from the bottom of the slot through the haulageways to the loading station at the bottom of the first excavation.
11. A system according to claim 10 further characterized in that said second excavation is formed concentric with the first excavation.
US818986A 1969-04-24 1969-04-24 Toroid excavation system Expired - Lifetime US3582138A (en)

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
US81898669A 1969-04-24 1969-04-24

Publications (1)

Publication Number Publication Date
US3582138A true US3582138A (en) 1971-06-01

Family

ID=25226937

Family Applications (1)

Application Number Title Priority Date Filing Date
US818986A Expired - Lifetime US3582138A (en) 1969-04-24 1969-04-24 Toroid excavation system

Country Status (1)

Country Link
US (1) US3582138A (en)

Cited By (28)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3692364A (en) * 1969-10-31 1972-09-19 Sune Torsten Henriksson Method of open-pit mining
US4043598A (en) * 1975-08-08 1977-08-23 Occidental Oil Shale, Inc. Multiple zone preparation of oil shale retort
US4043597A (en) * 1975-08-08 1977-08-23 Occidental Oil Shale, Inc. Multiple level preparation of oil shale retort
US4072351A (en) * 1977-01-24 1978-02-07 Roye Henry L Radial mining method
US4452489A (en) * 1982-09-20 1984-06-05 Methane Drainage Ventures Multiple level methane drainage shaft method
US4690058A (en) * 1986-04-09 1987-09-01 C-I-L Inc. Smooth wall blasting in rock
US4938536A (en) * 1989-11-22 1990-07-03 Lee Raymond C Conic mass caving structure and method
US20020096336A1 (en) * 1998-11-20 2002-07-25 Zupanick Joseph A. Method and system for surface production of gas from a subterranean zone
US20020189801A1 (en) * 2001-01-30 2002-12-19 Cdx Gas, L.L.C., A Texas Limited Liability Company Method and system for accessing a subterranean zone from a limited surface area
US20040007390A1 (en) * 2002-07-12 2004-01-15 Zupanick Joseph A. Wellbore plug system and method
US20040050554A1 (en) * 2002-09-17 2004-03-18 Zupanick Joseph A. Accelerated production of gas from a subterranean zone
US20050115709A1 (en) * 2002-09-12 2005-06-02 Cdx Gas, Llc Method and system for controlling pressure in a dual well system
US6942030B2 (en) * 2002-09-12 2005-09-13 Cdx Gas, Llc Three-dimensional well system for accessing subterranean zones
US6964308B1 (en) 2002-10-08 2005-11-15 Cdx Gas, Llc Method of drilling lateral wellbores from a slant well without utilizing a whipstock
US6964298B2 (en) 1998-11-20 2005-11-15 Cdx Gas, Llc Method and system for accessing subterranean deposits from the surface
US6976533B2 (en) 1998-11-20 2005-12-20 Cdx Gas, Llc Method and system for accessing subterranean deposits from the surface
US6991047B2 (en) 2002-07-12 2006-01-31 Cdx Gas, Llc Wellbore sealing system and method
US7025154B2 (en) 1998-11-20 2006-04-11 Cdx Gas, Llc Method and system for circulating fluid in a well system
US7048049B2 (en) 2001-10-30 2006-05-23 Cdx Gas, Llc Slant entry well system and method
US7100687B2 (en) 2003-11-17 2006-09-05 Cdx Gas, Llc Multi-purpose well bores and method for accessing a subterranean zone from the surface
US7134494B2 (en) 2003-06-05 2006-11-14 Cdx Gas, Llc Method and system for recirculating fluid in a well system
US7207395B2 (en) 2004-01-30 2007-04-24 Cdx Gas, Llc Method and system for testing a partially formed hydrocarbon well for evaluation and well planning refinement
US7222670B2 (en) 2004-02-27 2007-05-29 Cdx Gas, Llc System and method for multiple wells from a common surface location
US7264048B2 (en) 2003-04-21 2007-09-04 Cdx Gas, Llc Slot cavity
US20080060571A1 (en) * 1998-11-20 2008-03-13 Cdx Gas, Llc. Method and system for accessing subterranean deposits from the surface and tools therefor
US7360595B2 (en) 2002-05-08 2008-04-22 Cdx Gas, Llc Method and system for underground treatment of materials
US7571771B2 (en) 2005-05-31 2009-08-11 Cdx Gas, Llc Cavity well system
WO2011000038A1 (en) 2009-06-30 2011-01-06 Technological Resources Pty. Limited Underground mining

Cited By (54)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3692364A (en) * 1969-10-31 1972-09-19 Sune Torsten Henriksson Method of open-pit mining
US4043598A (en) * 1975-08-08 1977-08-23 Occidental Oil Shale, Inc. Multiple zone preparation of oil shale retort
US4043597A (en) * 1975-08-08 1977-08-23 Occidental Oil Shale, Inc. Multiple level preparation of oil shale retort
US4072351A (en) * 1977-01-24 1978-02-07 Roye Henry L Radial mining method
US4452489A (en) * 1982-09-20 1984-06-05 Methane Drainage Ventures Multiple level methane drainage shaft method
US4611855A (en) * 1982-09-20 1986-09-16 Methane Drainage Ventures Multiple level methane drainage method
US4690058A (en) * 1986-04-09 1987-09-01 C-I-L Inc. Smooth wall blasting in rock
US4938536A (en) * 1989-11-22 1990-07-03 Lee Raymond C Conic mass caving structure and method
US6976533B2 (en) 1998-11-20 2005-12-20 Cdx Gas, Llc Method and system for accessing subterranean deposits from the surface
US8505620B2 (en) 1998-11-20 2013-08-13 Vitruvian Exploration, Llc Method and system for accessing subterranean deposits from the surface and tools therefor
US8297350B2 (en) 1998-11-20 2012-10-30 Vitruvian Exploration, Llc Method and system for accessing subterranean deposits from the surface
US9551209B2 (en) 1998-11-20 2017-01-24 Effective Exploration, LLC System and method for accessing subterranean deposits
US8813840B2 (en) 1998-11-20 2014-08-26 Efective Exploration, LLC Method and system for accessing subterranean deposits from the surface and tools therefor
US20020096336A1 (en) * 1998-11-20 2002-07-25 Zupanick Joseph A. Method and system for surface production of gas from a subterranean zone
US8511372B2 (en) 1998-11-20 2013-08-20 Vitruvian Exploration, Llc Method and system for accessing subterranean deposits from the surface
US6964298B2 (en) 1998-11-20 2005-11-15 Cdx Gas, Llc Method and system for accessing subterranean deposits from the surface
US8291974B2 (en) 1998-11-20 2012-10-23 Vitruvian Exploration, Llc Method and system for accessing subterranean deposits from the surface and tools therefor
US8297377B2 (en) 1998-11-20 2012-10-30 Vitruvian Exploration, Llc Method and system for accessing subterranean deposits from the surface and tools therefor
US8316966B2 (en) 1998-11-20 2012-11-27 Vitruvian Exploration, Llc Method and system for accessing subterranean deposits from the surface and tools therefor
US20080060571A1 (en) * 1998-11-20 2008-03-13 Cdx Gas, Llc. Method and system for accessing subterranean deposits from the surface and tools therefor
US7025154B2 (en) 1998-11-20 2006-04-11 Cdx Gas, Llc Method and system for circulating fluid in a well system
US8371399B2 (en) 1998-11-20 2013-02-12 Vitruvian Exploration, Llc Method and system for accessing subterranean deposits from the surface and tools therefor
US8376039B2 (en) 1998-11-20 2013-02-19 Vitruvian Exploration, Llc Method and system for accessing subterranean deposits from the surface and tools therefor
US8479812B2 (en) 1998-11-20 2013-07-09 Vitruvian Exploration, Llc Method and system for accessing subterranean deposits from the surface and tools therefor
US8469119B2 (en) 1998-11-20 2013-06-25 Vitruvian Exploration, Llc Method and system for accessing subterranean deposits from the surface and tools therefor
US8464784B2 (en) 1998-11-20 2013-06-18 Vitruvian Exploration, Llc Method and system for accessing subterranean deposits from the surface and tools therefor
US8434568B2 (en) 1998-11-20 2013-05-07 Vitruvian Exploration, Llc Method and system for circulating fluid in a well system
US8376052B2 (en) 1998-11-20 2013-02-19 Vitruvian Exploration, Llc Method and system for surface production of gas from a subterranean zone
US20020189801A1 (en) * 2001-01-30 2002-12-19 Cdx Gas, L.L.C., A Texas Limited Liability Company Method and system for accessing a subterranean zone from a limited surface area
US6986388B2 (en) 2001-01-30 2006-01-17 Cdx Gas, Llc Method and system for accessing a subterranean zone from a limited surface area
US7048049B2 (en) 2001-10-30 2006-05-23 Cdx Gas, Llc Slant entry well system and method
US7360595B2 (en) 2002-05-08 2008-04-22 Cdx Gas, Llc Method and system for underground treatment of materials
US6991048B2 (en) 2002-07-12 2006-01-31 Cdx Gas, Llc Wellbore plug system and method
US6991047B2 (en) 2002-07-12 2006-01-31 Cdx Gas, Llc Wellbore sealing system and method
US20040007390A1 (en) * 2002-07-12 2004-01-15 Zupanick Joseph A. Wellbore plug system and method
US6942030B2 (en) * 2002-09-12 2005-09-13 Cdx Gas, Llc Three-dimensional well system for accessing subterranean zones
US7090009B2 (en) 2002-09-12 2006-08-15 Cdx Gas, Llc Three-dimensional well system for accessing subterranean zones
US20050115709A1 (en) * 2002-09-12 2005-06-02 Cdx Gas, Llc Method and system for controlling pressure in a dual well system
US7025137B2 (en) 2002-09-12 2006-04-11 Cdx Gas, Llc Three-dimensional well system for accessing subterranean zones
US7073595B2 (en) 2002-09-12 2006-07-11 Cdx Gas, Llc Method and system for controlling pressure in a dual well system
US8333245B2 (en) 2002-09-17 2012-12-18 Vitruvian Exploration, Llc Accelerated production of gas from a subterranean zone
US20040050554A1 (en) * 2002-09-17 2004-03-18 Zupanick Joseph A. Accelerated production of gas from a subterranean zone
US6964308B1 (en) 2002-10-08 2005-11-15 Cdx Gas, Llc Method of drilling lateral wellbores from a slant well without utilizing a whipstock
US7264048B2 (en) 2003-04-21 2007-09-04 Cdx Gas, Llc Slot cavity
US7134494B2 (en) 2003-06-05 2006-11-14 Cdx Gas, Llc Method and system for recirculating fluid in a well system
US7100687B2 (en) 2003-11-17 2006-09-05 Cdx Gas, Llc Multi-purpose well bores and method for accessing a subterranean zone from the surface
US7207395B2 (en) 2004-01-30 2007-04-24 Cdx Gas, Llc Method and system for testing a partially formed hydrocarbon well for evaluation and well planning refinement
US7222670B2 (en) 2004-02-27 2007-05-29 Cdx Gas, Llc System and method for multiple wells from a common surface location
US7571771B2 (en) 2005-05-31 2009-08-11 Cdx Gas, Llc Cavity well system
WO2011000038A1 (en) 2009-06-30 2011-01-06 Technological Resources Pty. Limited Underground mining
CN102472100A (en) * 2009-06-30 2012-05-23 技术资源有限公司 Underground mining
US8905486B2 (en) * 2009-06-30 2014-12-09 Technological Resources Pty. Ltd. Underground mining
US20120200139A1 (en) * 2009-06-30 2012-08-09 Fredric Christopher Delabbio Underground mining
EP2449213A4 (en) * 2009-06-30 2019-03-06 Technological Resources PTY. Limited Underground mining

Similar Documents

Publication Publication Date Title
US3582138A (en) Toroid excavation system
US5782539A (en) Wall-to-wall surface mining process
CN104790956B (en) It is remotely controlled roadway formula exploitation end and helps coal technique
CN102168579A (en) Rib-pillar-free continuous sublevel filling method for mining preparation in medium-thickness slope crushed ore body vein
Liu et al. Key technologies of drilling process with raise boring method
CN112746847B (en) Mining method for gently-inclined medium-thickness ore body
CN110735639B (en) Open pit backfilling method after mining by open pit to underground caving method
CN111364997A (en) Upward drift-caving combined mining method
RU2344291C2 (en) System of deposit development
US3588175A (en) Methods for mining deep thick oil shale deposits
CN111058847A (en) Continuous large-aperture deep hole blasting mechanized mining method for thick and large ore body
CN106761745A (en) The outer sublevel open stope method of arteries and veins
US4458947A (en) Mining method
US3537753A (en) Oil shale mining method
CN104179505A (en) Phosphorus ore underground mining method
US10267147B2 (en) Surface access borehole resource extraction method
RU2224107C1 (en) Process of opencast-underground mining of mineral resources
CN112901175A (en) Method for constructing underground laboratory spiral downward slope by applying TBM
Abzalov et al. Mining methods
RU2158826C2 (en) Method of mine construction for small kimberlite pipes by means of self-propelled mining machinery and complex for its lowering and lifting and ore delivery to surface
RU2059073C1 (en) Method for development of mineral deposits
RU2187646C2 (en) Method of opencast mining of beded mineral deposits
RU2762170C1 (en) Method for developing thin and low-powered steel-falling ore bodies
Kalmykov et al. Justification of the technology of construction of mine shafts for the conditions of the maly kuibas deposit
US3716272A (en) Method of creating large diameter cylindrical cavities by solution mining