USRE36360E - Method for determining flexible demand in a manufacturing process - Google Patents

Method for determining flexible demand in a manufacturing process Download PDF

Info

Publication number
USRE36360E
USRE36360E US08/907,848 US90784897A USRE36360E US RE36360 E USRE36360 E US RE36360E US 90784897 A US90784897 A US 90784897A US RE36360 E USRE36360 E US RE36360E
Authority
US
United States
Prior art keywords
flex
period
day
periods
demand
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
US08/907,848
Inventor
John R. Costanza
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JCIT INTERNATIONAL Inc
John Costanza Institute of Technology Inc
Original Assignee
John Costanza Institute of Technology Inc
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by John Costanza Institute of Technology Inc filed Critical John Costanza Institute of Technology Inc
Priority to US08/907,848 priority Critical patent/USRE36360E/en
Application granted granted Critical
Publication of USRE36360E publication Critical patent/USRE36360E/en
Assigned to SILICON VALLEY BANK reassignment SILICON VALLEY BANK SECURITY AGREEMENT Assignors: DEMAND FLOW INSTITUTE, LLC
Assigned to JCIT INTERNATIONAL, INC. reassignment JCIT INTERNATIONAL, INC. ASSIGNMENT OF ASSIGNORS INTEREST (SEE DOCUMENT FOR DETAILS). Assignors: DEMAND FLOW INSTITUTE, LLC, A COLORADO CORPORATION
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06315Needs-based resource requirements planning or analysis
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling

Definitions

  • This invention relates to computer systems and more particularly to such systems used in manufacturing planning. Even more particularly, the invention relates to a computer system method for determining the demand for purchased materials independent of the manufacturing production demand.
  • MRP Manufacturing Resource Planning
  • JIT Just-In-Time
  • the manufacturing lead time The number of days that it takes to complete a product from the time the first, lowest-level, manufactured component or subassembly is produced until the final product is shipped is called the manufacturing lead time.
  • a long lead time caused by the subassembly manufacturing techniques, makes it difficult to react quickly to changing customer demand.
  • Another object is to modify this projection each time new information is input to the system.
  • a further object is to restrict the modification to specific time periods.
  • the above and other aspects of the invention are accomplished in a system that determines the total demand for a product for each day over four time periods specified by the user of the system.
  • the total demand cannot be altered, since this quantity of products is already in production.
  • the flex fence periods the total demand for each day can vary by a percentage amount determined by the user.
  • Each period can have a different percentage, and each period can have a different number of days, however all days within a period use the percentage for the period.
  • the system produces orders for raw material sufficient to build the total demand plus the flex fence percentage.
  • the system has the flexibility to expand up to the amounts determined by the flex fences.
  • the system will recalculate total demand for all days beyond the demand fence date and prior to the order date to attempt to produce the total demand quantity necessary to fulfill the order.
  • the system uses a formula that adjusts the quantities in a manner that prevents the total demand quantity for any day from exceeding the amount of material that was ordered for that day.
  • FIG. 1 shows a prior art manufacturing system
  • FIG. 2 shows a block diagram of a computer system and the software of the present invention
  • FIG. 3 shows a top level flowchart of the present invention
  • FIG. 4 shows a flowchart of the determine flex limits method of the invention
  • FIG. 5 shows a flowchart of the smoothing method of the invention
  • FIG. 6 shows a flowchart of the smoothing method for a single day
  • FIG. 7 shows a screen display from the invention containing an example of the results of applying the method of the invention.
  • FIG. 1 shows a prior art manufacturing method.
  • customer orders 102 and a marketing forecast 104 are input to a master schedule 106.
  • the master schedule 106 may be created by software or manually. It is typically done manually.
  • work orders 108 are created for the quantity of products to be produced.
  • a material planning system creates purchase orders for the amount of material needed to build the quantity of products and sends these purchase orders to purchasing, where vendors are contacted to procure the material.
  • FIG. 2 shows a block diagram of the hardware and software of the invention.
  • a computer system 100 contains a processing element 102 which communicates to other elements of the computer system 100 over a system bus 104.
  • a keyboard 106 allows user of the system 100 to input commands and data into the computer system 100, such as customer orders and marketing forecast data.
  • a mouse 110 allows the user to input graphical information into the computer system 100.
  • a display 108 allows the computer system 100 to output information to the user of the system.
  • a disk 112 stores the software of the present invention as well as all the data collected or calculated by the present invention.
  • a memory 114 contains an operating system 116 which is used by the present invention to access the keyboard 106, graphics display 108, mouse 110, disk 112, as well as other elements of the computer system 100.
  • the total demand method software 120, of the present invention is part of the "FLOWPOWER"(TM) manufacturing software 118 which performs other "DEMAND FLOW”(TM) manufacturing software functions for the user of the system.
  • FLOWPOWER is a trademark of Nexteqx International, Inc.
  • DEMANDFLOW is a trademark of JIT Institute of Technology, Inc.
  • FIG. 3 shows the stop level flowchart of the total demand method of the present invention. This method is called ftom the FLOWPOWER(TM) manufacturing software system 118 (FIG. 2) when a total demand quantity calculation is desired.
  • block 302 gets customer or marketing orders, typically entered by a user on the keyboard 106 (FIG. 2). Marketing orders are for products that will be placed in finished goods, awaiting customer purchase. These orders extend for the number of days that includes four time periods, each set by the user of the system. The first time period is the time up to a demand fence. This is the time from the current day up to a point within which the total demand quantity cannot be altered because this quantity is currently being manufactured. This period might typically be a few days, however, it could be longer based upon the manufacturing lead time and the time necessary to acquire raw materials.
  • the next three time periods are called flex fences, since the total demand quantity of product to be produced during these periods is flexible, within percentage limits set by the user.
  • the user can set different flex percentages for each of the periods, and these percentages reflect the amount of variance allowable in the total demand quantity to be produced during these periods.
  • block 302 transfers to block 304 which obtains a marketing forecast for these same time periods.
  • Block 306 determines the total demand for each date within the four periods. Within the first period, before the demand fence, the system selects only customer orders or marketing orders for shipment to finished goods. Beyond the first period, the system selects the greater of orders or marketing forecast as the total demand for each day. Block 308 then calls FIG. 4 to determine the flex limits for each day within the periods.
  • block 310 determines whether the total demand is greater than the flex limit for any of the days within the four periods. If not, block 310 transfers to block 316 which prints order quantities for the amount of raw material necessary to build the quantity of product determined by the upper flex limit for each day. This information is then sent to a purchasing system, which may determine the amount of raw material already on hand and order only the additional material needed.
  • block 310 goes to block 312 which calls FIG. 5 to attempt to smooth the total demand quantity for previous days in order to provide the requested quantity.
  • Block 314 determines if the smoothing was successful, and if so, transfers to block 316 to print the order for the raw material.
  • block 314 transfers back to block 318 which displays an error message showing that the total demand quantity violates the amount of raw material available. Control then goes back to block 302 to allow the user to correct the situation.
  • FIG. 4 shows a flowchart of the determine flex limits process called from FIG. 3, block 308.
  • the flex limits are set using the formula:
  • Dr ffL is the Flex fence Limit Value for the future period
  • Dr is the daily rate for Total Demand
  • X is the flex percentage for the period
  • N is the future flex period
  • block 402 gets the total demand for the demand fence day, that is, the last day prior to the first flex period, and block 404 then sets the variable PERIOD to 1.
  • Block 406 gets the flex percent for the period set in the PERIOD variable. This value is input by the user of the system to allow the user to set the maximum total demand quantity for each of the three flex periods. The flex percentage for each period is set separately, allowing the user to set the same or a different percentage for each period.
  • Block 410 sets the value of a variable MULTIPLIER1 to one plus the flex percent divided by 100. For example, if the flex percent is 10%, MULTIPLIER1 would be set to 1.1.
  • Block 412 sets the value of a variable MULTIPLIER2 to the value of MULTIPLIER1 raised to the power of the variable PERIOD, and block 414 then sets the flex limit for the period to the total demand multiplied by MULTIPLIER2.
  • Block 416 puts the flex limit for the period into each day of the period, and block 418 increments the PERIOD variable. If all three periods have not yet been calculated, block 420 returns to block 406 to calculate the next period, otherwise, block 420 returns to FIG. 3.
  • FIG. 5 shows a flowchart of the smooth demand process called from block 312 of FIG. 3.
  • This process attempts to adjust the total demand in all days prior to a customer order required date in order to satisfy a large demand on the customer order date. To accomplish this, it processes each day of the four periods to determine if the total demand for that day exceeds the flex limit for the day, and if it does, each previous day is then processed to determine if the total demand can be increased.
  • block 502 sets the value of a variable DAY to 0.
  • Block 504 increments DAY, and block 506 determines if the total demand for the day exceeds the flex limit for the day. If the flex limit is not exceeded, block 506 transfers back to block 504 to process the next day.
  • block 506 goes to block 508 which determines whether the date for this day occurs before the demand fence. Since the total demand cannot be altered before the demand fence, if this day occurs before the demand fence, block 508 goes to block 516 which sets a smooth not successful flag before returning to FIG. 3.
  • block 508 goes to block 510 which calls FIG. 6 to attempt to smooth the total demand for this day.
  • block 512 determines if the process of FIG. 6 was successful, and if not, block 512 goes to block 516 which returns a not successful flag to FIG. 3, indicating the smoothing is not possible.
  • block 512 goes to block 514 which determines if all days have been processed, and if not, block 514 returns to block 504 to process the next day.
  • the number of days to be processed is determined by the size of the flex periods set by the user of the system.
  • block 514 returns to FIG. 3 indicating that smoothing was successful.
  • FIG. 6 shows a flowchart of the smoothing method for a single day called from block 510 of FIG. 5.
  • block 602 sets TARGET, which is the customer required ship date, to the current DAY, since this process will attempt to smooth the total demand for this day.
  • Block 604 sets the SMOOTH AMOUNT to the total demand of the target day minus the flex demand for the target day, thus SMOOTH AMOUNT is the quantity that must be increased in previous days in order to provide the requested quantity on the target day.
  • Block 606 decrements DAY, and block 610 determines if all days have been processed. Since the total demand for days before the demand fence cannot be altered, there is no need to process any days earlier than the demand fence. If all days have been processed, block 610 goes to block 616 which sets the smooth not successful flag. Block 630 then resets the value of DAY before returning to FIG. 5.
  • block 610 goes to block 614 which calculates the increase available for this day as the flex demand for the day less the total demand for the day. Block 618 then determines if any increase is possible, and if not, goes to block 606 to process the next day.
  • block 618 goes to block 620 which determines whether the amount available for this day is less than the smooth amount, thus whether this day can absorb the entire remaining smooth amount. If not, block 620 goes to block 622 which decreases the smooth amount by the amount available for this day, and block 624 sets the total demand for this day to the flex demand, thus raising the total demand for this day to the maximum. Block 624 then returns to block 606 to process the next day.
  • block 620 goes to block 626 which increases the total demand for this day by the smooth amount.
  • Block 628 sets the smooth successful flag before transferring to block 630 to return to FIG. 5.
  • FIG. 7 shows an example output screen using this method.
  • screen 702 contains a flex fence area 704 which indicates the flex fence values, in percentages and actual quantity, for the four periods.
  • the first period 706 is the demand fence, and the range (percentage) for this period is zero, since the total demand cannot be changed within the demand fence.
  • the range indicates the percentage of flex, and the range in units indicates the amount in units that the total demand for each day in the period can be increased or decreased.
  • the smoothing method of the present invention adjusts total demand quantity to meet a requirement.
  • the total demand for each day is 120 units, and the demand fence occurs at day 2.
  • the flex percentage is 10% and the number of days in the period is 4.
  • the flex percentage is 9% and the number of days in the period is 8.
  • the flex percentage is 8%, and the number of days in the period is 12.
  • Table 1 shows the total demand and actual orders for the next 9 days.
  • Table 2 shows the addition of a customer order for 325 units at day 5.
  • the flex limit for days 1 and 2 cannot be changed, since they are within the demand fence of 2 days.
  • the flex limit for days 3-5 is 132, that is 120, [1.1] 1 .
  • This new customer order causes the total demand for day 5 to exceed the flex limit for day, therefore the system must smooth the additional amount over the previous two days, if possible.
  • Table 3 shows the result of processing by the smoothing method of FIGS. 5 and 6, described above.

Abstract

A system that determines the total demand for a product for each day over four time periods specified by the user of the system. Within the first time period, from the current date up to a demand fence, the total demand cannot be altered. For the next three periods, called the flex fence periods, the total demand for each day can vary by a percentage amount set by the user. If an order exceeding capacity is received for a date beyond the demand fence, the system will recalculate total demand for all days beyond the demand fence and prior to the order date to attempt to produce the total demand quantity necessary to fulfill the order. In calculating the increased quantities, the system uses a formula that prevents the total demand quantity for any day from exceeding the amount of material that was ordered for that day.

Description

This application is a continuation of application Ser. No. 07/884,599, filed May 15, 1992, now abandoned.
FIELD OF THE INVENTION
This invention relates to computer systems and more particularly to such systems used in manufacturing planning. Even more particularly, the invention relates to a computer system method for determining the demand for purchased materials independent of the manufacturing production demand.
BACKGROUND OF THE INVENTION
Traditional manufacturing systems use customer orders and marketing forecasts to predict the quantity of product needed at any given time. This process is based upon scheduled batch manufacturing techniques where products are created based upon a weekly or monthly schedule. Usually these products are produced as subassemblies or fabricated parts which are scheduled based upon the monthly requirement of the finished products. These subassemblies are then assembled into the final product to fill the customer orders, or placed into finished goods.
Formalized computer systems have been developed to assist in the traditional scheduling and tracking of these batch subassemblies or fabricated parts, as well as buying the required raw material. These systems are called Manufacturing Resource Planning (MRP) systems. The prevailing manufacturing methodology in the Far East, commonly referred to by the adopting Japanese as Kanban Flow Manufacturing, is often called Just-In-Time (JIT) by western manufacturers.
In traditional batch manufacturing, raw material is ordered well in advance and kept in a storeroom. Once the assembly or fabricated part is scheduled, a work order is released, and the parts required to produce the assembly are issued based upon a planned start date and start quantity. Subassembly parts are often produced in the same manner as the final product, thus, after being produced, the subassemblies are stored until they are needed for a final assembly. Because of the length of the process, a large inventory of finished goods is often needed to satisfy a fluctuating customer demand. This schedulized manufacturing makes customer responsiveness very slow.
The number of days that it takes to complete a product from the time the first, lowest-level, manufactured component or subassembly is produced until the final product is shipped is called the manufacturing lead time. A long lead time, caused by the subassembly manufacturing techniques, makes it difficult to react quickly to changing customer demand. The lengthy process of long manufacturing lead times, queues for each subassembly, and frequent trips to the storeroom place a long period of time between the customer's order and manufacturing's completion of that order.
One of the more significant problems caused by this process is that the production schedule is created well in advance, and cannot be altered easily. Because of this, the software used in this process also lacks the ability to easily adjust schedules. If the manufacturing process is to become more flexible, the system software used for scheduling must also become more flexible. In the traditional system, however, the production quantity, or total demand, is manually set by a master scheduler, and cannot easily be adjusted.
It is thus apparent that there is a need in the art for an improved method or apparatus which automatically determines the total demand on a daily basis. There is a further need in the art for such a system that can automatically adjust the demand, within customer supplied limits, to allow the quantity to vary for future dates. The present invention meets these and other needs.
SUMMARY OF THE INVENTION
It is an aspect of the present invention to determine the total product demand in a manufacturing system.
It is another aspect of the invention to project the demand on a daily basis.
Another object is to modify this projection each time new information is input to the system.
A further object is to restrict the modification to specific time periods.
The above and other aspects of the invention are accomplished in a system that determines the total demand for a product for each day over four time periods specified by the user of the system. Within the first time period, from the current date up to a demand fence, the total demand cannot be altered, since this quantity of products is already in production. For the next three periods beyond the demand fence, called the flex fence periods, the total demand for each day can vary by a percentage amount determined by the user. Each period can have a different percentage, and each period can have a different number of days, however all days within a period use the percentage for the period.
Once the quantities within the periods have been determined, the system produces orders for raw material sufficient to build the total demand plus the flex fence percentage. Thus the system has the flexibility to expand up to the amounts determined by the flex fences.
If an order is received for a date beyond the demand fence, and the order is larger that the total demand for that date, the system will recalculate total demand for all days beyond the demand fence date and prior to the order date to attempt to produce the total demand quantity necessary to fulfill the order.
In calculating the quantity from the flex fence percentages, the system uses a formula that adjusts the quantities in a manner that prevents the total demand quantity for any day from exceeding the amount of material that was ordered for that day.
BRIEF DESCRIPTION OF THE DRAWINGS
The above and other aspects, features, and advantages of the invention will be better understood by reading the following more particular description of the invention, presented in conjunction with the following drawings, wherein:
FIG. 1 shows a prior art manufacturing system;
FIG. 2 shows a block diagram of a computer system and the software of the present invention;
FIG. 3 shows a top level flowchart of the present invention;
FIG. 4 shows a flowchart of the determine flex limits method of the invention;
FIG. 5 shows a flowchart of the smoothing method of the invention;
FIG. 6 shows a flowchart of the smoothing method for a single day; and
FIG. 7 shows a screen display from the invention containing an example of the results of applying the method of the invention.
DESCRIPTION OF THE PREFERRED EMBODIMENT
The following description is of the best presently contemplated mode of carrying out the present invention. This description is not to be taken in a limiting sense but is made merely for the purpose of describing the general principles of the invention. The scope of the invention should be determined by referencing the appended claims.
FIG. 1 shows a prior art manufacturing method. Referring now to FIG. 1, customer orders 102 and a marketing forecast 104 are input to a master schedule 106. The master schedule 106 may be created by software or manually. It is typically done manually. Once the master schedule is determined, work orders 108 are created for the quantity of products to be produced. Once the work orders 108 have been created, a material planning system creates purchase orders for the amount of material needed to build the quantity of products and sends these purchase orders to purchasing, where vendors are contacted to procure the material.
FIG. 2 shows a block diagram of the hardware and software of the invention. Referring now to FIG. 2, a computer system 100 contains a processing element 102 which communicates to other elements of the computer system 100 over a system bus 104. A keyboard 106 allows user of the system 100 to input commands and data into the computer system 100, such as customer orders and marketing forecast data. Optionally, a mouse 110, allows the user to input graphical information into the computer system 100. A display 108 allows the computer system 100 to output information to the user of the system. A disk 112 stores the software of the present invention as well as all the data collected or calculated by the present invention.
A memory 114 contains an operating system 116 which is used by the present invention to access the keyboard 106, graphics display 108, mouse 110, disk 112, as well as other elements of the computer system 100. The total demand method software 120, of the present invention, is part of the "FLOWPOWER"(™) manufacturing software 118 which performs other "DEMAND FLOW"(™) manufacturing software functions for the user of the system. FLOWPOWER is a trademark of Nexteqx International, Inc., and DEMANDFLOW is a trademark of JIT Institute of Technology, Inc.
FIG. 3 shows the stop level flowchart of the total demand method of the present invention. This method is called ftom the FLOWPOWER(™) manufacturing software system 118 (FIG. 2) when a total demand quantity calculation is desired. Referring now to FIG. 3, after entry, block 302 gets customer or marketing orders, typically entered by a user on the keyboard 106 (FIG. 2). Marketing orders are for products that will be placed in finished goods, awaiting customer purchase. These orders extend for the number of days that includes four time periods, each set by the user of the system. The first time period is the time up to a demand fence. This is the time from the current day up to a point within which the total demand quantity cannot be altered because this quantity is currently being manufactured. This period might typically be a few days, however, it could be longer based upon the manufacturing lead time and the time necessary to acquire raw materials.
The next three time periods are called flex fences, since the total demand quantity of product to be produced during these periods is flexible, within percentage limits set by the user. The user can set different flex percentages for each of the periods, and these percentages reflect the amount of variance allowable in the total demand quantity to be produced during these periods.
After obtaining customer orders, block 302 transfers to block 304 which obtains a marketing forecast for these same time periods. Block 306 determines the total demand for each date within the four periods. Within the first period, before the demand fence, the system selects only customer orders or marketing orders for shipment to finished goods. Beyond the first period, the system selects the greater of orders or marketing forecast as the total demand for each day. Block 308 then calls FIG. 4 to determine the flex limits for each day within the periods.
After determining the flex limits, block 310 determines whether the total demand is greater than the flex limit for any of the days within the four periods. If not, block 310 transfers to block 316 which prints order quantities for the amount of raw material necessary to build the quantity of product determined by the upper flex limit for each day. This information is then sent to a purchasing system, which may determine the amount of raw material already on hand and order only the additional material needed.
If the total demand for any day exceeds the flex limit for the day, block 310 goes to block 312 which calls FIG. 5 to attempt to smooth the total demand quantity for previous days in order to provide the requested quantity. Block 314 determines if the smoothing was successful, and if so, transfers to block 316 to print the order for the raw material.
If the smoothing was not successful, block 314 transfers back to block 318 which displays an error message showing that the total demand quantity violates the amount of raw material available. Control then goes back to block 302 to allow the user to correct the situation.
FIG. 4 shows a flowchart of the determine flex limits process called from FIG. 3, block 308. The flex limits are set using the formula:
Dr.sub.ffL DR[1+X%/100].sup.N
where:
DrffL is the Flex Fence Limit Value for the future period
Dr is the daily rate for Total Demand
X is the flex percentage for the period
N is the future flex period
For Example, consider three future periods having flex percentages of 10%, 9%, and 8% respectively, and the daily rate total demand at the beginning of the first period of 32. The maximum daily rate total demand for the days of each of these future periods would be:
______________________________________                                    
Period 1         35.20 = 32 [1 + 10/100].sup.1                            
Period 2               38.02 = 32 [1 + 9/100].sup.2                       
Period 3               40.31 = 32 [1 + 8/100].sup.3                       
______________________________________                                    
Referring now to FIG. 4, after entry, block 402 gets the total demand for the demand fence day, that is, the last day prior to the first flex period, and block 404 then sets the variable PERIOD to 1. Block 406 gets the flex percent for the period set in the PERIOD variable. This value is input by the user of the system to allow the user to set the maximum total demand quantity for each of the three flex periods. The flex percentage for each period is set separately, allowing the user to set the same or a different percentage for each period.
Block 410 then sets the value of a variable MULTIPLIER1 to one plus the flex percent divided by 100. For example, if the flex percent is 10%, MULTIPLIER1 would be set to 1.1. Block 412 sets the value of a variable MULTIPLIER2 to the value of MULTIPLIER1 raised to the power of the variable PERIOD, and block 414 then sets the flex limit for the period to the total demand multiplied by MULTIPLIER2. Block 416 puts the flex limit for the period into each day of the period, and block 418 increments the PERIOD variable. If all three periods have not yet been calculated, block 420 returns to block 406 to calculate the next period, otherwise, block 420 returns to FIG. 3.
FIG. 5 shows a flowchart of the smooth demand process called from block 312 of FIG. 3. This process attempts to adjust the total demand in all days prior to a customer order required date in order to satisfy a large demand on the customer order date. To accomplish this, it processes each day of the four periods to determine if the total demand for that day exceeds the flex limit for the day, and if it does, each previous day is then processed to determine if the total demand can be increased.
Referring now to FIG. 5, after entry, block 502 sets the value of a variable DAY to 0. Block 504 increments DAY, and block 506 determines if the total demand for the day exceeds the flex limit for the day. If the flex limit is not exceeded, block 506 transfers back to block 504 to process the next day.
If the flex limit is exceeded for this day, block 506 goes to block 508 which determines whether the date for this day occurs before the demand fence. Since the total demand cannot be altered before the demand fence, if this day occurs before the demand fence, block 508 goes to block 516 which sets a smooth not successful flag before returning to FIG. 3.
If the day is beyond the demand fence, block 508 goes to block 510 which calls FIG. 6 to attempt to smooth the total demand for this day. After returning from FIG. 6, block 512 determines if the process of FIG. 6 was successful, and if not, block 512 goes to block 516 which returns a not successful flag to FIG. 3, indicating the smoothing is not possible.
If the process of FIG. 6 was successful for this day, block 512 goes to block 514 which determines if all days have been processed, and if not, block 514 returns to block 504 to process the next day. The number of days to be processed is determined by the size of the flex periods set by the user of the system.
If all days have been processed, block 514 returns to FIG. 3 indicating that smoothing was successful.
FIG. 6 shows a flowchart of the smoothing method for a single day called from block 510 of FIG. 5. Referring now to FIG. 6, after entry, block 602 sets TARGET, which is the customer required ship date, to the current DAY, since this process will attempt to smooth the total demand for this day. Block 604 sets the SMOOTH AMOUNT to the total demand of the target day minus the flex demand for the target day, thus SMOOTH AMOUNT is the quantity that must be increased in previous days in order to provide the requested quantity on the target day.
Block 606 decrements DAY, and block 610 determines if all days have been processed. Since the total demand for days before the demand fence cannot be altered, there is no need to process any days earlier than the demand fence. If all days have been processed, block 610 goes to block 616 which sets the smooth not successful flag. Block 630 then resets the value of DAY before returning to FIG. 5.
If the day to be processed is beyond the demand fence, block 610 goes to block 614 which calculates the increase available for this day as the flex demand for the day less the total demand for the day. Block 618 then determines if any increase is possible, and if not, goes to block 606 to process the next day.
If the total demand for this day can be increased, block 618 goes to block 620 which determines whether the amount available for this day is less than the smooth amount, thus whether this day can absorb the entire remaining smooth amount. If not, block 620 goes to block 622 which decreases the smooth amount by the amount available for this day, and block 624 sets the total demand for this day to the flex demand, thus raising the total demand for this day to the maximum. Block 624 then returns to block 606 to process the next day.
If this day can absorb the total smooth amount, block 620 goes to block 626 which increases the total demand for this day by the smooth amount. Block 628 then sets the smooth successful flag before transferring to block 630 to return to FIG. 5.
FIG. 7 shows an example output screen using this method. Referring now to FIG. 7, screen 702 contains a flex fence area 704 which indicates the flex fence values, in percentages and actual quantity, for the four periods. The first period 706 is the demand fence, and the range (percentage) for this period is zero, since the total demand cannot be changed within the demand fence.
For the next three periods, 710, 712, and 714, the range indicates the percentage of flex, and the range in units indicates the amount in units that the total demand for each day in the period can be increased or decreased.
Following is an example that shows how the smoothing method of the present invention adjusts total demand quantity to meet a requirement. For this example, the total demand for each day is 120 units, and the demand fence occurs at day 2. For the first flex period, the flex percentage is 10% and the number of days in the period is 4. For the second flex period, the flex percentage is 9% and the number of days in the period is 8. For the third period, the flex percentage is 8%, and the number of days in the period is 12. Table 1 shows the total demand and actual orders for the next 9 days.
              TABLE 1                                                     
______________________________________                                    
       1    2      3      4   5    6   7    8   9                         
______________________________________                                    
Orders   120    120    60   0   0    0   0    0   0                       
Total Demand                                                              
           120  120    60   0   0    0   0    0     0                     
______________________________________                                    
Table 2 shows the addition of a customer order for 325 units at day 5.
              TABLE 2                                                     
______________________________________                                    
       1    2      3      4   5    6    7   8    9                        
______________________________________                                    
Orders   120    120    60   0   325  0    0   0    0                      
Total Demand                                                              
            120  120   60   0    325  0   0    0    0                     
______________________________________                                    
The flex limit for days 1 and 2 cannot be changed, since they are within the demand fence of 2 days. The flex limit for days 3-5, however, is 132, that is 120, [1.1]1. This new customer order causes the total demand for day 5 to exceed the flex limit for day, therefore the system must smooth the additional amount over the previous two days, if possible. Table 3 shows the result of processing by the smoothing method of FIGS. 5 and 6, described above.
              TABLE 3                                                     
______________________________________                                    
1         2      3      4     5    6    7   8    9                        
______________________________________                                    
Orders                                                                    
      120     120    60   0     325  0    0   0    0                      
Smooth                                                                    
       0         0     +61                                                
                          +132  -193                                      
Total   120    120   121     132                                          
                                    132                                   
                                         0                                
                                          0    0   0                      
Demand                                                                    
______________________________________                                    
The system placed the largest changes into the last days, thus increased flexibility is achieved by delaying the increase as long as possible.
Having thus described a presently preferred embodiment of the present invention, it will now be appreciated that the aspects of the invention have been fully achieved, and it will be understood by those skilled in the art that many changes in construction and widely differing embodiments and applications of the invention will suggest themselves without departing from the spirit and scope of the present invention. The disclosures and the description herein are intended to be illustrative and are not in any sense limiting of the invention, more preferably defined in scope by the following claims.

Claims (5)

What is claimed is:
1. In a computerized manufacturing system, a computer implemented method for determining a production quantity for a plurality of flex periods, and ordering material for said production quantity during said plurality of flex periods, said method comprising:
(a) accepting a quantity of flex periods from a user of the system and assigning each flex period a sequential number, wherein said flex periods occur after a demand fence date;
(b) accepting a daily rate total demand from the user of the system, wherein said daily rate total demand equals said production quantity at said demand fence date;
(c) accepting a flex period percentage for each of said flex periods from the user;
(d) accepting a flex period number of days, one said flex period number of days for each of said flex periods;
(e) calculating a flex period total demand for each of said flex periods, comprising the steps of
(e1) calculating a first multiplier by dividing said flex period percentage for said flex period by one-hundred and adding one to a result of said dividing to produce said first multiplier;
(e2) calculating a second multiplier by raising said first multiplier to the power of said sequential number assigned to said flex period in step (a), and
(e3) calculating said flex period total demand for said flex period by multiplying said second multiplier by said daily rate total demand, and
(e4) assigning said flex period total demand to each day of said flex period;
(f) accepting at least one customer order from a user of said system;
(g) for each said customer order accepted, increasing said production quantity for .[.all days in each of said flex periods.]. .Iadd.at least one day .Iaddend.prior to a .[.day of said.]. customer order .Iadd.required date .Iaddend.and after said .[.flex.]. .Iadd.demand .Iaddend.fence date, wherein said production quantity for each .[.of said days.]. .Iadd.day in each flex period .Iaddend.does not exceed said flex period total demand set for said day; and
(h) placing an order for material for said production quantity for each of said flex .[.fence.]. periods .Iadd.according to the maximum daily total demand calculated for each of said flex periods.Iaddend..
2. The computer implemented method of claim 1 wherein step .[.(g2).]. (.Iadd.g) .Iaddend.further comprises the steps of:
.[.(g2a).]. (.Iadd.g2) .Iaddend.increasing said production quantity starting with said day of said customer order and increasing said production quantity for previous days until said customer order is satisfied.
3. The computer implemented method of claim 2 wherein step .[.(g2a).]. (.Iadd.g2) .Iaddend.further comprises the step of increasing said production quantity for each sequentially previous day, starting with said day of said customer order, to a maximum allowed amount within said flex period total demand for each sequentially previous day, until a total amount of increase in said production quantity equals an amount of said customer order. .Iadd.
4. In a computerized manufacturing system, a computer-implemented method for determining a production quantity for a plurality of flex periods and ordering material for said production quantity comprising the steps of:
(a) accepting a number of flex periods from a user of the system, wherein said flex periods occur after a demand fence date;
(b) accepting a daily rate total demand from the user of the system, wherein said daily rate total demand equals said production quantity at said demand fence date;
(c) accepting a flex period percentage for each said flex period wherein each successive flex period's percentage is increased by an incrementally smaller amount than the preceding flex period's percentage;
(d) accepting a flex period number of days, one said flex period number of days for each of said flex periods;
(e) calculating a total demand for each of said flex periods based upon that flex period's percentage;
(f) accepting at least one customer order from a user of said system;
(g) for each said customer order accepted, increasing said production quantity for at least one day in at least one said flex period, wherein said production quantity for each day in each flex period does not exceed said flex period total demand set for said day; and
(h) ordering material for said production quantity for each of said flex periods according to the maximum daily total demand calculated for each of said flex periods..Iaddend..Iadd.
5. A computer implemented method, as claimed in claim 4, wherein step (d) further comprises accepting a flex period number of days, wherein each successive flex period number of days is larger than each previous flex period number of days..Iaddend.
US08/907,848 1992-05-15 1997-08-08 Method for determining flexible demand in a manufacturing process Expired - Lifetime USRE36360E (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
US08/907,848 USRE36360E (en) 1992-05-15 1997-08-08 Method for determining flexible demand in a manufacturing process

Applications Claiming Priority (3)

Application Number Priority Date Filing Date Title
US88459992A 1992-05-15 1992-05-15
US08/264,171 US5440480A (en) 1992-05-15 1994-06-16 Method for determining flexible demand in a manufacturing process
US08/907,848 USRE36360E (en) 1992-05-15 1997-08-08 Method for determining flexible demand in a manufacturing process

Related Parent Applications (2)

Application Number Title Priority Date Filing Date
US88459992A Continuation 1992-05-15 1992-05-15
US08/264,171 Reissue US5440480A (en) 1992-05-15 1994-06-16 Method for determining flexible demand in a manufacturing process

Publications (1)

Publication Number Publication Date
USRE36360E true USRE36360E (en) 1999-10-26

Family

ID=25384974

Family Applications (2)

Application Number Title Priority Date Filing Date
US08/264,171 Ceased US5440480A (en) 1992-05-15 1994-06-16 Method for determining flexible demand in a manufacturing process
US08/907,848 Expired - Lifetime USRE36360E (en) 1992-05-15 1997-08-08 Method for determining flexible demand in a manufacturing process

Family Applications Before (1)

Application Number Title Priority Date Filing Date
US08/264,171 Ceased US5440480A (en) 1992-05-15 1994-06-16 Method for determining flexible demand in a manufacturing process

Country Status (1)

Country Link
US (2) US5440480A (en)

Cited By (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6188990B1 (en) * 1996-05-14 2001-02-13 Autosystems Limited Method and apparatus for monitoring the processing of articles
US6681141B2 (en) 2001-08-23 2004-01-20 International Business Machines Corporation Materials requirements planning simulation analysis
US6816751B1 (en) 2000-02-07 2004-11-09 Seagate Technology Llc Material inline quality management system
US6823228B2 (en) 2002-02-21 2004-11-23 International Business Machines Corporation Fabricator capacity analysis
US20060022454A1 (en) * 2004-07-29 2006-02-02 Comap Ring for visually determining the crimped status of a coupling for tubes
US7016865B1 (en) 2000-04-14 2006-03-21 Deluxe Corporation Personalization format converter system and method
US20070005167A1 (en) * 2005-06-30 2007-01-04 George Roumeliotis System and method for pro-active manufacturing performance management
US7216092B1 (en) 2000-04-14 2007-05-08 Deluxe Corporation Intelligent personalization system and method
US20100114401A1 (en) * 2008-11-06 2010-05-06 Industrial Technology Research Institute Method and Device of Predicting the Level of Customer Amount, and Method and System of Controlling Temperature of Aircondiction by Using the Same
US20100168929A1 (en) * 2008-12-26 2010-07-01 Industrial Technology Research Institute Method of determining demand threshold, and method and system of demand control
US20100312611A1 (en) * 2005-09-02 2010-12-09 Flow Vision LLC Inventory management system
US8209242B1 (en) 2005-09-02 2012-06-26 Flowvision, Llc Inventory management system
US8644974B2 (en) 2010-10-14 2014-02-04 Honda Motor Co., Ltd. Computerized system and method for managing supply chain orders
US8671031B2 (en) 2005-09-02 2014-03-11 Flowvision, Llc Inventory management system
US10417595B2 (en) 2017-05-05 2019-09-17 DeHart Consulting, LLC Time-based, demand-pull production

Families Citing this family (30)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5991732A (en) * 1989-02-15 1999-11-23 Moslares; Andres Monedero Strategical-tactical logistic system
US5712985A (en) * 1989-09-12 1998-01-27 Lee; Michael D. System and method for estimating business demand based on business influences
US6801820B1 (en) 1994-05-27 2004-10-05 Lilly Software Associates, Inc. Method and apparatus for scheduling work orders in a manufacturing process
US7647241B1 (en) 1994-05-27 2010-01-12 Infor Global Solutions (Veenendaal) B.V Computer program product for determining and reducing customer service impact
US7039595B1 (en) 1998-10-21 2006-05-02 Infor International Limited System and method for throughput measurement
US5787000A (en) * 1994-05-27 1998-07-28 Lilly Software Associates, Inc. Method and apparatus for scheduling work orders in a manufacturing process
US5699259A (en) * 1995-03-01 1997-12-16 Siemens Business Communication Systems, Inc. Inventory control procedure
SE9803586L (en) * 1998-10-21 2000-04-22 Ma System Ab Method and system for controlling a supply chain
US6463345B1 (en) * 1999-01-04 2002-10-08 International Business Machines Corporation Regenerative available to promise
US6415194B1 (en) 1999-04-02 2002-07-02 American Standard Inc. Method and system for providing sufficient availability of manufacturing resources to meet unanticipated demand
EP1192578A4 (en) * 1999-04-02 2005-08-17 American Standard Int Inc System and method of scheduling manufacturing resources
US6397118B1 (en) 1999-04-02 2002-05-28 American Standard Inc. Method and system for providing sufficient availability of manufacturing resources to meet unanticipated demand
US6393332B1 (en) 1999-04-02 2002-05-21 American Standard Inc. Method and system for providing sufficient availability of manufacturing resources to meet unanticipated demand
US6415195B1 (en) 1999-04-02 2002-07-02 American Standard Inc. Method and system for providing sufficient availability of manufacturing resources to meet unanticipated demand
US20030018550A1 (en) * 2000-02-22 2003-01-23 Rotman Frank Lewis Methods and systems for providing transaction data
US6711550B1 (en) * 2000-03-31 2004-03-23 Ford Motor Company Method and system for capacity planning
US20020049643A1 (en) * 2000-09-27 2002-04-25 Church Diana L. On-line ingredient exchange system and method
US20030014314A1 (en) * 2001-03-15 2003-01-16 Pelion Systems, Inc. Manufacturing flow control method and system
US20030139952A1 (en) * 2002-01-24 2003-07-24 Ford Global Technologies, Inc. Complexity management and production optimization system
US20030229550A1 (en) * 2002-06-07 2003-12-11 International Business Machines Corporation System and method for planning and ordering components for a configure-to-order manufacturing process
US8160914B1 (en) * 2003-10-31 2012-04-17 Versata Development Group, Inc. Identifying quality user sessions and determining product demand with high resolution capabilities
TW200411456A (en) * 2002-12-20 2004-07-01 Hon Hai Prec Ind Co Ltd System and method for processing lack of materials in a manufacturing order
DE10315897B4 (en) * 2003-04-08 2005-03-10 Karlsruhe Forschzent Method and use of a device for separating metallic and semiconductive carbon nanotubes
US8615416B2 (en) * 2006-02-27 2013-12-24 International Business Machines Corporation Method for avoiding or limiting early build due to yield decreases
US7694874B2 (en) 2006-03-29 2010-04-13 Amazon Technologies, Inc. Over-the-air device provisioning and activation
US10366426B2 (en) * 2007-03-09 2019-07-30 Amazon Technologies, Inc. Personalizing handheld electronic book readers
US8108989B2 (en) * 2007-06-28 2012-02-07 Crown Equipment Corporation Manufacturing cell and elements of the cell
US7810095B2 (en) * 2007-09-12 2010-10-05 Xerox Corporation Method and system for characterizing elements of a print production queuing model
EP2256679A1 (en) * 2009-05-29 2010-12-01 Siemens Aktiengesellschaft Customizable scheduling tool, manufacturing executing system comprising said tool and method of using said tool
US20140172490A1 (en) * 2012-12-17 2014-06-19 David M. Snyder System, method, and apparatus for managing and performing geographically distributed cell-based manufacturing and/or assembly

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4866628A (en) * 1987-12-18 1989-09-12 International Business Machines Corp. Automated production dispatch system with feedback control
US5099431A (en) * 1989-10-23 1992-03-24 International Business Machines Corporation Automated re-work shop order scheduling system
US5148370A (en) * 1987-06-17 1992-09-15 The Standard Oil Company Expert system and method for batch production scheduling and planning
US5193065A (en) * 1990-12-03 1993-03-09 Caterpillar Inc. System for requistioning and distributing material in a manufacturing environment

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5148370A (en) * 1987-06-17 1992-09-15 The Standard Oil Company Expert system and method for batch production scheduling and planning
US4866628A (en) * 1987-12-18 1989-09-12 International Business Machines Corp. Automated production dispatch system with feedback control
US5099431A (en) * 1989-10-23 1992-03-24 International Business Machines Corporation Automated re-work shop order scheduling system
US5193065A (en) * 1990-12-03 1993-03-09 Caterpillar Inc. System for requistioning and distributing material in a manufacturing environment

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
Costanza, John R., The Quantum Leap in Speed to Market; J I T Institute of Technology, 1990, pp. 89 94. *
Costanza, John R., The Quantum Leap in Speed to Market; J-I-T Institute of Technology, 1990, pp. 89-94.

Cited By (18)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6188990B1 (en) * 1996-05-14 2001-02-13 Autosystems Limited Method and apparatus for monitoring the processing of articles
US6816751B1 (en) 2000-02-07 2004-11-09 Seagate Technology Llc Material inline quality management system
US7216092B1 (en) 2000-04-14 2007-05-08 Deluxe Corporation Intelligent personalization system and method
US7016865B1 (en) 2000-04-14 2006-03-21 Deluxe Corporation Personalization format converter system and method
US6681141B2 (en) 2001-08-23 2004-01-20 International Business Machines Corporation Materials requirements planning simulation analysis
US6823228B2 (en) 2002-02-21 2004-11-23 International Business Machines Corporation Fabricator capacity analysis
US20060022454A1 (en) * 2004-07-29 2006-02-02 Comap Ring for visually determining the crimped status of a coupling for tubes
US20070005167A1 (en) * 2005-06-30 2007-01-04 George Roumeliotis System and method for pro-active manufacturing performance management
US8515834B2 (en) 2005-09-02 2013-08-20 Flowvision, Llc Inventory management system
US9183521B2 (en) 2005-09-02 2015-11-10 Flowvision, Llc Inventory management system
US20100312611A1 (en) * 2005-09-02 2010-12-09 Flow Vision LLC Inventory management system
US8209242B1 (en) 2005-09-02 2012-06-26 Flowvision, Llc Inventory management system
US8671031B2 (en) 2005-09-02 2014-03-11 Flowvision, Llc Inventory management system
US20100114401A1 (en) * 2008-11-06 2010-05-06 Industrial Technology Research Institute Method and Device of Predicting the Level of Customer Amount, and Method and System of Controlling Temperature of Aircondiction by Using the Same
US8311680B2 (en) * 2008-12-26 2012-11-13 Industrial Technology Research Institute Method of determining demand threshold, and method and system of demand control
US20100168929A1 (en) * 2008-12-26 2010-07-01 Industrial Technology Research Institute Method of determining demand threshold, and method and system of demand control
US8644974B2 (en) 2010-10-14 2014-02-04 Honda Motor Co., Ltd. Computerized system and method for managing supply chain orders
US10417595B2 (en) 2017-05-05 2019-09-17 DeHart Consulting, LLC Time-based, demand-pull production

Also Published As

Publication number Publication date
US5440480A (en) 1995-08-08

Similar Documents

Publication Publication Date Title
USRE36360E (en) Method for determining flexible demand in a manufacturing process
CA2455639C (en) Automated listing management
US5971585A (en) Best can do matching of assets with demand in microelectronics manufacturing
US6393332B1 (en) Method and system for providing sufficient availability of manufacturing resources to meet unanticipated demand
US6415195B1 (en) Method and system for providing sufficient availability of manufacturing resources to meet unanticipated demand
JP3698433B2 (en) Safety stock quantity calculation device, safety stock quantity calculation program and order point calculation device
US11915175B2 (en) System and method for allocating manufactured products to sellers using profitable order promising
AU2002355130A1 (en) Automated listing management
JPH096862A (en) Promise management system
AU769097B2 (en) System and method of scheduling manufacturing resources
EP1701302A1 (en) Ordering/order receiving system
US7974720B2 (en) Dynamic fulfillment planning method and apparatus
US6415194B1 (en) Method and system for providing sufficient availability of manufacturing resources to meet unanticipated demand
JP3119195B2 (en) Production planning device, method, and recording medium recording program for executing the same
US6397118B1 (en) Method and system for providing sufficient availability of manufacturing resources to meet unanticipated demand
JP2020119029A (en) Order information calculation program, device, and method
EP1843232B1 (en) Production scheduling system
JP2002012308A (en) Inventory management method
JPH0877278A (en) Method for stabilizing various activities accompanying production of material preparation schedule, process schedule, or the like against variation of production schedule
JPH0756987A (en) Commodity ordering system
Denkena et al. Optimization of delivery adherence based on capacity planning and bid pricing
JPH08215996A (en) Device for stock addition corresponding to variation of production plan and method corresponding to variation of production plan
JP2002132329A (en) Method and system for demand and supply plan
JP3109610B2 (en) How to manage order instruction cards
JP2004227442A (en) Scheduling system

Legal Events

Date Code Title Description
AS Assignment

Owner name: SILICON VALLEY BANK, CALIFORNIA

Free format text: SECURITY AGREEMENT;ASSIGNOR:DEMAND FLOW INSTITUTE, LLC;REEL/FRAME:011846/0616

Effective date: 20001227

FPAY Fee payment

Year of fee payment: 8

AS Assignment

Owner name: JCIT INTERNATIONAL, INC., COLORADO

Free format text: ASSIGNMENT OF ASSIGNORS INTEREST;ASSIGNOR:DEMAND FLOW INSTITUTE, LLC, A COLORADO CORPORATION;REEL/FRAME:015962/0799

Effective date: 20050316

FPAY Fee payment

Year of fee payment: 12