USRE43293E1 - Inter-rat handover to UTRAN with simultaneous PS and CS domain services - Google Patents

Inter-rat handover to UTRAN with simultaneous PS and CS domain services Download PDF

Info

Publication number
USRE43293E1
USRE43293E1 US12/542,722 US54272209A USRE43293E US RE43293 E1 USRE43293 E1 US RE43293E1 US 54272209 A US54272209 A US 54272209A US RE43293 E USRE43293 E US RE43293E
Authority
US
United States
Prior art keywords
handover
utran
handed over
domain
command message
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active, expires
Application number
US12/542,722
Inventor
Chih-Hsiang Wu
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
HTC Corp
Original Assignee
HTC Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by HTC Corp filed Critical HTC Corp
Priority to US12/542,722 priority Critical patent/USRE43293E1/en
Assigned to HTC CORPORATION reassignment HTC CORPORATION ASSIGNMENT OF ASSIGNORS INTEREST (SEE DOCUMENT FOR DETAILS). Assignors: WU, CHIH-HSIANG
Application granted granted Critical
Publication of USRE43293E1 publication Critical patent/USRE43293E1/en
Active legal-status Critical Current
Adjusted expiration legal-status Critical

Links

Images

Classifications

    • HELECTRICITY
    • H04ELECTRIC COMMUNICATION TECHNIQUE
    • H04WWIRELESS COMMUNICATION NETWORKS
    • H04W36/00Hand-off or reselection arrangements
    • H04W36/0005Control or signalling for completing the hand-off
    • H04W36/0055Transmission or use of information for re-establishing the radio link
    • H04W36/0066Transmission or use of information for re-establishing the radio link of control information between different types of networks in order to establish a new radio link in the target network
    • HELECTRICITY
    • H04ELECTRIC COMMUNICATION TECHNIQUE
    • H04WWIRELESS COMMUNICATION NETWORKS
    • H04W88/00Devices specially adapted for wireless communication networks, e.g. terminals, base stations or access point devices
    • H04W88/02Terminal devices
    • H04W88/06Terminal devices adapted for operation in multiple networks or having at least two operational modes, e.g. multi-mode terminals
    • HELECTRICITY
    • H04ELECTRIC COMMUNICATION TECHNIQUE
    • H04WWIRELESS COMMUNICATION NETWORKS
    • H04W92/00Interfaces specially adapted for wireless communication networks
    • H04W92/04Interfaces between hierarchically different network devices
    • H04W92/10Interfaces between hierarchically different network devices between terminal device and access point, i.e. wireless air interface

Definitions

  • the present invention relates to cellular networks. More specifically, a method for performing an Inter-RAT handover is disclosed.
  • Inter system handovers between Global System for Mobile Communications (GSM) and Universal Terrestrial Radio Access Network (UTRAN) are expected to play an increasingly important role, as many 3 rd Generation (3G) operators will provide wide-area coverage with the GSM Base Station System (BSS) and use the 3G UTRAN in relatively small traffic hotspots.
  • a dual-system user equipment (UE) is capable of supporting both GSM and UTRAN systems. Each time such a UE moves between the two types of coverage areas, an inter system handover must be performed.
  • RAT radio access technology
  • the inter system handover is often called an inter-RAT handover.
  • An inter-RAT handover to UTRAN procedure hands the UE over from a GSM system to a UTRAN system.
  • an inter-RAT handover from UTAN procedure hands the UE over from the UTRAN system to a GSM system.
  • UMTS Universal Mobile Telecommunications System
  • the UE can support both circuit switched (CS) and packet switched (PS) connections, and both types of connections must be handed over.
  • CS circuit switched
  • PS packet switched
  • the handover to UTRAN procedure is quite complex, and a complete description of every aspect of the procedure is quite beyond this background description.
  • 3GPP TS 23.060 General Packet Radio Service (GPRS); Service description; Stage 2”, and 3GPP TS 24.008 “Mobile radio interface layer 3 specification; Core Network Protocols; Stage 3”, both of which are included herein by reference.
  • the above specifications indicate that both PS and CS services are to be handed over concurrently.
  • the handover to UTRAN procedure can only utilize the default/predefined UMTS radio configurations for the CS connection, and consequently a great deal of information must be explicitly provided for the PS connection. As indicated above, this can lead to segmentation over more than two GSM air interface messages, which will adversely impact the handover performance.
  • the above references do not provide a clear method for enabling the UE to determine whether or not a signaling connection exists after the handover to UTRAN procedure. This may cause the UE to subsequently use an incorrect procedure (initial direct transfer or uplink direct transfer) to transfer a message to the UTRAN.
  • UTRAN Universal Terrestrial Radio Access Network
  • UE user equipment
  • the preferred embodiment of the present invention discloses a wireless device initially having simultaneous circuit switched (CS) and packet switched (PS) services with a first radio access technology (RAT) system that is not a UMTS (for example, a GSM system).
  • a radio access technology (RAT) system that is not a UMTS (for example, a GSM system).
  • the first RAT system transmits a HANDOVER TO UTRAN COMMAND message to the wireless device to perform a handover to UTRAN procedure.
  • the HANDOVER TO UTRAN COMMAND message excludes information used for handing over the PS signaling connections to the UTRAN so that only CS signaling connections are handed over.
  • the wireless device receives and parses the HANDOVER TO UTRAN COMMAND message to determine what signaling connections are being handed over.
  • a radio resource control (RRC) layer within the wireless device informs an upper layer within the wireless device that no PS radio access bearers or no PS signaling connections are present.
  • RRC radio resource control
  • FIG. 1 is a simple block diagram of a wireless device according to a preferred embodiment of the present invention.
  • FIG. 2 is a message sequence chart for performing the present invention handover to UTRAN procedure.
  • FIG. 3 is a message sequence chart for performing a first embodiment packet switched (PS) radio access bearer (RAB) re-establishment procedure to re-establish PS services.
  • PS packet switched
  • RAB radio access bearer
  • FIG. 4 is a message sequence chart for performing a second embodiment PS RAB re-establishment procedure to re-establish PS services.
  • FIG. 5 is a simplified block diagram of a Handover to UTRAN command that holds a complete specification of RABs that are being handed over.
  • FIG. 6 is a simplified block diagram of a Handover to UTRAN command that utilizes predefined configurations to indicate which RABs are being handed over.
  • FIG. 7 is a simplified block diagram of a Handover to UTRAN command that utilizes the default configurations to indicate which RABs are being handed over.
  • FIG. 8 is a flow chart of the present invention method for parsing a Handover to UTRAN command to determine what signaling connections are handed over during a Handover to UTRAN procedure.
  • a GSM system serves as an example of a non-UMTS system with which a handover to UTRAN procedure is performed.
  • the method of the present invention is suitable for other types of non-UMTS systems that support the handover to UTRAN procedure. Adapting the present invention method to such other systems should be clear after reading the following detailed description that is made with specific reference to a GSM system.
  • FIG. 1 is a simple block diagram of a wireless system 1 capable of performing the present invention method, and includes a wireless device 100 in communications with a UMTS target radio network controller (t-RNC) 10 and a GSM base station system (BSS) 20 .
  • the t-RNC 10 communicates with a core network (CN) 11 , and the CN 11 is capable of communicating with the BSS 20 .
  • the t-RNC 10 and the BSS 20 together provide a base station network (communicating via the CN 11 ) that provides radio access support for the wireless device 100 .
  • the wireless device 100 may be any sort of equipment, typically mobile but not necessarily so, that provides both UMTS and non-UMTS support.
  • the wireless device 100 may include input/output (I/O) hardware 110 , a wireless transceiver 120 and memory 140 that are all connected to and under the control of a central processing unit (CPU) 130 in a manner familiar to those of regular skill in the art.
  • the I/O hardware 110 may include, for example, both a display and speaker for output, and a keypad and microphone for input.
  • the wireless transceiver 120 enables the UE 100 to send and receive wireless signals.
  • the CPU 130 controls the functionality of the UE 100 according to program code 149 contained within the memory 140 and executable by the CPU 130 . In most aspects the UE 100 is identical to that of the prior art, but for modifications made to the program code 149 to implement the present invention method.
  • the program code 149 will support both a GSM stack (for communications with the non-UMTS GSM system, as indicated by BSS 20 ) and a UMTS stack (for communications with the UTRAN, as indicated by the t-RNC 10 ).
  • the RRC layer 142 there is an upper layer 143 and a lower layer 141 .
  • the lower layer 141 may include, for example, a radio link control (RLC) layer.
  • the upper layer 143 may include a mobility management/GPRS mobility management (MM/GMM) layer 143 m.
  • FIG. 2 is a message sequence chart for performing the present invention method.
  • the UE 100 has established both PS and CS connections with the GSM system via the BSS 20 .
  • the RRC layer 142 sends signal measurement information to the BSS 20 by way of an “Enhanced measurement report” 201 .
  • This measurement information includes measurement data for the t-RNC 10 , and results in the BSS 20 determining that the UE 100 should be handed over to the t-RNC 10 .
  • the BSS 20 consequently informs the CN 11 of this fact by way of a Handover Required message 202 .
  • the CN 11 correspondingly notifies the t-RNC 10 by way of a relocation request message 203 .
  • the t-RNC 10 responds to the CN 11 with a Relocation request ack 204 , which contains a Handover to UTRAN command for the UE 100 .
  • the CN 11 issues a Handover Command 205 to the BSS 20 , which contains the Handover to UTRAN command for the UE 100 .
  • the BSS 20 then sends a Handover command 206 to the UE 100 , which contains the Handover to UTRAN command, and which is forwarded to the RRC 142 .
  • the handover procedure is nearly identical to that of the prior art, but for one important difference: the Handover to UTRAN command that is provided to the UE RRC layer 142 by way of the BSS 20 contains only the information needed to handover the CS connection or connections.
  • the Handover to UTRAN command embedded within the Handover command 206 does not contain information needed to handover the PS connection or connections. Consequently, despite the fact that at the time the Handover command 206 is issued to the UE 100 the UE 100 has both CS and PS connections established with the BSS 20 , only the CS connections are handed over to the t-RNC 10 .
  • the purpose of this is to keep the Handover command 206 as small as possible so as to avoid excessive segmentation of the Handover command 206 that may result in degradation of the handover procedure. It is preferable to handover CS connections over PS connections as PS connections can generally tolerate brief interruptions of service, whereas this is typically not the case for CS connections.
  • the t-RNC 10 may build the embedded Handover to UTRAN command so that only CS connection information is provided, deliberately leaving out information needed to handover any PS connections. This deliberately incomplete Handover to UTRAN command is then sent to the BSS 20 via the CN 11 , and thence on to the UE RRC 142 via the Handover command 206 .
  • the t-RNC 10 may include a complete Handover to UTRAN command in the Relocation request ack 204 , including information for both PS and CS connections.
  • the CN 11 may then strip the Handover to UTRAN command of the PS information, and in the Handover Command 205 include only the information needed for handing over CS connections in the Handover to UTRAN command. This stripped Handover to UTRAN command would then be forwarded to the UE RRC 142 via the BSS 20 . Finally, it may be the BSS 20 itself that generates an incomplete Handover to UTRAN command in the Handover command 206 , insuring that the Handover command 206 contains only enough information to enable the UE 100 to handover the CS connections to the t-RNC 10 .
  • the RRC layer 142 Upon receiving the Handover to UTRAN command, the RRC layer 142 must parse the Handover to UTRAN command to determine what connections are being handed over. This parsing is described later. However, as the Handover to UTRAN command contains only information need to hand over the CS connections, the RRC layer 142 determines that only CS connections are being handed over, and behaves accordingly. The UE 100 thus succeeds in establishing a CS connection (or connections) with the t-RNC 10 to re-establish CS services. This is detected by the t-RNC 10 , which notifies the CN 11 with a Relocation detect message 207 .
  • the RRC layer 142 informs the upper layer 143 (i.e., the MM/GMM layer 143 m) that there are no PS signaling connections and no PS radio access bearers (RABs) Not only does this enable the upper layer 143 to know that the PS services have not been handed over, but it also enables the upper layer 143 to know that the UE 100 is now camped on a UMTS system rather than the non-UMTS system. This is useful information, as the behavior of the MM/GMM layer 143 m may change depending upon the type of network upon which the UE 100 is camped.
  • RRC layer 142 informs the upper layer 143 (i.e., the MM/GMM layer 143 m) that there are no PS signaling connections and no PS radio access bearers (RABs)
  • RRBs PS radio access bearers
  • the RRC 142 sends a Handover to UTRAN complete message 208 to the t-RNC 10 (which establishes the RRC signaling connection), completing the Handover to UTRAN procedure between the UE 100 and the t-RNC 10 .
  • the t-RNC 10 correspondingly informs the CN 11 with a Relocation complete message 209 , and the CN 11 responds by sending a Clear Command 210 to the BSS 20 .
  • the Clear Command 210 is responded to with a Clear Complete message 211 .
  • the MM/GMM layer 143 m initiates a routing area update procedure by sending a Routing Area Update Request 212 to the CN 11 .
  • the purpose of the routing area update procedure is to change from the old 2G-SGSN to the new 3G-SGSN.
  • the CN 11 performs various procedures, which culminate in the sending of a Routing Area Update Accept message 213 to the MM/GMM 143 , and whichresponds with a Routing Area Update Complete message 214 . Thereafter, the UE 100 can work with the UTRAN to re-establish the PS services.
  • the sequencing of events in the above is preferred, but may be changed.
  • the routing area update procedure may be performed before, or concurrently with, the sending of the Handover to UTRAN complete message 208 . Other sequences may also possibly be changed.
  • re-establishment of PS services is preferably done after the routing area update procedure.
  • FIG. 3 is a message sequence chart for performing a first embodiment PS RAB re-establishment procedure to re-establish PS services.
  • the UE 100 that initiates the PS RAB re-establishment procedure.
  • the MM/GMM 143 m of the UE 100 sends a Service Request message to the SGSN.
  • the SGSN responds with a Service Accept message to the UE 100 , and so informs the t-RNC 10 with a Radio Access Bearer Assignment Request. If the PS signaling connection established during the routing area update procedure is released, then the SGSN performs various security functions to authenticate the UE 100 . After the above, the t-RNC 10 sends a Radio Bearer Setup message to the UE 100 , which indicates to the UE 100 the new Radio Bearer Identity established and the corresponding RAB ID.
  • the UE 100 responds with a Radio Bearer Setup Complete message, and at this point, as far as the UE 100 is concerned, the PS RAB re-establishment procedure is complete and PS services are restored to the user of the UE 100 .
  • the t-RNC 10 responds by sending a Radio Access Bearer Assignment Response message to the SGSN.
  • the SGSN may optionally initiate a PDP Context Modification procedure to inform the UE 100 and the GGSN of the new negotiated QoS profile for the corresponding PDP context.
  • the UE 100 can then send or receive an uplink protocol data unit (PDU).
  • PDU uplink protocol data unit
  • FIG. 4 is a message sequence chart for performing a second embodiment PS RAB re-establishment procedure to re-establish PS services.
  • this second embodiment it is the UTRAN that initiates the PS RAB re-establishment procedure.
  • the PS signaling connection established during the routing area update procedure is not released.
  • the SGSN sends a Radio Access Bearer Assignment Request to the t-RNC 10 to re-establish RABs for every appropriately activated PDP context.
  • the t-RNC 10 sends a Radio Bearer Setup message to the UE 100 , which indicates to the UE 100 the new radio bearer identity established, and the corresponding RAB ID.
  • the UE 100 responds with a Radio Bearer Setup Complete message, and at this point, as far as the UE 100 is concerned, the PS RAB re-establishment procedure is complete and PS services are restored to the user of the UE 100 .
  • the t-RNC 10 responds by sending a Radio Access Bearer Assignment Response message to the SGSN.
  • the SGSN may optionally initiate a PDP Context Modification procedure to inform the UE 100 and the GGSN of the new negotiated QoS profile for the corresponding PDP context.
  • the UE 100 can then send an uplink protocol data unit (PDU).
  • PDU uplink protocol data unit
  • FIG. 5 is a simplified block diagram of a Handover to UTRAN command that holds a complete specification of the RABs that are being handed over.
  • FIG. 6 is a simplified block diagram of a Handover to UTRAN command that utilizes the predefined configurations to indicate which RABs are being handed over.
  • FIG. 7 is a simplified block diagram of a Handover to UTRAN command that utilizes the default configurations to indicate which RABs are being handed over.
  • FIG. 8 is a flow chart of the present invention method for parsing the Handover to UTRAN command to determine what signaling connections are handed over during the Handover to UTRAN procedure. It should be noted that FIGS. 5 to 7 show only those portions of the Handover to UTRAN command that are relevant to the present invention method. A complete description of the Handover to UTRAN command data structure can be found in 3GPP TS 25.331 clause 10.2.16a.
  • the format of the Handover to UTRAN command changes depending upon whether the complete specification, predefined configuration or default configuration is used. If, as shown in FIG. 5 , a complete specification is used, then an information element (IE) Specification mode 301 will be set to a value “Complete specification”. In this case, then, an IE RAB information to setup list 302 will exist, containing one or more IEs RAB information for setup 303 . Each IE RAB information for setup 303 contains an IE CN domain identity 304 . The IE CN domain identity 304 can have a value of either “CS domain” or “PS domain”.
  • IE information element
  • each IE RAB information for setup 303 is individually extracted and the corresponding IE CN domain identity 304 is checked. If the IE CN domain identity 304 is “PS domain”, then it is determined that a PS signaling connection exists. If the IE CN domain identity 304 is “CS domain”, then it is determined that a CS signaling connection exists. Note, then, that it is possible to have both CS and PS signaling connections with a complete specification type Handover to UTRAN command.
  • predefined configurations 147 are downloaded from the UTRAN and stored within the UE 100 .
  • an IE Preconfiguration mode 312 will exist.
  • the IE Preconfiguration mode 312 is set to “Predefined configuration”
  • the IE Preconfiguration mode 312 will hold an integer valued IE Predefined configuration identity 313 .
  • This IE Predefined configuration identity 313 indicates which of the predefined configurations 147 should be used, and is used as an index to extract an IE RAB information for setup 148 .
  • the extracted IE 148 holds an IE CN domain identity 148 c that can be either “CS domain” or “PS domain”. If the IE CN domain identity 148 c is “PS domain”, then it is determined that a PS signaling connection exists. If the IE CN domain identity 148 c is “CS domain”, then it is determined that a CS signaling connection exists.
  • the IE Preconfiguration mode 322 will exist. If the IE Preconfiguration mode 322 is set to “Default configuration”, then an IE RAB info 323 will be present in the Handover to UTRAN command.
  • the IE RAB info 323 has an IE CN domain identity that can be either “CS domain” or “PS domain”. If the IE CN domain identity 324 is “PS domain”, then it is determined that a PS signaling connection exists. If the IE CN domain identity 324 is “CS domain”, then it is determined that a CS signaling connection exists.
  • the present invention does not include PS information in a Handover to UTRAN command when both PS and CS RABs are established with the non-UMTS network at the time of the handover procedure. This helps to ensure that CS services are handed over smoothly and in an uninterrupted manner. PS services are then restored after the CS services are handed over, and ideally after performing a routing area update procedure, as this ensures that packets are properly routed. Additionally, the present invention provides an explicit method that enables a wireless device to determine which services (CS, PS or both) are being handed over during a Handover to UTRAN procedure.

Abstract

A wireless device initially has simultaneous circuit switched (CS) and packet switched (PS) services with a non-UMTS network. With the CS and PS services ongoing, the non-UMTS network transmits a HANDOVER TO UTRAN COMMAND message to the wireless device to perform a handover to UTRAN procedure. The HANDOVER TO UTRAN COMMAND message excludes information used for handing over the PS signaling connections to the UTRAN so that only CS signaling connections are handed over. The wireless device receives and parses the HANDOVER TO UTRAN COMMAND message to determine what signaling connections are being handed over. Upon determining that only CS signaling connections are being handed over, a radio resource control (RRC) layer within the wireless device informs an upper layer within the wireless device that no PS radio access bearers or no PS signaling connections are present.

Description

BACKGROUND OF INVENTION
1. Field of the Invention
The present invention relates to cellular networks. More specifically, a method for performing an Inter-RAT handover is disclosed.
2. Description of the Prior Art
Inter system handovers between Global System for Mobile Communications (GSM) and Universal Terrestrial Radio Access Network (UTRAN) are expected to play an increasingly important role, as many 3rd Generation (3G) operators will provide wide-area coverage with the GSM Base Station System (BSS) and use the 3G UTRAN in relatively small traffic hotspots. A dual-system user equipment (UE) is capable of supporting both GSM and UTRAN systems. Each time such a UE moves between the two types of coverage areas, an inter system handover must be performed. Because the 3GPP specifications make wide use of the term “radio access technology (RAT)” when referring to application network technologies, the inter system handover is often called an inter-RAT handover. An inter-RAT handover to UTRAN procedure hands the UE over from a GSM system to a UTRAN system. Similarly, an inter-RAT handover from UTAN procedure hands the UE over from the UTRAN system to a GSM system.
To perform an inter-RAT handover to UTRAN, a large amount of information, such as spreading, channelization codes and frequency information, must be provided to the UE. Relaying so much information to the UE using an extended (and possibly segmented) GSM handover command would be impractical. In particular, segmentation over more than two GSM air interface messages would have an unacceptable impact on handover performance. Consequently, the use of predefined and default Universal Mobile Telecommunications System (UMTS) radio configurations was proposed. This is discussed in detail in the specifications 3GPP 25.331 “Radio Resource Control (RRC) Protocol Specification”, and 3GPP TS 25.922 “Radio Resource Management Strategies”, both of which are included herein by reference. Attention is drawn in particular to clause 5.1.5.2 of 3GPP TS 25.922, which deals with the use of predefined radio configuration during handover from 2G (i.e., GSM) to 3G (i.e., UTRAN). In short, by utilizing default configurations stored in every UE, and up to sixteen predefined configurations that are downloadable from the UTRAN, it is possible to greatly reduce the total amount of information that needs to be sent to the UE to perform the inter-RAT handover to UTRAN procedure, and thus ensure that the handover performance is acceptable.
The UE can support both circuit switched (CS) and packet switched (PS) connections, and both types of connections must be handed over. The handover to UTRAN procedure is quite complex, and a complete description of every aspect of the procedure is quite beyond this background description. However, for more details, in addition to the above-noted specifications, attention is also drawn to 3GPP TS 23.060 “General Packet Radio Service (GPRS); Service description; Stage 2”, and 3GPP TS 24.008 “Mobile radio interface layer 3 specification; Core Network Protocols; Stage 3”, both of which are included herein by reference. Of particular note is clause 6.13.2.2 of 3GPP TS 23.060, which details aspects of the handover to UTRAN procedure for PS services; clause 4.7.1.7 of 3GPP TS 24.008, and, within 3GPP TS 25.331, clauses B.6.2, 8.3.6 and 10.2.16a.
Briefly, though, the above specifications indicate that both PS and CS services are to be handed over concurrently. As it turns out, though, the handover to UTRAN procedure can only utilize the default/predefined UMTS radio configurations for the CS connection, and consequently a great deal of information must be explicitly provided for the PS connection. As indicated above, this can lead to segmentation over more than two GSM air interface messages, which will adversely impact the handover performance. In addition, the above references do not provide a clear method for enabling the UE to determine whether or not a signaling connection exists after the handover to UTRAN procedure. This may cause the UE to subsequently use an incorrect procedure (initial direct transfer or uplink direct transfer) to transfer a message to the UTRAN.
SUMMARY OF INVENTION
It is therefore a primary objective of this invention to provide an inter system handover to Universal Terrestrial Radio Access Network (UTRAN) procedure that provides for the handing over of both circuit switched (CS) and packet switch (PS) services while keeping the information needed to perform the handover down to a minimum.
It is a further objective of this invention to provide the user equipment (UE) with the ability to determine what signaling connections are handed over during the handover to UTRAN procedure.
Briefly summarized, the preferred embodiment of the present invention discloses a wireless device initially having simultaneous circuit switched (CS) and packet switched (PS) services with a first radio access technology (RAT) system that is not a UMTS (for example, a GSM system). With the CS and PS services ongoing, the first RAT system transmits a HANDOVER TO UTRAN COMMAND message to the wireless device to perform a handover to UTRAN procedure. The HANDOVER TO UTRAN COMMAND message excludes information used for handing over the PS signaling connections to the UTRAN so that only CS signaling connections are handed over. The wireless device receives and parses the HANDOVER TO UTRAN COMMAND message to determine what signaling connections are being handed over. Upon determining that only CS signaling connections are being handed over, a radio resource control (RRC) layer within the wireless device informs an upper layer within the wireless device that no PS radio access bearers or no PS signaling connections are present.
It is an advantage of the present invention that by providing for the handing over of only the CS services, the amount of information needed to perform the handover procedure is reduced, and thus the handover procedure is more likely to be performed successfully. That is, excessive segmentation of the handover information is avoided. Consequently, CS services proceed smoothly around the handover procedure. PS services, which are better able to handle brief suspensions of service without inconvenience to the user, can be re-established later.
These and other objectives of the present invention will no doubt become obvious to those of ordinary skill in the art after reading the following detailed description of the preferred embodiment, which is illustrated in the various figures and drawings.
BRIEF DESCRIPTION OF DRAWINGS
FIG. 1 is a simple block diagram of a wireless device according to a preferred embodiment of the present invention.
FIG. 2 is a message sequence chart for performing the present invention handover to UTRAN procedure.
FIG. 3 is a message sequence chart for performing a first embodiment packet switched (PS) radio access bearer (RAB) re-establishment procedure to re-establish PS services.
FIG. 4 is a message sequence chart for performing a second embodiment PS RAB re-establishment procedure to re-establish PS services.
FIG. 5 is a simplified block diagram of a Handover to UTRAN command that holds a complete specification of RABs that are being handed over.
FIG. 6 is a simplified block diagram of a Handover to UTRAN command that utilizes predefined configurations to indicate which RABs are being handed over.
FIG. 7 is a simplified block diagram of a Handover to UTRAN command that utilizes the default configurations to indicate which RABs are being handed over.
FIG. 8 is a flow chart of the present invention method for parsing a Handover to UTRAN command to determine what signaling connections are handed over during a Handover to UTRAN procedure.
DETAILED DESCRIPTION
In the following, a GSM system serves as an example of a non-UMTS system with which a handover to UTRAN procedure is performed. The method of the present invention, however, is suitable for other types of non-UMTS systems that support the handover to UTRAN procedure. Adapting the present invention method to such other systems should be clear after reading the following detailed description that is made with specific reference to a GSM system.
Please refer to FIG. 1. FIG. 1 is a simple block diagram of a wireless system 1 capable of performing the present invention method, and includes a wireless device 100 in communications with a UMTS target radio network controller (t-RNC) 10 and a GSM base station system (BSS) 20. The t-RNC 10 communicates with a core network (CN) 11, and the CN11 is capable of communicating with the BSS 20. The t-RNC 10 and the BSS 20 together provide a base station network (communicating via the CN 11) that provides radio access support for the wireless device 100. The wireless device 100 may be any sort of equipment, typically mobile but not necessarily so, that provides both UMTS and non-UMTS support. The wireless device 100 (hereinafter termed the UE 100) may include input/output (I/O) hardware 110, a wireless transceiver 120 and memory 140 that are all connected to and under the control of a central processing unit (CPU) 130 in a manner familiar to those of regular skill in the art. The I/O hardware 110 may include, for example, both a display and speaker for output, and a keypad and microphone for input. The wireless transceiver 120 enables the UE 100 to send and receive wireless signals. The CPU 130 controls the functionality of the UE 100 according to program code 149 contained within the memory 140 and executable by the CPU 130. In most aspects the UE 100 is identical to that of the prior art, but for modifications made to the program code 149 to implement the present invention method. How to effect such changes to the program code 149 should be clear to one of ordinary skill in the art after reading the following detailed description of the present invention method. Similarly, within the base station network, the t-RNC 10, the CN 11 and the BSS 20 are nearly identical to their prior art counterparts, but for modifications to implement the present invention method. As with the UE 100, respective program code is used to implement the functionality of the t-RNC 20, CN 11 and BSS 20. Hence, modifications to such program code can be made to provide the present invention method, and should be straightforward to one of reasonable skill in the art.
Because the UE 100 is a dual-system device, the program code 149 will support both a GSM stack (for communications with the non-UMTS GSM system, as indicated by BSS 20) and a UMTS stack (for communications with the UTRAN, as indicated by the t-RNC 10). It is the RRC layer 142 that is responsible for radio resource management by communicating with the UTRAN and GSM BSS. Relative to the RRC layer 142, there is an upper layer 143 and a lower layer 141. The lower layer 141 may include, for example, a radio link control (RLC) layer. The upper layer 143 may include a mobility management/GPRS mobility management (MM/GMM) layer 143m.
Please refer to FIG. 2 with reference to FIG. 1. FIG. 2 is a message sequence chart for performing the present invention method. Initially, the UE 100 has established both PS and CS connections with the GSM system via the BSS 20. While connected to the BSS 20, the RRC layer 142 sends signal measurement information to the BSS 20 by way of an “Enhanced measurement report” 201. This measurement information includes measurement data for the t-RNC 10, and results in the BSS 20 determining that the UE 100 should be handed over to the t-RNC 10. The BSS 20 consequently informs the CN 11 of this fact by way of a Handover Required message 202. The CN 11, in turn, correspondingly notifies the t-RNC 10 by way of a relocation request message 203. The t-RNC 10 responds to the CN 11 with a Relocation request ack 204, which contains a Handover to UTRAN command for the UE 100. The CN 11 issues a Handover Command 205 to the BSS 20, which contains the Handover to UTRAN command for the UE 100. The BSS 20 then sends a Handover command 206 to the UE 100, which contains the Handover to UTRAN command, and which is forwarded to the RRC 142. Up to this point, the handover procedure is nearly identical to that of the prior art, but for one important difference: the Handover to UTRAN command that is provided to the UE RRC layer 142 by way of the BSS 20 contains only the information needed to handover the CS connection or connections. The Handover to UTRAN command embedded within the Handover command 206 does not contain information needed to handover the PS connection or connections. Consequently, despite the fact that at the time the Handover command 206 is issued to the UE 100 the UE 100 has both CS and PS connections established with the BSS 20, only the CS connections are handed over to the t-RNC 10. The purpose of this is to keep the Handover command 206 as small as possible so as to avoid excessive segmentation of the Handover command 206 that may result in degradation of the handover procedure. It is preferable to handover CS connections over PS connections as PS connections can generally tolerate brief interruptions of service, whereas this is typically not the case for CS connections.
When generating the Relocation request ack 204, the t-RNC 10 may build the embedded Handover to UTRAN command so that only CS connection information is provided, deliberately leaving out information needed to handover any PS connections. This deliberately incomplete Handover to UTRAN command is then sent to the BSS 20 via the CN 11, and thence on to the UE RRC 142 via the Handover command 206. Alternatively, the t-RNC 10 may include a complete Handover to UTRAN command in the Relocation request ack 204, including information for both PS and CS connections. The CN 11, however, may then strip the Handover to UTRAN command of the PS information, and in the Handover Command 205 include only the information needed for handing over CS connections in the Handover to UTRAN command. This stripped Handover to UTRAN command would then be forwarded to the UE RRC 142 via the BSS 20. Finally, it may be the BSS 20 itself that generates an incomplete Handover to UTRAN command in the Handover command 206, insuring that the Handover command 206 contains only enough information to enable the UE 100 to handover the CS connections to the t-RNC 10.
Upon receiving the Handover to UTRAN command, the RRC layer 142 must parse the Handover to UTRAN command to determine what connections are being handed over. This parsing is described later. However, as the Handover to UTRAN command contains only information need to hand over the CS connections, the RRC layer 142 determines that only CS connections are being handed over, and behaves accordingly. The UE 100 thus succeeds in establishing a CS connection (or connections) with the t-RNC 10 to re-establish CS services. This is detected by the t-RNC 10, which notifies the CN 11 with a Relocation detect message 207. At this time as well, the RRC layer 142 informs the upper layer 143 (i.e., the MM/GMM layer 143m) that there are no PS signaling connections and no PS radio access bearers (RABs) Not only does this enable the upper layer 143 to know that the PS services have not been handed over, but it also enables the upper layer 143 to know that the UE 100 is now camped on a UMTS system rather than the non-UMTS system. This is useful information, as the behavior of the MM/GMM layer 143m may change depending upon the type of network upon which the UE 100 is camped.
The RRC 142 sends a Handover to UTRAN complete message 208 to the t-RNC 10 (which establishes the RRC signaling connection), completing the Handover to UTRAN procedure between the UE 100 and the t-RNC 10. The t-RNC 10 correspondingly informs the CN 11 with a Relocation complete message 209, and the CN 11 responds by sending a Clear Command 210 to the BSS 20. The Clear Command 210 is responded to with a Clear Complete message 211. In response to learning that the UE 100 is now camped on the UTRAN, the MM/GMM layer 143m initiates a routing area update procedure by sending a Routing Area Update Request 212 to the CN 11. The purpose of the routing area update procedure is to change from the old 2G-SGSN to the new 3G-SGSN. The CN 11 performs various procedures, which culminate in the sending of a Routing Area Update Accept message 213 to the MM/GMM 143, and whichresponds with a Routing Area Update Complete message 214. Thereafter, the UE 100 can work with the UTRAN to re-establish the PS services. It should be noted that the sequencing of events in the above is preferred, but may be changed. For example, the routing area update procedure may be performed before, or concurrently with, the sending of the Handover to UTRAN complete message 208. Other sequences may also possibly be changed. However, re-establishment of PS services is preferably done after the routing area update procedure.
There are two ways to perform the PS RAB re-establishment procedure. For the first, it is the UE 100 that initiates the PS RAB re-establishment procedure. For the second, it is the UTRAN (by way of the t-RNC 10) that initiates the PS RAB re-establishment procedure. Please refer to FIG. 3. FIG. 3 is a message sequence chart for performing a first embodiment PS RAB re-establishment procedure to re-establish PS services. In this first embodiment, it is the UE 100 that initiates the PS RAB re-establishment procedure. After the routing area update procedure, the MM/GMM 143m of the UE 100 sends a Service Request message to the SGSN. This is in response to learning that PS services are no longer available after the handover to UTRAN procedure. If the PS signaling connection established during the routing area update procedure is not released, then the SGSN responds with a Service Accept message to the UE 100, and so informs the t-RNC 10 with a Radio Access Bearer Assignment Request. If the PS signaling connection established during the routing area update procedure is released, then the SGSN performs various security functions to authenticate the UE 100. After the above, the t-RNC 10 sends a Radio Bearer Setup message to the UE 100, which indicates to the UE 100 the new Radio Bearer Identity established and the corresponding RAB ID. The UE 100 responds with a Radio Bearer Setup Complete message, and at this point, as far as the UE 100 is concerned, the PS RAB re-establishment procedure is complete and PS services are restored to the user of the UE 100. The t-RNC 10 responds by sending a Radio Access Bearer Assignment Response message to the SGSN. For each RAB re-established with a modified QoS profile, the SGSN may optionally initiate a PDP Context Modification procedure to inform the UE 100 and the GGSN of the new negotiated QoS profile for the corresponding PDP context. The UE 100 can then send or receive an uplink protocol data unit (PDU).
Please refer to FIG. 4. FIG. 4 is a message sequence chart for performing a second embodiment PS RAB re-establishment procedure to re-establish PS services. In this second embodiment, it is the UTRAN that initiates the PS RAB re-establishment procedure. In this case, it should be noted that the PS signaling connection established during the routing area update procedure is not released. In response to learning that PS services are no longer available after the handover to UTRAN procedure, the SGSN sends a Radio Access Bearer Assignment Request to the t-RNC 10 to re-establish RABs for every appropriately activated PDP context. In response, the t-RNC 10 sends a Radio Bearer Setup message to the UE 100, which indicates to the UE 100 the new radio bearer identity established, and the corresponding RAB ID. The UE 100 responds with a Radio Bearer Setup Complete message, and at this point, as far as the UE 100 is concerned, the PS RAB re-establishment procedure is complete and PS services are restored to the user of the UE 100. The t-RNC 10 responds by sending a Radio Access Bearer Assignment Response message to the SGSN. For each RAB re-established with a modified QoS profile, the SGSN may optionally initiate a PDP Context Modification procedure to inform the UE 100 and the GGSN of the new negotiated QoS profile for the corresponding PDP context. The UE 100 can then send an uplink protocol data unit (PDU).
The UE 100 must determine what signaling connections are handed over during the handover to UTRAN command so as to know what sort of procedure to use to transfer messages to the UTRAN (i.e., the t-RNC 10), and does so by parsing the Handover to UTRAN command. Please refer to FIGS. 5 to 8. FIG. 5 is a simplified block diagram of a Handover to UTRAN command that holds a complete specification of the RABs that are being handed over. FIG. 6 is a simplified block diagram of a Handover to UTRAN command that utilizes the predefined configurations to indicate which RABs are being handed over. FIG. 7 is a simplified block diagram of a Handover to UTRAN command that utilizes the default configurations to indicate which RABs are being handed over. FIG. 8 is a flow chart of the present invention method for parsing the Handover to UTRAN command to determine what signaling connections are handed over during the Handover to UTRAN procedure. It should be noted that FIGS. 5 to 7 show only those portions of the Handover to UTRAN command that are relevant to the present invention method. A complete description of the Handover to UTRAN command data structure can be found in 3GPP TS 25.331 clause 10.2.16a.
The format of the Handover to UTRAN command changes depending upon whether the complete specification, predefined configuration or default configuration is used. If, as shown in FIG. 5, a complete specification is used, then an information element (IE) Specification mode 301 will be set to a value “Complete specification”. In this case, then, an IE RAB information to setup list 302 will exist, containing one or more IEs RAB information for setup 303. Each IE RAB information for setup 303 contains an IE CN domain identity 304. The IE CN domain identity 304 can have a value of either “CS domain” or “PS domain”. Consequently, if the IE Specification mode 301 is “Complete specification”, then each IE RAB information for setup 303 is individually extracted and the corresponding IE CN domain identity 304 is checked. If the IE CN domain identity 304 is “PS domain”, then it is determined that a PS signaling connection exists. If the IE CN domain identity 304 is “CS domain”, then it is determined that a CS signaling connection exists. Note, then, that it is possible to have both CS and PS signaling connections with a complete specification type Handover to UTRAN command.
As noted earlier, predefined configurations 147 are downloaded from the UTRAN and stored within the UE 100. With reference to FIG. 6, if the IE Specification mode 311 within the Handover to UTRAN command is set to “Preconfiguration”, then an IE Preconfiguration mode 312 will exist. If the IE Preconfiguration mode 312 is set to “Predefined configuration”, then the IE Preconfiguration mode 312 will hold an integer valued IE Predefined configuration identity 313. This IE Predefined configuration identity 313 indicates which of the predefined configurations 147 should be used, and is used as an index to extract an IE RAB information for setup 148. The extracted IE 148 holds an IE CN domain identity 148c that can be either “CS domain” or “PS domain”. If the IE CN domain identity 148c is “PS domain”, then it is determined that a PS signaling connection exists. If the IE CN domain identity 148c is “CS domain”, then it is determined that a CS signaling connection exists.
With reference to FIG. 7, if the IE Specification mode 321 within the Handover to UTRAN command is set to “Preconfiguration”, then the IE Preconfiguration mode 322 will exist. If the IE Preconfiguration mode 322 is set to “Default configuration”, then an IE RAB info 323 will be present in the Handover to UTRAN command. The IE RAB info 323 has an IE CN domain identity that can be either “CS domain” or “PS domain”. If the IE CN domain identity 324 is “PS domain”, then it is determined that a PS signaling connection exists. If the IE CN domain identity 324 is “CS domain”, then it is determined that a CS signaling connection exists.
In contrast to the prior art, the present invention does not include PS information in a Handover to UTRAN command when both PS and CS RABs are established with the non-UMTS network at the time of the handover procedure. This helps to ensure that CS services are handed over smoothly and in an uninterrupted manner. PS services are then restored after the CS services are handed over, and ideally after performing a routing area update procedure, as this ensures that packets are properly routed. Additionally, the present invention provides an explicit method that enables a wireless device to determine which services (CS, PS or both) are being handed over during a Handover to UTRAN procedure.
Those skilled in the art will readily observe that numerous modifications and alterations of the device may be made while retaining the teachings of the invention. Accordingly, the above disclosure should be construed as limited only by the metes and bounds of the appended claims.

Claims (28)

What is claimed is:
1. A method for performing an inter system handover to Universal Terrestrial Radio Access Network (UTRAN) procedure, the method comprising:
a wireless device establishing simultaneous circuit switched (CS) and packet switched (PS) services with a first radio access technology (RAT) system;
with the CS and PS services ongoing, the first RAT system transmitting a HANDOVER TO UTRAN COMMAND message to the wireless device to perform a handover to UTRAN procedure, the HANDOVER TO UTRAN COMMAND message excluding information used for handing over PS connections to the UTRAN so that the handover to UTRAN procedure hands over only CS connections;
the wireless device receiving the HANDOVER TO UTRAN COMMAND message;
the wireless device parsing the HANDOVER TO UTRAN COMMAND to determine what connections are handed over during the handover to UTRAN procedure, wherein parsing the HANDOVER TO UTRAN COMMAND to determine what connections are handed over during the handover to UTRAN procedure comprises:
determining a CS connection is handed over if an information element (IE) “Specification mode” in the HANDOVER TO UTRAN COMMAND message is set to “Complete specification” and a core network (CN) domain identity of an IE “RAB information for setup” is a CS domain;
determining a PS connection is handed over if the IE “Specification mode” in the HANDOVER TO UTRAN COMMAND message is set to “Complete specification” and the core CN domain identity of the IE “RAB information for setup” is a PS domain;
determining a CS connection is handed over if the IE “Specification mode” in the HANDOVER TO UTRAN COMMAND message is set to “Preconfiguration”, an IE “Preconfiguration mode” is set to “Predefined configuration”, and the CN domain identity of the IE “RAB information for setup” identified by an IE “Predefined configuration identity” is the CS domain;
determining a PS connection is handed over if the IE “Specification mode” in the HANDOVER TO UTRAN COMMAND message is set to “Preconfiguration”, the IE “Preconfiguration mode” is set to “Predefined configuration”, and the CN domain identity of the IE “RAB information for setup” identified by the IE “Predefined configuration identity” is the PS domain;
determining a CS connection is handed over if the IE “Specification mode” in the HANDOVER TO UTRAN COMMAND message is set to “Preconfiguration”, the IE “Preconfiguration mode” is set to “Default configuration”, and a CN domain identity of an IE “RAB info” is the CS domain; and
determining a PS signaling connection is handed over if the IE “Specification mode” in the HANDOVER TO UTRAN COMMAND message is set to “Preconfiguration”, the IE “Preconfiguration mode” is set to “Default configuration”, and the CN domain identity of the IE “RAB info” is the PS domain; and
in response to the wireless device parsing the HANDOVER TO UTRAN COMMAND message and determining that only CS connections are handed over during the handover to UTRAN procedure, a radio resource control (RRC) layer within the wireless device informing an upper layer within the wireless device that no PS radio access bearers or no PS signaling connections are present.
2. The method of claim 1 wherein the RRC layer informs the upper layer that no PS radio access bearers or no PS signaling connections are present after successful completion of the handover to UTRAN procedure.
3. The method of claim 1 further comprising performing a routing area update procedure.
4. The method of claim 3 wherein in response to the RRC layer informing the upper layer that no PS radio access bearers or no PS signaling connections are present, the upper layer initiates the routing area update procedure.
5. The method of claim 3 further comprising the wireless device initiating re-establishment of radio access bearers in response to determining that only CS connections are handed over during the handover to UTRAN procedure.
6. The method of claim 5 wherein the re-establishment of radio access bearers is performed to re-establish PS services.
7. The method of claim 5 wherein the re-establishment of radio access bearers is performed by sending a SERVICE REQUEST message after completion of the routing area update procedure.
8. The method of claim 3 further comprising a network initiating re-establishment of radio access bearers in response to determining that only CS connections are handed over during the handover to UTRAN procedure.
9. The method of claim 8 wherein the re-establishment of radio access bearers is performed to re-establish PS services.
10. The method of claim 8 wherein the re-establishment of radio access bearers is performed by sending a RAB assignment request message after completion of the routing area update procedure.
11. A wireless device comprising a central processing unit (CPU) and memory, the memory containing program code executable by the CPU for performing the following steps:
receiving a HANDOVER TO UTRAN COMMAND message from a first RAT system to perform a handover to Universal Terrestrial Radio Access Network (UTRAN) procedure;
parsing the HANDOVER TO UTRAN COMMAND to determine what connections are handed over during the handover to UTRAN procedure, wherein the program code associated with parsing the HANDOVER TO UTRAN COMMAND to determine what connections are handed over during the handover to UTRAN procedure is capable of performing the following steps:
determining a CS signaling connection is handed over if an information element (IE) “Specification mode” in the HANDOVER TO UTRAN COMMAND message is set to “Complete specification” and a core network (CN) domain identity of an IE “RAB information for setup” is a CS domain;
determining a PS signaling connection is handed over if the IE “Specification mode” in the HANDOVER TO UTRAN COMMAND message is set to “Complete specification” and the core CN domain identity of the IE “RAB information for setup” is a PS domain;
determining a CS signaling connection is handed over if the IE “Specification mode” in the HANDOVER TO UTRAN COMMAND message is set to “Preconfiguration”, an IE “Preconfiguration mode” is set to “Predefined configuration”, and the CN domain identity of the IE “RAB information for setup” identified by an IE “Predefined configuration identity” is the CS domain;
determining a PS signaling connection is handed over if the IE “Specification mode” in the HANDOVER TO UTRAN COMMAND message is set to “Preconfiguration”, the IE “Preconfiguration mode” is set to “Predefined configuration”, and the CN domain identity of the IE “RAB information for setup” identified by the IE “Predefined configuration identity” is the PS domain;
determining a CS signaling connection is handed over if the IE “Specification mode” in the HANDOVER TO UTRAN COMMAND message is set to “Preconfiguration”, the IE “Preconfiguration mode” is set to “Default configuration”, and a CN domain identity of an IE “RAB info” is the CS domain; and
determining a PS signaling connection is handed over if the IE “Specification mode” in the HANDOVER TO UTRAN COMMAND message is set to “Preconfiguration”, the IE “Preconfiguration mode” is set to “Default configuration”, and the CN domain identity of the IE “RAB info” is the PS domain; and
in response to parsing the HANDOVER TO UTRAN COMMAND message and determining that only circuit switched (CS) connections are handed over during the handover to UTRAN procedure when both CS and packet switched (PS) services are ongoing in the first RAT system upon reception of the HANDOVER TO UTRAN COMMAND message, causing a radio resource control (RRC) layer within the wireless device to inform an upper layer within the wireless device that no PS radio access bearers or no PS signaling connections are present.
12. The wireless device of claim 11 wherein the program code further causes the RRC layer to inform the upper layer that no PS radio access bearers or no PS signaling connections are present after successful completion of the handover to UTRAN procedure when both CS and PS services are ongoing in the first RAT system upon reception of the HANDOVER TO UTRAN COMMAND message.
13. The wireless device of claim 11 wherein the program code further causes the upper layer to perform a routing area update procedure in response to the RRC layer informing the upper layer that no PS radio access bearers or no PS signaling connections are present when both CS and PS services are ongoing in the first RAT system upon reception of the HANDOVER TO UTRAN COMMAND message.
14. The wireless device of claim 13 wherein the program code further causes the wireless device to initiate re-establishment of radio access bearers in response to determining that only CS connections are handed over during the handover to UTRAN procedure when both CS and PS services are ongoing in the first RAT system upon reception of the HANDOVER TO UTRAN COMMAND message.
15. The wireless device of claim 14 wherein the re-establishment of radio access bearers is performed to re-establish PS services.
16. The wireless device of claim 14 wherein the re-establishment of radio access bearers is performed by sending a SERVICE REQUEST message after completion of the routing area update procedure.
17. A wireless system comprising:
a base station network comprising a Universal Mobile Telecommunications System (UMTS) network and a non-UMTS network; and
a user equipment (UE) capable of establishing simultaneous packet switched (PS) and circuit switched (CS) connections with the base station network;
wherein the base station network further comprises:
means for generating and transmitting a HANDOVER TO UTRAN COMMAND message to the UE when CS and PS services are being simultaneously supported by the UE for performing a handover to UTRAN procedure to hand over the UE to the UMTS network from the non-UMTS network, the HANDOVER TO UTRAN COMMAND message excluding information used for handing over PS connections to the UMTS network so that the handover procedure hands over only CS connections;
wherein the UE further comprises:
means for parsing the HANDOVER TO UTRAN COMMAND message to determine what connections are handed over during the handover to UTRAN procedure, wherein the means for parsing the HANDOVER TO UTRAN COMMAND message is capable of performing the following steps:
determining a CS signaling connection is handed over if an information element (IE) “Specification mode” in the HANDOVER TO UTRAN COMMAND message is set to “Complete specification” and a core network (CN) domain identity of an IE “RAB information for setup” is a CS domain;
determining a PS signaling connection is handed over if the IE “Specification mode” in the HANDOVER TO UTRAN COMMAND message is set to “Complete specification” and the core CN domain identity of the IE “RAB information for setup” is a PS domain;
determining a CS signaling connection is handed over if the IE “Specification mode” in the HANDOVER TO UTRAN COMMAND message is set to “Preconfiguration”, an IE “Preconfiguration mode” is set to “Predefined configuration”, and the CN domain identity of the IE “RAB information for setup” identified by an IE “Predefined configuration identity” is the CS domain;
determining a PS signaling connection is handed over if the IE “Specification mode” in the HANDOVER TO UTRAN COMMAND message is set to “Preconfiguration”, the IE “Preconfiguration mode” is set to “Predefined configuration”, and the CN domain identity of the IE “RAB information for setup” identified by the IE “Predefined configuration identity” is the PS domain;
determining a CS signaling connection is handed over if the IE “Specification mode” in the HANDOVER TO UTRAN COMMAND message is set to “Preconfiguration”, the IE “Preconfiguration mode” is set to “Default configuration”, and a CN domain identity of an IE “RAB info” is the CS domain; and
determining a PS signaling connection is handed over if the IE “Specification mode” in the HANDOVER TO UTRAN COMMAND message is set to “Preconfiguration”, the IE “Preconfiguration mode” is set to “Default configuration”, and the CN domain identity of the IE “RAB info” is the PS domain; and
means for causing a radio resource control (RRC) layer within the UE to inform an upper layer within the UE that no PS radio access bearers or no PS signaling connections are present in response to parsing the HANDOVER TO UTRAN COMMAND message and determining that only CS connections are handed over during the handover to UTRAN procedure when both CS and PS services are being simultaneously supported by the UE.
18. The wireless system of claim 17 wherein the UE further comprises means for causing the upper layer to perform a routing area update procedure in response to the RRC layer informing the upper layer that no PS radio access bearers or no PS signaling connections are present when both CS and PS services are being simultaneously supported by the UE.
19. The wireless system of claim 18 wherein the UE further comprises means for causing the UE to initiate re-establishment of radio access bearers in response to determining that only CS connections are handed over during the handover to UTRAN procedure when both CS and PS services are being simultaneously supported by the UE.
20. The wireless system of claim 19 wherein the re-establishment of radio access bearers is performed to re-establish PS services.
21. The wireless system of claim 19 wherein the re-establishment of radio access bearers is performed by sending a SERVICE REQUEST message after completion of the routing area update procedure.
22. The wireless system of claim 17 wherein the base station network further comprises means for initiating re-establishment of radio access bearers in response to determining that only CS connections are handed over during the handover to UTRAN procedure.
23. The wireless system of claim 22 wherein the re-establishment of radio access bearers is performed to re-establish PS services.
24. The wireless system of claim 22 wherein the re-establishment of radio access bearers is performed by sending a RAB assignment request message after completion of an associated routing area update procedure.
25. A method for performing an inter system handover to Universal Terrestrial Radio Access Network (UTRAN) procedure for a wireless device, the method comprising: receiving a HANDOVER TO UTRAN COMMAND message from a first radio access technology (RAT) system for performing a handover to UTRAN procedure; parsing the HANDOVER TO UTRAN COMMAND message to determine what connections are handed over during the handover to UTRAN procedure, wherein parsing the HANDOVER TO UTRAN COMMAND message to determine what connections are handed over during the handover to UTRAN procedure comprises: determining a CS (Circuit Switched) connection is handed over if an information element (IE) “Specification mode” in the HANDOVER TO UTRAN COMMAND message is set to “Complete specification” and a core network (CN) domain identity of an IE “RAB information for setup” is a CS domain; determining a PS (Packet Switched) connection is handed over if the IE “Specification mode” in the HANDOVER TO UTRAN COMMAND message is set to “Complete specification” and the core CN domain identity of the IE “RAB information for setup” is a PS domain; determining a CS connection is handed over if the IE “Specification mode” in the HANDOVER TO UTRAN COMMAND message is set to “Preconfiguration”, an IE “Preconfiguration mode” is set to “Predefined configuration”, and the CN domain identity of the IE “RAB information for setup” identified by an IE “Predefined configuration identity” is the CS domain; determining a PS connection is handed over if the IE “Specification mode” in the HANDOVER TO UTRAN COMMAND message is set to “Preconfiguration”, the IE “Preconfiguration mode” is set to “Predefined configuration”, and the CN domain identity of the IE “RAB information for setup” identified by the IE “Predefined configuration identity” is the PS domain; determining a CS connection is handed over if the IE “Specification mode” in the HANDOVER TO UTRAN COMMAND message is set to “Preconfiguration”, the IE “Preconfiguration mode” is set to “Default configuration”, and a CN domain identity of an IE “RAB info” is the CS domain; and determining a PS signaling connection is handed over if the IE “Specification mode” in the HANDOVER TO UTRAN COMMAND message is set to “Preconfiguration”, the IE “Preconfiguration mode” is set to “Default configuration”, and the CN domain identity of the IE “RAB info” is the PS domain; in response to the wireless device parsing the HANDOVER TO UTRAN COMMAND message and determining that the CS connection is handed over during the handover to UTRAN procedure, a radio resource control (RRC) layer within the wireless device determining that a CS signaling connection exists; and in response to the wireless device parsing the HANDOVER TO UTRAN COMMAND message and determining that the PS connection is handed over during the handover to UTRAN procedure, the RRC layer within the wireless device determining that the PS signaling connection exists.
26. The method of claim 25 further comprising: when only CS connections are determined to be handed over during the handover to UTRAN procedure, the RRC layer informs the upper layer that no PS radio access bearers or no PS signaling connections are present.
27. A wireless device comprising a central processing unit (CPU) and memory, the memory containing program code executable by the CPU for performing the following steps: receiving a HANDOVER TO UTRAN COMMAND message from a first radio access technology (RAT) system to perform a handover to Universal Terrestrial Radio Access Network (UTRAN) procedure; parsing the HANDOVER TO UTRAN COMMAND message to determine what connections are handed over during the handover to UTRAN procedure, wherein the program code associated with parsing the HANDOVER TO UTRAN COMMAND message to determine what connections are handed over during the handover to UTRAN procedure is capable of performing the following steps: determining a CS (Circuit Switched) signaling connection is handed over if an information element (IE) “Specification mode” in the HANDOVER TO UTRAN COMMAND message is set to “Complete specification” and a core network (CN) domain identity of an IE “RAB information for setup” is a CS domain; determining a PS (Packet Switched) signaling connection is handed over if the IE “Specification mode” in the HANDOVER TO UTRAN COMMAND message is set to “Complete specification” and the core CN domain identity of the IE “RAB information for setup” is a PS domain; determining a CS signaling connection is handed over if the IE “Specification mode” in the HANDOVER TO UTRAN COMMAND message is set to “Preconfiguration”, an IE “Preconfiguration mode” is set to “Predefined configuration”, and the CN domain identity of the IE “RAB information for setup” identified by an IE “Predefined configuration identity” is the CS domain; determining a PS signaling connection is handed over if the IE “Specification mode” in the HANDOVER TO UTRAN COMMAND message is set to “Preconfiguration”, the IE “Preconfiguration mode” is set to “Predefined configuration”, and the CN domain identity of the IE “RAB information for setup” identified by the IE “Predefined configuration identity” is the PS domain; determining a CS signaling connection is handed over if the IE “Specification mode” in the HANDOVER TO UTRAN COMMAND message is set to “Preconfiguration”, the IE “Preconfiguration mode” is set to “Default configuration”, and a CN domain identity of an IE “RAB info” is the CS domain; and determining a PS signaling connection is handed over if the IE “Specification mode” in the HANDOVER TO UTRAN COMMAND message is set to “Preconfiguration”, the IE “Preconfiguration mode” is set to “Default configuration”, and the CN domain identity of the IE “RAB info” is the PS domain; in response to parsing the HANDOVER TO UTRAN COMMAND message and determining that the CS signaling connection is handed over during the handover to UTRAN procedure, causing a radio resource control (RRC) layer within the wireless device to determine that the a CS signaling connection exists; and in response to parsing the HANDOVER TO UTRAN COMMAND message and determining that the PS signaling connection is handed over during the handover to UTRAN procedure, causing the RRC layer within the wireless device to determine that the PS signaling connection exists.
28. The wireless device of claim 27 wherein the program code further causes the RRC layer to inform the upper layer that no PS radio access bearers or no PS signaling connections are present when only CS signaling connections are determined to be handed over during the handover to UTRAN procedure.
US12/542,722 2003-07-02 2009-08-18 Inter-rat handover to UTRAN with simultaneous PS and CS domain services Active 2026-02-08 USRE43293E1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
US12/542,722 USRE43293E1 (en) 2003-07-02 2009-08-18 Inter-rat handover to UTRAN with simultaneous PS and CS domain services

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
US10/610,791 US7382750B2 (en) 2003-07-02 2003-07-02 Inter-RAT handover to UTRAN with simultaneous PS and CS domain sevices
US12/542,722 USRE43293E1 (en) 2003-07-02 2009-08-18 Inter-rat handover to UTRAN with simultaneous PS and CS domain services

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
US10/610,791 Reissue US7382750B2 (en) 2003-07-02 2003-07-02 Inter-RAT handover to UTRAN with simultaneous PS and CS domain sevices

Publications (1)

Publication Number Publication Date
USRE43293E1 true USRE43293E1 (en) 2012-04-03

Family

ID=33435415

Family Applications (2)

Application Number Title Priority Date Filing Date
US10/610,791 Ceased US7382750B2 (en) 2003-07-02 2003-07-02 Inter-RAT handover to UTRAN with simultaneous PS and CS domain sevices
US12/542,722 Active 2026-02-08 USRE43293E1 (en) 2003-07-02 2009-08-18 Inter-rat handover to UTRAN with simultaneous PS and CS domain services

Family Applications Before (1)

Application Number Title Priority Date Filing Date
US10/610,791 Ceased US7382750B2 (en) 2003-07-02 2003-07-02 Inter-RAT handover to UTRAN with simultaneous PS and CS domain sevices

Country Status (6)

Country Link
US (2) US7382750B2 (en)
EP (1) EP1494494B1 (en)
CN (1) CN1305331C (en)
CA (1) CA2465139C (en)
DE (1) DE602004010575T2 (en)
TW (1) TWI269593B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20130250032A1 (en) * 2012-03-23 2013-09-26 Henrik ANDRÉ-JÖNSSON Method and Arrangement for Supporting Hand Over of a Mobile Terminal

Families Citing this family (54)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP1382215B1 (en) * 2001-04-23 2008-01-16 Nokia Corporation Method and system for implementing a signalling connection in a distributed radio access network
US7565145B2 (en) * 2002-10-18 2009-07-21 Kineto Wireless, Inc. Handover messaging in an unlicensed mobile access telecommunications system
GB0413484D0 (en) * 2004-06-16 2004-07-21 Nokia Corp Inter-mode/inter-rat handover
US7940746B2 (en) 2004-08-24 2011-05-10 Comcast Cable Holdings, Llc Method and system for locating a voice over internet protocol (VoIP) device connected to a network
US7463602B2 (en) * 2004-09-13 2008-12-09 Research In Motion Limited Configuring signaling radio bearer information in a user equipment protocol stack
DE102005005254B4 (en) 2005-02-04 2007-05-10 Infineon Technologies Ag A mobile radio communication system, method for operating a mobile radio communication system, core network switching layer unit and method for operating a core network network layer unit
US7616956B2 (en) * 2005-03-15 2009-11-10 Interdigital Technology Corporation Measurement request report extensions for media independent handover
EP1864542B1 (en) * 2005-03-30 2014-09-03 Qualcomm Incorporated Utilizing a same target cell during circuit-switched and packet switched handover
BRPI0608476A2 (en) 2005-03-30 2010-01-05 Nokia Corp transfer signaling method for initialization by the source radio access network element after determining radio interface transfer measurements, source radio access network element, method to perform on the radio access network element target after the source radio access network element has determined that the transfer is appropriate, target radio access network element, radio access network element, mobile station, computer program, system, transfer method to communicate the resources provided to the mobile station, and integrated circuit for use in the radio access network element
CN101180909A (en) * 2005-03-30 2008-05-14 诺基亚公司 System, devices, methods and programs for reducing service interruption during routing area change
KR101092447B1 (en) * 2005-04-11 2011-12-13 엘지전자 주식회사 Method for setting link of mobile terminal for performing handover
WO2007004051A1 (en) * 2005-07-06 2007-01-11 Nokia Corporation Secure session keys context
US8553643B2 (en) 2005-07-19 2013-10-08 Qualcomm Incorporated Inter-system handover using legacy interface
US7836294B2 (en) * 2005-08-08 2010-11-16 Motorola Mobility, Inc. Mobile station security mode method
CN101278593A (en) * 2005-10-07 2008-10-01 阿尔卡特朗讯公司 Method and apparatus for assisting a radio communication transfer in a cellular radio comunication system
US8134977B2 (en) * 2005-10-27 2012-03-13 Qualcomm Incorporated Tune-away protocols for wireless systems
US8068835B2 (en) 2005-10-27 2011-11-29 Qualcomm Incorporated Tune-away and cross paging systems and methods
US8229433B2 (en) * 2005-10-27 2012-07-24 Qualcomm Incorporated Inter-frequency handoff
US9247467B2 (en) * 2005-10-27 2016-01-26 Qualcomm Incorporated Resource allocation during tune-away
CN1984438B (en) * 2005-12-15 2010-10-06 华为技术有限公司 Method and system for establishing connection
US20070155339A1 (en) * 2006-01-04 2007-07-05 Innovative Sonic Limited Method and apparatus for initialization of integrity protection
EP1835776B1 (en) * 2006-03-17 2008-08-20 Research In Motion Limited Method and apparatus to restore always-on connectivity during network handover
US8078178B2 (en) * 2006-03-17 2011-12-13 Research In Motion Limited Method and apparatus to restore always-on connectivity during network handover
KR101495107B1 (en) 2006-06-20 2015-02-25 인터디지탈 테크날러지 코포레이션 Methods and system for performing handover in a wireless communication system
EP2104996A1 (en) * 2007-01-15 2009-09-30 Telefonaktiebolaget LM Ericsson (publ) Method and apparatus for providing circuit switched domain services over a packet switchednetwork
BRPI0721811A2 (en) * 2007-06-08 2013-02-13 Ericsson Telefon Ab L M Method for performing global system circuit switched services for mobile communications / broadband code division multiple access over long-term evolution radio access, combination of an access connection point and a mobility management entity for use in a telecommunication network, and mobile switching center for use in a telecommunication network
GB2455706A (en) * 2007-12-12 2009-06-24 Nec Corp Inter-RAT handover signalling and related mobile radio communications device
KR20090073443A (en) * 2007-12-31 2009-07-03 엘지전자 주식회사 Method for inter rat handover
CN101971669B (en) * 2008-01-10 2014-08-20 爱立信电话股份有限公司 Improved method and arrangement in a telecommunications system
KR20100120664A (en) 2008-02-21 2010-11-16 알까뗄 루슨트 Method, user equipment and communication system for inter-rat handover in 3g lte
US8199719B2 (en) 2008-03-13 2012-06-12 Apple Inc. Methods and apparatus for performing handover between a long term evolution (LTE) network and another type of radio access network
WO2009117588A1 (en) * 2008-03-21 2009-09-24 Interdigital Patent Holdings, Inc. Method and apparatus to enable fallback to circuit switched domain from packet switched domain
US20090245200A1 (en) * 2008-03-31 2009-10-01 Violeta Cakulev Method and apparatus for communication between wireless telecommunications networks of different technology types
EP2890186B1 (en) * 2008-04-01 2016-03-09 Wireless Future Technologies Inc. Apparatus,method and non-transitory computer readable storage medium for inter-domain handover
WO2009149600A1 (en) * 2008-06-13 2009-12-17 Huawei Technologies Co., Ltd. Method of load balancing in a mobile communications system
US9232452B2 (en) * 2008-10-31 2016-01-05 Htc Corporation Method of handling an inter rat handover in wireless communication system and related communication device
WO2010079715A1 (en) * 2009-01-06 2010-07-15 シャープ株式会社 MOBILE COMMUNICATION SYSTEM, QoS CONTROL STATION, AND MOBILE STATION
JP5456883B2 (en) 2009-04-23 2014-04-02 テレフオンアクチーボラゲット エル エム エリクソン(パブル) PS to CS handover indicator
CA2779492C (en) 2009-10-30 2016-03-22 Interdigital Patent Holdings, Inc. Method and apparatus for efficient signaling and usage of resources for wireless communications supporting circuit switched and packet switched sessions
US8086236B2 (en) * 2010-01-06 2011-12-27 Htc Corporation Methods to configure proximity indication in wireless communications systems
US8929284B2 (en) * 2010-02-03 2015-01-06 Qualcomm Incorporated Method and apparatus to enable inter-system transfer of a packet switched session
JP4841675B2 (en) * 2010-02-09 2011-12-21 株式会社エヌ・ティ・ティ・ドコモ Mobile communication system, network device, and mobile communication method
US8081604B2 (en) * 2010-02-22 2011-12-20 Htc Corporation Method and apparatus for handling SRVCC in an inter radio access technology handover
KR101857530B1 (en) 2010-05-13 2018-05-15 삼성전자주식회사 Method and system of managing voice call and ip media sessions in a wireless network environment
US8346274B2 (en) 2010-05-21 2013-01-01 Apple Inc. Method to control multiple radio access bearers in a wireless device
US20110299429A1 (en) * 2010-06-02 2011-12-08 Kundan Tiwari Methods for handling ps and cs communication service
US9001784B2 (en) * 2010-09-09 2015-04-07 Qualcomm Incorporated Handover of multimode user equipment between radio access technologies for reduced call setup time
US9179381B2 (en) * 2011-09-29 2015-11-03 Qualcomm Incorporated Reducing network-initiated QoS interruption time when radio and core networks are out of synchronization due to different underlying technologies
US20140254547A1 (en) * 2013-03-06 2014-09-11 Qualcomm Incorporated Uplink buffer status reporting for multiple preserved pdp contexts
CN105917702B (en) * 2014-01-14 2020-03-03 Lg电子株式会社 Path switching method for dual connection in wireless communication system and apparatus thereof
US10440626B2 (en) * 2015-03-20 2019-10-08 Parallel Wireless, Inc. Content-aware inter-RAT RAB steering
EP3195655B1 (en) 2016-04-01 2020-01-29 Telefonaktiebolaget LM Ericsson (PUBL) Method and device for resource configuration in handover
US10708830B2 (en) * 2017-06-06 2020-07-07 Lg Electronics Inc. Method and cell for determining handover of PDU session
EP3756380B1 (en) * 2018-02-20 2023-08-09 Nokia Technologies Oy Edge service continuity

Citations (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2001089251A1 (en) 2000-05-17 2001-11-22 Nokia Corporation Connections in a communication system
US6549779B1 (en) * 2000-01-17 2003-04-15 Telefonaktiebolaget Lm Ericsson (Publ) Method and system for improving the performance of inter-systems handovers
WO2003037022A2 (en) 2001-10-18 2003-05-01 Telefonaktiebolaget Lm Ericsson (Publ) Mobile telecommunications networks
US20030114158A1 (en) 2001-12-18 2003-06-19 Lauri Soderbacka Intersystem handover of a mobile terminal
US6643513B2 (en) * 2001-11-15 2003-11-04 Nokia Corporation Method and apparatus for providing immediate ciphering after an inter-system UTRAN-GSM handover
US20040228491A1 (en) * 2003-05-13 2004-11-18 Chih-Hsiang Wu Ciphering activation during an inter-rat handover procedure
US20040240430A1 (en) 2003-05-27 2004-12-02 Innomedia Pte Ltd. IP gateway for hybrid circuit switched and IP based mobile wireless telephone system
US6845095B2 (en) * 2001-04-27 2005-01-18 Telefonaktiebolaget Lm Ericsson (Publ) Efficient header handling involving GSM/EDGE radio access networks
US20050239461A1 (en) 2002-06-21 2005-10-27 The Regents Of The Unviersity Of California Registration of a wlan as a umts routing area for wlan-umts interworking
US6963745B2 (en) * 2002-01-23 2005-11-08 Samsung Electronics Co., Ltd. Method for performing inter system handovers in mobile telecommunication system
US7123910B2 (en) 2001-05-10 2006-10-17 Nortel Networks Limited System and method for message redirection between mobile telecommunication networks with different radio access technologies
US7181218B2 (en) * 2001-04-10 2007-02-20 Telefonaktiebolaget Lm Ericsson (Publ) Commanding handover between differing radio access technologies
US7257403B2 (en) * 2002-05-03 2007-08-14 Telefonaktiebolaget Lm Ericsson (Publ) Service-based inter-system handover

Patent Citations (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6549779B1 (en) * 2000-01-17 2003-04-15 Telefonaktiebolaget Lm Ericsson (Publ) Method and system for improving the performance of inter-systems handovers
US20030169725A1 (en) 2000-05-17 2003-09-11 Kalle Ahmavaara Connections in a comunication system
WO2001089251A1 (en) 2000-05-17 2001-11-22 Nokia Corporation Connections in a communication system
US7181218B2 (en) * 2001-04-10 2007-02-20 Telefonaktiebolaget Lm Ericsson (Publ) Commanding handover between differing radio access technologies
US6845095B2 (en) * 2001-04-27 2005-01-18 Telefonaktiebolaget Lm Ericsson (Publ) Efficient header handling involving GSM/EDGE radio access networks
US7123910B2 (en) 2001-05-10 2006-10-17 Nortel Networks Limited System and method for message redirection between mobile telecommunication networks with different radio access technologies
WO2003037022A2 (en) 2001-10-18 2003-05-01 Telefonaktiebolaget Lm Ericsson (Publ) Mobile telecommunications networks
US6643513B2 (en) * 2001-11-15 2003-11-04 Nokia Corporation Method and apparatus for providing immediate ciphering after an inter-system UTRAN-GSM handover
US20030114158A1 (en) 2001-12-18 2003-06-19 Lauri Soderbacka Intersystem handover of a mobile terminal
US6963745B2 (en) * 2002-01-23 2005-11-08 Samsung Electronics Co., Ltd. Method for performing inter system handovers in mobile telecommunication system
US7257403B2 (en) * 2002-05-03 2007-08-14 Telefonaktiebolaget Lm Ericsson (Publ) Service-based inter-system handover
US20050239461A1 (en) 2002-06-21 2005-10-27 The Regents Of The Unviersity Of California Registration of a wlan as a umts routing area for wlan-umts interworking
US20040228491A1 (en) * 2003-05-13 2004-11-18 Chih-Hsiang Wu Ciphering activation during an inter-rat handover procedure
US20040240430A1 (en) 2003-05-27 2004-12-02 Innomedia Pte Ltd. IP gateway for hybrid circuit switched and IP based mobile wireless telephone system

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20130250032A1 (en) * 2012-03-23 2013-09-26 Henrik ANDRÉ-JÖNSSON Method and Arrangement for Supporting Hand Over of a Mobile Terminal
US9119116B2 (en) * 2012-03-23 2015-08-25 Telefonaktiebolaget L M Ericsson (Publ) Method and arrangement for supporting hand over of a mobile terminal

Also Published As

Publication number Publication date
EP1494494B1 (en) 2007-12-12
CN1305331C (en) 2007-03-14
CN1578495A (en) 2005-02-09
CA2465139A1 (en) 2005-01-02
EP1494494A2 (en) 2005-01-05
DE602004010575D1 (en) 2008-01-24
CA2465139C (en) 2007-11-06
US20050003819A1 (en) 2005-01-06
TW200503563A (en) 2005-01-16
EP1494494A3 (en) 2005-11-09
TWI269593B (en) 2006-12-21
DE602004010575T2 (en) 2008-12-04
US7382750B2 (en) 2008-06-03

Similar Documents

Publication Publication Date Title
USRE43293E1 (en) Inter-rat handover to UTRAN with simultaneous PS and CS domain services
US11057812B2 (en) Mobile radio communication system
KR100588072B1 (en) A communication system comprising a plurality of communication networks
EP2521395B1 (en) Method of handling an inter RAT handover in wireless communication system
EP2191658B1 (en) System for providing voice service in a multimedia mobile network
JP3936334B2 (en) Method and apparatus for providing immediate encryption after inter-system UTRAN-GMS handover
CN101218843B (en) Method and base station controller for handover of simultaneous voice and data sessions
US7392052B2 (en) Hard handover method and controller
US8730906B2 (en) Apparatus and method for removing path management
US20060159047A1 (en) Method and system for context transfer across heterogeneous networks
WO2011083663A1 (en) Mobile terminal and mobile communication method
WO2012130046A1 (en) Method and apparatus for transferring service bearer
WO2013097373A1 (en) Method and apparatus for service equalization
JP4433152B2 (en) Method of handover in a multi-mode telecommunications network
EP1871134A1 (en) A method for realizing handover between systems
CN105282769A (en) Network switching processing method and device
EP1537753B1 (en) Method and apparatus for cell reselection within a communications system
JP4597520B2 (en) Authentication in hybrid communication networks
WO2010145490A1 (en) Method, apparatus and system for handoff between systems in packet domains
KR100713485B1 (en) Method for controlling handover of packet switch call between the first mobile communication system capable of hspda service and the second mobile communication system capable of non-hspda service
KR20050102370A (en) Mobile communication system and method for packet hand-over between asynchronous communication network and synchronous communication network, and mobile communication terminal therefor
KR100733035B1 (en) Method for processing handover

Legal Events

Date Code Title Description
AS Assignment

Owner name: HTC CORPORATION, TAIWAN

Free format text: ASSIGNMENT OF ASSIGNORS INTEREST;ASSIGNOR:WU, CHIH-HSIANG;REEL/FRAME:023114/0633

Effective date: 20090805

FPAY Fee payment

Year of fee payment: 8

MAFP Maintenance fee payment

Free format text: PAYMENT OF MAINTENANCE FEE, 12TH YEAR, LARGE ENTITY (ORIGINAL EVENT CODE: M1553); ENTITY STATUS OF PATENT OWNER: LARGE ENTITY

Year of fee payment: 12