WO1997043892A2 - System and method for estimating a load to optimize a backup energy system response - Google Patents

System and method for estimating a load to optimize a backup energy system response Download PDF

Info

Publication number
WO1997043892A2
WO1997043892A2 PCT/US1997/007666 US9707666W WO9743892A2 WO 1997043892 A2 WO1997043892 A2 WO 1997043892A2 US 9707666 W US9707666 W US 9707666W WO 9743892 A2 WO9743892 A2 WO 9743892A2
Authority
WO
WIPO (PCT)
Prior art keywords
link
voltage
converter
load
rate
Prior art date
Application number
PCT/US1997/007666
Other languages
French (fr)
Other versions
WO1997043892A3 (en
Inventor
Jeffrey C. Emmerich
Original Assignee
Superconductivity, Inc.
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Superconductivity, Inc. filed Critical Superconductivity, Inc.
Publication of WO1997043892A2 publication Critical patent/WO1997043892A2/en
Publication of WO1997043892A3 publication Critical patent/WO1997043892A3/en

Links

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J9/00Circuit arrangements for emergency or stand-by power supply, e.g. for emergency lighting
    • H02J9/04Circuit arrangements for emergency or stand-by power supply, e.g. for emergency lighting in which the distribution system is disconnected from the normal source and connected to a standby source
    • H02J9/06Circuit arrangements for emergency or stand-by power supply, e.g. for emergency lighting in which the distribution system is disconnected from the normal source and connected to a standby source with automatic change-over, e.g. UPS systems
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01RMEASURING ELECTRIC VARIABLES; MEASURING MAGNETIC VARIABLES
    • G01R19/00Arrangements for measuring currents or voltages or for indicating presence or sign thereof
    • G01R19/0092Arrangements for measuring currents or voltages or for indicating presence or sign thereof measuring current only
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J9/00Circuit arrangements for emergency or stand-by power supply, e.g. for emergency lighting
    • H02J9/04Circuit arrangements for emergency or stand-by power supply, e.g. for emergency lighting in which the distribution system is disconnected from the normal source and connected to a standby source
    • H02J9/06Circuit arrangements for emergency or stand-by power supply, e.g. for emergency lighting in which the distribution system is disconnected from the normal source and connected to a standby source with automatic change-over, e.g. UPS systems
    • H02J9/062Circuit arrangements for emergency or stand-by power supply, e.g. for emergency lighting in which the distribution system is disconnected from the normal source and connected to a standby source with automatic change-over, e.g. UPS systems for AC powered loads
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02MAPPARATUS FOR CONVERSION BETWEEN AC AND AC, BETWEEN AC AND DC, OR BETWEEN DC AND DC, AND FOR USE WITH MAINS OR SIMILAR POWER SUPPLY SYSTEMS; CONVERSION OF DC OR AC INPUT POWER INTO SURGE OUTPUT POWER; CONTROL OR REGULATION THEREOF
    • H02M1/00Details of apparatus for conversion
    • H02M1/0067Converter structures employing plural converter units, other than for parallel operation of the units on a single load
    • H02M1/007Plural converter units in cascade

Definitions

  • the present invention relates generally to estimating a load and more particularly to a method for load estimation using only DC link voltage measurements to determine an average load current which is used as an initial condition for optimally controlling a converter connected between a backup DC energy source and a customer load.
  • Known inverter systems i.e., commercially available motor drives and uninterruptable power supply (UPS) systems, etc.
  • UPS uninterruptable power supply
  • Normally, the DC link of the inverter system is supported by the utility via a rectifier. When the utility fails, the DC link voltage falls as the inverter continues to draw from it. The voltage quickly falls to a level insufficient to support the inverter, and the system subsequently trips off line.
  • a backup energy source delivers supplemental energy to stop the fall of the DC link and hold it at a potential above the trip point.
  • Energy is provided through a power converter which is typically waiting in a standby mode until the DC link falls. This converter must assume the entire load as quickly as possible so as to prevent the further collapse of the DC link voltage.
  • the method provides a non-intrusive estimation of a load that a converter is about to assume by looking at only DC link voltage information. It is an advantage of the present invention to provide a method for estimating the load to be assumed by a converter that allows converter switching to commence at a level optimized to the anticipated load. This advantage minimizes any voltage undershoot as the converter picks up the load.
  • the method has the steps of: sensing a voltage of the DC link; connecting a converter between the backup energy supply and the DC link; evaluating a rate of change of the voltage of the DC link; determining an estimate of the average load current representing an optimized load using the rate of change of the DC link voltage; and controlling the converter using the average load current to deliver an optimized power output level from the backup energy supply to the load.
  • the DC link is embodied as a capacitor bank.
  • the step of evaluating a rate of change of the DC link voltage is performed by representing a plurality of DC link voltage samples taken over time as points in an x-y coordinate system connected by a best fit line such that the slope of the line represents the rate of change of the voltage of the DC link.
  • the step of evaluating the rate of change of the DC link voltage may be implemented using a first plurality of serially connected sample and hold amplifiers having a second plurality of difference amplifiers selectively connected to the first plurality of sample and hold amplifiers and an operational amplifier summer connected to sum outputs of the difference amplifiers to produce an output.
  • the output is used to control the converter for an optimized power switchover.
  • the method of the present invention provides an estimate of the load about to be assumed by the converter based upon the rate of change of the voltage of the DC link. This rate of change of the DC link voltage may be estimated by observing a slope of the voltage rate of change. This slope may be determined using a curve fitting algorithm as described below.
  • such a curve-fitting algorithm can be represented and implemented by a finite impulse response (FIR) filter.
  • FIR finite impulse response
  • Such a FIR filter is easily implemented using analog circuitry as also discussed below.
  • FIG. 1 is a block diagram illustrating interconnection of system components for use in accordance with an embodiment of the method of the present invention.
  • Fig. 2 is an embodiment of a six sample load estimator for use in accordance with an embodiment of the method of the present invention.
  • Fig. 3 is a schematic diagram illustrating an embodiment of an electrical circuit for use in accordance with an embodiment of the method of the present invention.
  • the present invention provides a backup DC energy system which protects inverter systems (i.e., motor drives, UPS's, etc.) against utility power outages and sags.
  • inverter systems i.e., motor drives, UPS's, etc.
  • UPS's UPS's
  • the DC link voltage falls as the inverter continues to draw from it. The voltage will quickly fall to a level insufficient to support the inverter, and the system will trip off line.
  • a non-invasive method for load estimation using only DC link voltage measurements to optimize switching from utility power to the backup DC energy source is provided.
  • a converter having a load estimator which is part of the backup energy system, senses the fallen DC link voltage and delivers supplemental energy to stop the fall of the DC link voltage and hold it at a potential well above the trip point. Energy is thus provided through the power converter which waits in a standby mode until the DC link falls a predetermined amount. This predetermined amount is provided to differentiate between real and false voltage drops thereby ensuring proper switchover operation.
  • the converter must assume the entire load as quickly as possible so as to prevent the further collapse of the DC link voltage. Therefore, a priori knowledge of the load that the converter is about to assume allows converter switching to begin at a level optimized to the load. Such operation minimizes voltage undershoot as the converter picks up the load.
  • Fig. 1 is a block diagram illustrating an arrangement of the system components for performing the method of the present invention.
  • An AC customer load 10 is connected to a utility 12.
  • the utility 12 provides AC power to a rectifier 14.
  • a DC link 16, which comprises a capacitor bank, for example, is connected between the rectifier 14 and a DC to AC inverter 18.
  • the inverter 18 is a device that takes a DC voltage input and provides an AC voltage output. Examples of typical inverters include motor drives and UPS systems, etc.
  • the inverter 18 provides AC power to the AC load 10.
  • an energy storage or supply system 20 for example, a magnet discharge system
  • a DC to DC converter 22 is connected to a DC to DC converter 22.
  • the converter 22 typically remains in a standby condition until the utility 12 fails, then the converter 22 starts operating to deliver energy to the customer AC load 10 via the DC link 16 and inverter 18.
  • the converter 22 gathers information while watching a failure of the utility 12 develop so that when the converter 22 turns on, it knows at what level to operate. For example, as the utility 12 begins to fail, the voltage of the DC link 16 begins to fall proportionately. In particular, the converter 22 measures the DC link voltage and determines when it reaches a predetermined level.
  • the predetermined level is set to ensure that a legitimate sag of power is experienced and needs to be corrected by the converter 22 and not just an occurrence of a false power drop.
  • the converter 22 gathers the voltage information as the voltage of the DC link 16 is falling to estimate the load.
  • the sampled data points may be represented as coordinates in a two- dimensional Cartesian space, ⁇ (Xi/Yi), (X 2 /Y 2 ) / (x 3 ,y 3 )... ⁇ .
  • the x-axis is time and the y-axis is DC link voltage.
  • V DCUnk (t) mt + b wherein m is the slope of the line.
  • a curve-fitting algorithm is used to determine the coefficients, m and b, which describe the best straight line that can be drawn through the sampled data points. Applying such an algorithm minimizes the effects of noise appearing on the feedback signal or the DC link 16.
  • Such an equation has the form of a simple finite impulse response (FIR) filter.
  • FIR finite impulse response
  • Such a filter may be implemented in many ways, using either digital or analog circuitry. Samples are taken continuously, and as the time window spanned by the data samples passes through time, new samples are shifted in and the oldest samples are discarded in a first in, first out fashion. By continually updating the samples as time passes, the load estimator applies a "flying" curve fit to the points in the sample window and returns the slope of the best straight line which can be drawn between them.
  • Fig. 2 is a block diagram of a six sample load estimator referenced generally at 30.
  • the load estimator 30 comprises 12 sample and hold amplifiers, individually numbered 1-12. Each sample and hold amplifier is connected to a clock signal.
  • Fig. 2 also illustrates respective timing diagrams for Clocks 1 and 2.
  • Each amplifier also has an input signal and an output signal.
  • the input signal for sample and hold amplifier 1 is the voltage potential of the DC link 16.
  • the output signal for amplifier 1 is connected to the input of amplifier 2.
  • the output signal of each successive amplifier is connected to the input of the following amplifier.
  • the output of each even-numbered sample and hold amplifier i.e., amplifiers 2, 4, 6 ...) is connected to a difference amplifier or summer junction, for example, summers 34, 36 and 38 shown in Fig. 2.
  • each summer 34, 36, 38 is respectively connected to a constant multiplier Cl, C2, C3 to provide a scaled output.
  • the scaled outputs are then summed at a further summer 40 to provide an output 44.
  • the output 44 is then provided as an initial condition to the converter 22 (see Fig. 1) .
  • the time that the voltage of the DC link 16 is actually allowed to fall may be a relatively short period of time, depending on the DC link capacitance and the load applied. For this reason, a digital implementation may not be as desirable as an analog one.
  • the load estimator equation consists of terms which are the difference between two samples multiplied by a constant gain. These terms are then summed together to form the output.
  • difference amplifiers 34, 36, 38 and operational amplifier summer 40 as indicated in Fig. 2.
  • 2n sample and hold amplifiers i.e., the 12 amplifiers in the six sample load estimator example of Fig. 2 may be cascaded in series. As shown in Fig. 2, this forms a "bucket brigade" of time-shifted analog voltages.
  • each sample and hold amplifier captures the potential present on its input and tracks this voltage on its output.
  • the voltage present on its output at that moment is frozen regardless of input changes.
  • Fig. 3 is a circuit diagram illustrating a preferred implementation of an electrical circuit of the six sample load estimator of Fig. 2. As shown in Fig. 2, the Clock 1 and Clock 2 inputs are provided, as well as inputs to each of the sample and hold amplifiers.
  • the 12 sample and hold amplifiers of Fig. 2 are embodied as four amplifiers on each of three IC chips 50, 52, 54 in Fig. 3.
  • the circuit of Fig. 3 operates similarly to Fig. 2.

Abstract

A method of delivering an optimized power level from a backup energy system (20) to a load (10) connected to a primary energy supply via a DC link (16) and an inverter is provided (18). The method has the steps of: sensing a voltage of the DC link (16) connected to the load (10); connecting a converter (22) between the backup energy supply (20) and the DC link (16); evaluating a rate of change of the voltage of the DC link (16); determining an estimate of the average load current using the rate of change of the DC link voltage; and controlling the converter (22) using the average load current to switch the optimized power output from the backup energy supply (20) to the load (10).

Description

SYSTEM AND METHOD FOR ESTIMATING A LOAD TO OPTIMIZE A BACKUP ENERGY SYSTEM RESPONSE
CROSS-REFERENCE TO RELATED APPLICATIONS
This application claims priority of provisional application, serial number 60/016,943, filed May 6, 1996.
STATEMENT REGARDING FEDERALLY SPONSORED
RESEARCH OR DEVELOPMENT
The U.S. Government has a paid-up license in this invention and the right in limited circumstances to require the patent owner to license others on reasonable terms as provided for by the terms of Contract Nos. FO-4606-89-D-0036 and FO-46O6-95-C-0293 awarded by the Department of Defense, Department of the Air Force.
BACKGROUND OF THE INVENTION The present invention relates generally to estimating a load and more particularly to a method for load estimation using only DC link voltage measurements to determine an average load current which is used as an initial condition for optimally controlling a converter connected between a backup DC energy source and a customer load. Known inverter systems (i.e., commercially available motor drives and uninterruptable power supply (UPS) systems, etc.) experience problems due to utility power outages and sags in power. Normally, the DC link of the inverter system is supported by the utility via a rectifier. When the utility fails, the DC link voltage falls as the inverter continues to draw from it. The voltage quickly falls to a level insufficient to support the inverter, and the system subsequently trips off line. In certain situations, a backup energy source delivers supplemental energy to stop the fall of the DC link and hold it at a potential above the trip point. Energy is provided through a power converter which is typically waiting in a standby mode until the DC link falls. This converter must assume the entire load as quickly as possible so as to prevent the further collapse of the DC link voltage.
Most applications of such a backup energy source do not provide for or allow the use of any in-line instrumentation to measure the load current. Typical ways of measuring the load current to determine the load include inserting a meter in series to measure the load current. However, often times the situation is such that the customer load is inaccessible or it is undesirable to open a line and insert such a measurement device. A system for estimating a load to optimize a power switchover is therefore needed which augments and supplements the customer's system without invasively violating it. BRIEF SUMMARY OF THE INVENTION To this end, a system and method for a load estimation using only DC link voltage measurements is provided. The method provides a non-intrusive estimation of a load that a converter is about to assume by looking at only DC link voltage information. It is an advantage of the present invention to provide a method for estimating the load to be assumed by a converter that allows converter switching to commence at a level optimized to the anticipated load. This advantage minimizes any voltage undershoot as the converter picks up the load.
It is another advantage of the present invention to provide a method for estimating a load using only DC link voltage measurements that is non-intrusive to a customer system.
It is a further advantage of the method of the present invention to set an initial condition so that when the converter starts running, the converter knows how much load is going to be on it based upon the DC link voltage measurements.
These and other advantages may be accomplished in an embodiment of the method of delivering an optimized output power level from a backup energy system to a load connected to a primary energy supply via a DC link and an inverter. The method has the steps of: sensing a voltage of the DC link; connecting a converter between the backup energy supply and the DC link; evaluating a rate of change of the voltage of the DC link; determining an estimate of the average load current representing an optimized load using the rate of change of the DC link voltage; and controlling the converter using the average load current to deliver an optimized power output level from the backup energy supply to the load.
In an embodiment, the step of determining an estimate of the average load current using the rate of change of the DC link voltage is performed in accordance with a formula Iload = CDC ]iak (dVDC iink/dt) , where CDCIink is the capacitance of the DC link. Typically, the DC link is embodied as a capacitor bank. Also, the step of evaluating a rate of change of the DC link voltage is performed by representing a plurality of DC link voltage samples taken over time as points in an x-y coordinate system connected by a best fit line such that the slope of the line represents the rate of change of the voltage of the DC link.
Further, the step of evaluating the rate of change of the DC link voltage may be implemented using a first plurality of serially connected sample and hold amplifiers having a second plurality of difference amplifiers selectively connected to the first plurality of sample and hold amplifiers and an operational amplifier summer connected to sum outputs of the difference amplifiers to produce an output. The output is used to control the converter for an optimized power switchover. The method of the present invention provides an estimate of the load about to be assumed by the converter based upon the rate of change of the voltage of the DC link. This rate of change of the DC link voltage may be estimated by observing a slope of the voltage rate of change. This slope may be determined using a curve fitting algorithm as described below. Further, such a curve-fitting algorithm can be represented and implemented by a finite impulse response (FIR) filter. Such a FIR filter is easily implemented using analog circuitry as also discussed below. Thus, the switchover from utility power during an outage or sag to an energy storage source via a converter, which is operated by initial conditions set by the rate of change of the DC link voltage, is provided. A smooth transition thereby results during the switch from the utility to the backup energy source. The load is closely estimated to the consumer load so that no further drop occurs during the switchover. The load estimation provides better control of the system since the initial condition of the converter is nearly equal to the load to be assumed.
BRIEF DESCRIPTION OF THE SEVERAL VIEWS OF THE DRAWINGS Fig. 1 is a block diagram illustrating interconnection of system components for use in accordance with an embodiment of the method of the present invention.
Fig. 2 is an embodiment of a six sample load estimator for use in accordance with an embodiment of the method of the present invention.
Fig. 3 is a schematic diagram illustrating an embodiment of an electrical circuit for use in accordance with an embodiment of the method of the present invention.
DETAILED DESCRIPTION OF THE INVENTION The present invention provides a backup DC energy system which protects inverter systems (i.e., motor drives, UPS's, etc.) against utility power outages and sags. Normally, the DC link of the inverter system is supported by the utility via a rectifier. When the utility fails, the DC link voltage falls as the inverter continues to draw from it. The voltage will quickly fall to a level insufficient to support the inverter, and the system will trip off line.
A non-invasive method for load estimation using only DC link voltage measurements to optimize switching from utility power to the backup DC energy source is provided. A converter having a load estimator, which is part of the backup energy system, senses the fallen DC link voltage and delivers supplemental energy to stop the fall of the DC link voltage and hold it at a potential well above the trip point. Energy is thus provided through the power converter which waits in a standby mode until the DC link falls a predetermined amount. This predetermined amount is provided to differentiate between real and false voltage drops thereby ensuring proper switchover operation.
In addition, the converter must assume the entire load as quickly as possible so as to prevent the further collapse of the DC link voltage. Therefore, a priori knowledge of the load that the converter is about to assume allows converter switching to begin at a level optimized to the load. Such operation minimizes voltage undershoot as the converter picks up the load.
Turning now to the figures, Fig. 1 is a block diagram illustrating an arrangement of the system components for performing the method of the present invention. An AC customer load 10 is connected to a utility 12. The utility 12 provides AC power to a rectifier 14. A DC link 16, which comprises a capacitor bank, for example, is connected between the rectifier 14 and a DC to AC inverter 18. The inverter 18 is a device that takes a DC voltage input and provides an AC voltage output. Examples of typical inverters include motor drives and UPS systems, etc. The inverter 18 provides AC power to the AC load 10.
In addition, an energy storage or supply system 20, for example, a magnet discharge system, is connected to a DC to DC converter 22. The converter 22 typically remains in a standby condition until the utility 12 fails, then the converter 22 starts operating to deliver energy to the customer AC load 10 via the DC link 16 and inverter 18. The converter 22 gathers information while watching a failure of the utility 12 develop so that when the converter 22 turns on, it knows at what level to operate. For example, as the utility 12 begins to fail, the voltage of the DC link 16 begins to fall proportionately. In particular, the converter 22 measures the DC link voltage and determines when it reaches a predetermined level. The predetermined level is set to ensure that a legitimate sag of power is experienced and needs to be corrected by the converter 22 and not just an occurrence of a false power drop. The converter 22 gathers the voltage information as the voltage of the DC link 16 is falling to estimate the load.
It is desired that the method used to estimate dVDChnk/dt be tolerant of noise that could be present on the DC link 16 or feedback signal. For this reason, a simple differentiating circuit is not preferred since differentiation circuits, by definition, amplify high frequency noise.
Instead, a number of voltage readings are taken over a period of time. The sampled data points may be represented as coordinates in a two- dimensional Cartesian space, {(Xi/Yi), (X2/Y2) / (x3,y3)...}. In this case, the x-axis is time and the y-axis is DC link voltage. Assuming that during the time spanned by the sample points the load current is constant, the trajectory of the DC link voltage is best approximated by a straight line, VDCUnk(t) = mt + b wherein m is the slope of the line. A curve-fitting algorithm is used to determine the coefficients, m and b, which describe the best straight line that can be drawn through the sampled data points. Applying such an algorithm minimizes the effects of noise appearing on the feedback signal or the DC link 16.
A common algorithm, the method of least squares, minimizes the sum of the squared error from the data points to the best fit curve. Applying this method to a linear curve fit yields the following two equations: bn + m ΣXj = ∑yj b ∑xj + m Ex/ = Σ XjYj,- where n is the number of sampled points, m is the slope of the line and the summations are taken from j = 1 to n. By taking n samples, uniformly separated in time by T0 seconds and starting at t = 0, the x coordinates become {0,T0 , 2T0 ... (n- 1)T0}. The corresponding y coordinates, or DC link voltages, are therefore {VDClmk(0), VDClιnk(T0), VDC
Figure imgf000012_0001
Solving this system of equations for the slope m, yields an expression which estimates the rate at which the voltage of the DC link is falling. As mentioned above, this slope (dV^ iuιk/dt) is directly proportional to the average current being drawn by the inverter 18, namely Iioad=CDcι-0k (dVDClink/dt) . If n is chosen to be an even number, this may be shown to have the form: lLo.d Ave=C,{VDC lmk((n-l)T0)- VDC Unk(0) } + c2{VDC tak((n-2)To)- VDclιnk(T0) } + C3{ VDChnk((n-3)T0)- VDC tok^T,,) } + ... + Cn/2{VDClulk(nT0/2)- VDclmk(nT0/2-
1)}, where C,...^ are constants. If n is chosen to be an odd number, the middle sample coefficient is zero and therefore does not contribute to the slope estimate. For a six sample approximator (n = 6) this reduces to:
Figure imgf000012_0002
VDClmk(0) } + C2{VDC , lmk(4T0)-
VncunkfTo)} + C3{ VDClmk(3T0)- VDChnk(2T0) }
Such an equation has the form of a simple finite impulse response (FIR) filter. Such a filter may be implemented in many ways, using either digital or analog circuitry. Samples are taken continuously, and as the time window spanned by the data samples passes through time, new samples are shifted in and the oldest samples are discarded in a first in, first out fashion. By continually updating the samples as time passes, the load estimator applies a "flying" curve fit to the points in the sample window and returns the slope of the best straight line which can be drawn between them. Fig. 2 is a block diagram of a six sample load estimator referenced generally at 30. The load estimator 30 comprises 12 sample and hold amplifiers, individually numbered 1-12. Each sample and hold amplifier is connected to a clock signal. In particular, odd-numbered amplifiers illustrated in Fig. 2 are connected to Clock 1 and even-numbered amplifiers are connected to Clock 2. Fig. 2 also illustrates respective timing diagrams for Clocks 1 and 2. Each amplifier also has an input signal and an output signal. As shown in Fig. 2, the input signal for sample and hold amplifier 1 is the voltage potential of the DC link 16. The output signal for amplifier 1 is connected to the input of amplifier 2. Similarly, the output signal of each successive amplifier is connected to the input of the following amplifier. The output of each even-numbered sample and hold amplifier (i.e., amplifiers 2, 4, 6 ...) is connected to a difference amplifier or summer junction, for example, summers 34, 36 and 38 shown in Fig. 2. The output of each summer 34, 36, 38 is respectively connected to a constant multiplier Cl, C2, C3 to provide a scaled output. The scaled outputs are then summed at a further summer 40 to provide an output 44. The output 44 is then provided as an initial condition to the converter 22 (see Fig. 1) .
The time that the voltage of the DC link 16 is actually allowed to fall may be a relatively short period of time, depending on the DC link capacitance and the load applied. For this reason, a digital implementation may not be as desirable as an analog one.
As described above, the load estimator equation consists of terms which are the difference between two samples multiplied by a constant gain. These terms are then summed together to form the output. Given analog representation of these time-delayed samples, such an equation can be easily implemented in hardware with difference amplifiers 34, 36, 38 and operational amplifier summer 40 as indicated in Fig. 2. In order to create the string of time- delayed samples to be used as the input to the equation, 2n sample and hold amplifiers (i.e., the 12 amplifiers in the six sample load estimator example of Fig. 2) may be cascaded in series. As shown in Fig. 2, this forms a "bucket brigade" of time-shifted analog voltages. A description of the operation of Fig. 2 in accordance with the method of the present invention follows.
During the time that the "sample" input is high, each sample and hold amplifier captures the potential present on its input and tracks this voltage on its output. When the "sample" input goes low, the voltage present on its output at that moment is frozen regardless of input changes. Again referring to the arrangement and timing diagrams of Fig. 2, suppose that at time = 0, Clock 1 and Clock 2 are both low. Also assume that some voltage, VA and Vc is present on points A and C, respectively. When Clock 1 goes high, point B changes to be equal to VA (via sample and hold number 3) , and point D changes to be equal to Vc (via sample and hold number 5) . Because Clock 2 is still low, points A and C remain unchanged. However, at time T,, Clock 1 goes low, and all voltages are now frozen until Clock 2 goes high at time T2. At this point, Vc is transferred to point E (via sample and hold number 6) , and point C transitions to VA (via sample and hold number 4) . At T3, Clock 2 again goes low, and all voltages are frozen. The end result of this cycle is that VA has been shifted from point A to point C, and Vc has been shifted from point C to point E. In the meantime, a new sample has been taken from the input signal and stored at point A. This cycle repeats every T0 seconds to form a string of time- delayed analog samples. The appropriate points in the string are then fed into the respective difference amplifier 34, 36, 38 as inputs as discussed above. This circuitry is very fast and demands no software overhead. It may also be implemented using relatively inexpensive and readily available analog components. As an example, Fig. 3 is a circuit diagram illustrating a preferred implementation of an electrical circuit of the six sample load estimator of Fig. 2. As shown in Fig. 2, the Clock 1 and Clock 2 inputs are provided, as well as inputs to each of the sample and hold amplifiers. The 12 sample and hold amplifiers of Fig. 2 are embodied as four amplifiers on each of three IC chips 50, 52, 54 in Fig. 3. The circuit of Fig. 3 operates similarly to Fig. 2.
Although the present invention has been described in substantial detail with reference to one or more specific embodiments, those of skill in the art will recognize that changes may be made thereto without departing from the scope and spirit of the invention as set forth in the appended claims.

Claims

1. A method of delivering an optimized power level output from a backup energy system to a load connected to a primary energy supply via a DC link and an inverter, the method comprising the steps of: sensing a voltage of the DC link connected to the load; connecting a converter between the backup energy supply and the DC link; evaluating a rate of change of the voltage of the DC link; determining an estimate of the average load current using the rate of change of the DC link voltage; and controlling the converter using the average load current to deliver an optimized power level output from the backup energy supply to the load.
2. The method of claim 1 further comprising the step of: setting an initial condition to control the converter so that when the converter switches on to deliver energy to the load, the initial condition sets pulse widths of switching elements in the converter.
3. The method of claim l further comprising the step of: allowing the voltage of the DC link to fall to a predetermined level before controlling the converter.
4. The method of claim 1 wherein the step of determining an estimate of the average load current using the rate of change of the
DC link voltage is performed in accordance with a formula 1^ = CDClink (dV^ /άt) .
5. The method of claim 1 wherein the step of evaluating a rate of change of the DC link voltage is performed by representing a plurality of DC link voltage samples taken over time as points in an x-y coordinate system and employing a curve-fitting algorithm to generate a best fit line such that the slope of the line represents the rate of change of the voltage of the DC link.
6. The method of claim 5 further comprising the step of: implementing the step of evaluating the rate of change of the DC link voltage using a first plurality of serially connected sample and hold amplifiers having a second plurality of difference amplifiers selectively connected to the first plurality of sample and hold amplifiers and an operational amplifier summer connected to sum outputs of the difference amplifiers to produce an output.
7. The method of claim 6 wherein the output of the operational amplifier summer is an estimate of the load.
8. The method of claim 6 wherein the output of the operational amplifier summer is an initial condition for controlling the converter.
9. The method of claim 1 further comprising the steps of: providing closed loop voltage control for the converter; using the estimate of the average load current as a feedback signal for the closed loop voltage control.
10. The method of claim 1 wherein the DC link comprises a capacitor bank.
11. A method of estimating an electrical load on an inverter system having a DC link, the method comprising the steps of: sensing a voltage of the DC link; evaluating a rate of change of the DC link voltage; and calculating an estimate of an average load current, using the rate of change of the DC link voltage.
12. The method of claim 11 further comprising the steps of: providing closed loop voltage control for the converter system; and using the estimate of the average load current as a feedback signal for the closed loop voltage control.
13. The method of claim 11 further comprising the step of providing a converter connected to the inverter system.
14. The method of claim 11 wherein the step of calculating an estimate of the average load current using the rate of change of the DC link voltage is performed in accordance with a formula Iω = CDClink (dVDclink/dt) .
15. The method of claim 11 wherein the DC link comprises a capacitor bank.
PCT/US1997/007666 1996-05-06 1997-05-05 System and method for estimating a load to optimize a backup energy system response WO1997043892A2 (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
US1694396P 1996-05-06 1996-05-06
US60/016,943 1996-05-06

Publications (2)

Publication Number Publication Date
WO1997043892A2 true WO1997043892A2 (en) 1997-11-27
WO1997043892A3 WO1997043892A3 (en) 1998-02-26

Family

ID=21779855

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/US1997/007666 WO1997043892A2 (en) 1996-05-06 1997-05-05 System and method for estimating a load to optimize a backup energy system response

Country Status (2)

Country Link
US (1) US5889659A (en)
WO (1) WO1997043892A2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
AT501542A1 (en) * 2004-12-16 2006-09-15 Fronius Int Gmbh METHOD FOR DETECTING THE LOAD OF AN ISLE CHANGE AND ISOLATOR INVERTER

Families Citing this family (22)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6175166B1 (en) * 1999-06-14 2001-01-16 Abb Power T&D Company Inc. System for mitigating voltage disturbances and interruptions for power distribution applications
US7164590B2 (en) * 2002-07-29 2007-01-16 International Rectifier Corporation Power transfer system with reduced component ratings
US7456513B2 (en) * 2002-11-15 2008-11-25 Sprint Communications Company L.P. Modular cell site with air-turbine backup
US20040125618A1 (en) * 2002-12-26 2004-07-01 Michael De Rooij Multiple energy-source power converter system
US7127895B2 (en) * 2003-02-05 2006-10-31 Active Power, Inc. Systems and methods for providing backup energy to a load
US20040178681A1 (en) * 2003-03-11 2004-09-16 Electronic Data Systems Corporation System for providing backup power to an electronic device
US7314059B2 (en) * 2004-09-17 2008-01-01 Active Power, Inc. Systems and methods for controlling pressure of fluids
US8333330B2 (en) * 2004-09-17 2012-12-18 Active Power, Inc. Systems and methods for controlling temperature and pressure of fluids
US20060059937A1 (en) * 2004-09-17 2006-03-23 Perkins David E Systems and methods for providing cooling in compressed air storage power supply systems
US20060059936A1 (en) * 2004-09-17 2006-03-23 Radke Robert E Systems and methods for providing cooling in compressed air storage power supply systems
US7918091B1 (en) 2006-09-20 2011-04-05 Active Power, Inc. Systems and methods for controlling humidity
US7710081B2 (en) 2006-10-27 2010-05-04 Direct Drive Systems, Inc. Electromechanical energy conversion systems
US7425807B1 (en) 2006-11-29 2008-09-16 Active Power, Inc. Transient energy systems and methods for use of the same
US7400052B1 (en) 2006-11-29 2008-07-15 Active Power, Inc. Transient energy systems and methods for use of the same
US7642664B1 (en) 2006-11-29 2010-01-05 Active Power, Inc. Transient energy systems and methods for use of the same
US7750518B1 (en) 2006-11-29 2010-07-06 Active Power, Inc. Transient energy systems and methods for use of the same
US20100019598A1 (en) * 2008-07-28 2010-01-28 Direct Drive Systems, Inc. Rotor for an electric machine
US8228191B2 (en) * 2009-03-30 2012-07-24 Magnasphere Corp. Anti-tamper assembly for surface mounted security switch
US9899831B2 (en) 2010-10-06 2018-02-20 General Electric Technology Gmbh Method and device to protect an ESP power supply from transient over-voltages on the power grid
US10734821B2 (en) 2018-03-08 2020-08-04 Saudi Arabian Oil Company Power control system
CN109450082A (en) * 2018-11-20 2019-03-08 四川省辛普森动力设备有限公司 A kind of dynamic UPS and control method
CN112798845A (en) * 2020-12-29 2021-05-14 联合汽车电子有限公司 Automated sampling method and system

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5315533A (en) * 1991-05-17 1994-05-24 Best Power Technology, Inc. Back-up uninterruptible power system
US5602462A (en) * 1995-02-21 1997-02-11 Best Power Technology, Incorporated Uninterruptible power system

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS62107647A (en) * 1985-10-31 1987-05-19 三菱電機株式会社 Flywheel source apparatus
US4719550A (en) * 1986-09-11 1988-01-12 Liebert Corporation Uninterruptible power supply with energy conversion and enhancement
US4709318A (en) * 1986-10-22 1987-11-24 Liebert Corporation UPS apparatus with control protocols
ES2066249T3 (en) * 1990-05-08 1995-03-01 Asea Brown Boveri TWO QUADRANT CURRENT RECTIFIER AND ITS USE AS A CONTROL ELEMENT OF AN ENERGY ACCUMULATOR.

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5315533A (en) * 1991-05-17 1994-05-24 Best Power Technology, Inc. Back-up uninterruptible power system
US5602462A (en) * 1995-02-21 1997-02-11 Best Power Technology, Incorporated Uninterruptible power system

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
AT501542A1 (en) * 2004-12-16 2006-09-15 Fronius Int Gmbh METHOD FOR DETECTING THE LOAD OF AN ISLE CHANGE AND ISOLATOR INVERTER
AT501542B1 (en) * 2004-12-16 2009-03-15 Fronius Int Gmbh METHOD FOR DETECTING THE LOAD OF AN ISLE CHANGE AND ISOLATOR INVERTER
US7577005B2 (en) 2004-12-16 2009-08-18 Fronius International Gmbh Method for recognizing the load of an island inverter and island inverter

Also Published As

Publication number Publication date
US5889659A (en) 1999-03-30
WO1997043892A3 (en) 1998-02-26

Similar Documents

Publication Publication Date Title
US5889659A (en) System for estimating a load to optimize a backup energy system response
EP2220745B1 (en) Systems for and methods of controlling operation of a ups
US6930474B2 (en) Current sense apparatus and method using a combination of a simulation and a real sense for a switching mode power converter
CN100575964C (en) Be used to measure the instrument of electric power
CN103378734B (en) Semiconductor device, power-supply device and the method for controlling power-supply device
CN107525526B (en) Device and method for providing a measurement of the uncertainty of a transfer function
US5808443A (en) Battery charging method
US8330295B2 (en) Uninterruptible power supply and method for selective tripping thereof
Amanci et al. Synchronization system with zero-crossing peak detection algorithm for power system applications
EP0104999B1 (en) Gain switching device with reduced error for watt meter
US20110063881A1 (en) System and method for automatically tuning a voltage converter
Kim et al. A time-domain procedure for locating switched capacitors in power distribution systems
US4371943A (en) External means for detecting normal zones in superconducting magnets or coils
EP2487476B1 (en) Circuits for accurately measuring temperature of semiconductor junctions
EP0573088B1 (en) Method and a circuit for controlling an inverter to switch in the sliding mode and by PWM with a three-level output voltage
CN115441710B (en) Inverter isolated-grid split-phase output voltage direct-current component suppression method and photovoltaic system
US20210240944A1 (en) Multiply-accumulate device and multiply-accumulate method
JP3460511B2 (en) IC circuit with pulse generation function and LSI test apparatus using the same
US20130285719A1 (en) Power system data acquisition systems
JP4946642B2 (en) Harmonic current compensator
JPS6218095B2 (en)
JPH1114674A (en) Method for measuring higher harmonics of power system
Cirrincione et al. Estimation of the electrical parameters of an induction motor with the TLS EXIN neuron
JP2005055385A (en) Multi-circuit watt-hour meter
JPH08223803A (en) Method and device for controlling active filter

Legal Events

Date Code Title Description
AK Designated states

Kind code of ref document: A2

Designated state(s): JP

AL Designated countries for regional patents

Kind code of ref document: A2

Designated state(s): AT BE CH DE DK ES FI FR GB GR IE IT LU MC NL PT SE

AK Designated states

Kind code of ref document: A3

Designated state(s): JP

AL Designated countries for regional patents

Kind code of ref document: A3

Designated state(s): AT BE CH DE DK ES FI FR GB GR IE IT LU MC NL PT SE

DFPE Request for preliminary examination filed prior to expiration of 19th month from priority date (pct application filed before 20040101)
121 Ep: the epo has been informed by wipo that ep was designated in this application
NENP Non-entry into the national phase

Ref country code: JP

Ref document number: 97542426

Format of ref document f/p: F

122 Ep: pct application non-entry in european phase