WO2001026005A1 - Method for determining total cost of ownership - Google Patents

Method for determining total cost of ownership Download PDF

Info

Publication number
WO2001026005A1
WO2001026005A1 PCT/US2000/027518 US0027518W WO0126005A1 WO 2001026005 A1 WO2001026005 A1 WO 2001026005A1 US 0027518 W US0027518 W US 0027518W WO 0126005 A1 WO0126005 A1 WO 0126005A1
Authority
WO
WIPO (PCT)
Prior art keywords
costs
measure
cost
management
metrics
Prior art date
Application number
PCT/US2000/027518
Other languages
French (fr)
Inventor
Stephen Nunn
Joaquin Feria
Original Assignee
Accenture Llp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Accenture Llp filed Critical Accenture Llp
Priority to AU78618/00A priority Critical patent/AU7861800A/en
Publication of WO2001026005A1 publication Critical patent/WO2001026005A1/en

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/80Management or planning

Definitions

  • This invention generally relates to methods for calculating costs attributed to the use of computing equipment and services.
  • this invention relates to the costs of providing and maintaining computing services and methods to analyze those costs.
  • TCO Total Cost of Ownership
  • the invention includes a method for determining the cost per user of an information technology system.
  • the method includes obtaining base costs, ongoing direct costs, and ongoing indirect costs.
  • the method further includes gathering information relating to user profiles and organizational characte ⁇ stics. These costs and information are input mto a computer program to determine the cost for each user.
  • the invention includes a method for analyzing the costs associated with supporting an information technology system.
  • the method includes obtaining cost information and system characte ⁇ stics.
  • Appraisal metncs are calculated based on the cost information and system characte ⁇ stics.
  • the metncs may be compared against established benchmarks.
  • This invention defines both metncs used to measure the costs associated with distributed computing when performing a TCO analysis, as well as metncs used to evaluate the operations effectiveness and efficiency Where possible, the metncs are referenced to IT organizational functions in order to define precisely potential added value.
  • One application of this invention is to provide a TCO framework aligned as far as possible with the Management of Distnaded Environments (MODE) framework (an IT organizational framework commercially available from MODE).
  • MODE Distnaded Environments
  • Another useful aspect of this invention is a set of metrics that give a holistic view of the TCO. These metncs enable comparative studies and benchmarking, as well as assessing the impact of possible changes and determining improvement opportunities through MODE's best practices implementation.
  • FIG 1 shows a representation of one embodiment of the method of the present invention DETAILED DESCRIPTION OF THE INVENTION
  • the TCO analysis becomes part of any Information Systems (IS) organization's continuous process of measurement, improvement and resource planning; it enables the simulation of improvement plans for asset changes, best practice implementation and complexity reductions
  • IS Information Systems
  • the initial step is to categonze the costs according to the MODE framework, or any other IT organizational framework implemented m an enterpnse's IT systems.
  • this mvention is descnbed m terms of the MODE framework
  • the costs may be categorized according to the IT framework which is described in co-pending application No , entitled Organization of Information Technology Functions, by Dove et al . which was filed October 6, 2000, which is herein incorporated by reference.
  • the costs have to be "standardized," l e., put under a format that allows one to compare the data elements with others and do benchmarking to depict typical values for each data element and metric
  • appraisal metrics will tally key staffing ratios, activity person hours, help desk performance metrics, and end user satisfaction metrics to provide the client with a complete perspective of its actual position and potential evolution
  • Benchmarks are considered to carry out a consistent evaluation of an enterprise's position that also give insight to improvement initiatives Actual and typical values for all the metrics and data elements, with all the relevant assumptions required to understand those values, are developed by experience in evaluating IT systems. The benchmarks are useful for an Opportunity/problem analysis.
  • BASE COSTS and ONGOING COSTS have been considered and have been adopted to categonze both one off investment and costs incurred through ongoing operations. Only the ONGOING COSTS will be aligned to the MODE framework, since MODE'S added value pnncipally lies m the potential changes that have to be made.
  • the BASE COSTS measure the one off costs of implementing the base
  • the ONGOING COSTS measures the total amount of expense since the IT Infrastructure has been running.
  • the costs are catego ⁇ zed as direct and indirect costs.
  • the direct costs are the day-to-day operational costs such as maintenance, support, momtonng etc.
  • the indirect costs pertain to the unbudgeted costs that are caused either by downtime or end-user inefficiency at work
  • the Direct Costs that refers to the Ongoing expenses of running IT operations, are hard factual costs, whereas the Indirect costs are often related as "soft" costs, because they are more subjective (i.e., it is difficult to measure them in a consistent way).
  • TCO Dnvers like Enterpnse profile (industry or business type, world-wide geographic location, enterpnse size, end users type), Technology volume and type (servers, Client computers-mobiles + desktops- pe ⁇ pherals, network), Management Practices (Technology, Process, People), Complexity (IS organization, IS processes and service, end-user organization, hardware and software) are "tuning" the average typical values collected in benchmarking databases. These factors must be related as assumptions when compa ⁇ ng data in order not to come to wrong conclusions.
  • Cost metncs can be denved straight forwardly from the costs elements, when associating the costs to another quantities (number of employees, number of desktops, etc.), which allows one to compare the TCO of vanous companies without having to make conversions.
  • Metncs are also helpful to provide the decision makers with a holistic view of the TCO. There are not only quantitative metncs, but also qualitative metncs, that examine the global performance of a company, and tend to determine its profile. Several appraisal metncs are defined that are categonzed according to three different areas:
  • IEP-Th ⁇ s area looks at the system's future and scalability.
  • the appropnate MODE function For each metric developed, the appropnate MODE function is allocated. category referenced, the parameters descnbed, how to compute it (construction and formula) and possibly its benchmark. Then the different relations that exist between all the appraisal metncs are detailed in order to make their interpretation easier and thus allowing to perform a better opportunity study.
  • the TCO metncs are aimed at not only reporting the costs of a distnaded environment, but also give a holistic view of its components.
  • the first step is to measure the costs, and then to see where they stem from, identify the factors of influence for each cost areas, the correlation between the metncs. and try to assess the impacts of change (management, technology) withm the IT organization The completion of this step will allow for assessment of opportunities agamst different plausible ⁇ os.
  • One embodiment of the method of the present mvention is represented m Figure 1.
  • a senes of cost data about a particular aspect of an information technology system is gathered.
  • the cost data includes base costs (10), ongoing direct costs (12), and ongomg indirect costs (14), which are input into a cost data array (16).
  • Infrstructure and evolution charactenstics (22) are obtained and input mto an IEP metncs array (28)
  • Specific cost information from the cost data array (16) is input mto the FP metncs array (24) and used for calculating certain FP metrics
  • the data is used to calculate cost information which is used to generate a summary report (30) of the total cost of ownership.
  • the cost data and the metrics are used to generate functional category detail reports and benchmark analyses (32). These reports and analyses break down the cost information and appraisal metncs according to the IT organizational functional categones to which that information corresponds.
  • the cost detail and appraisal metncs are broken out and provided in separate reports relating to service management (34), systems management (36), service planning (38), and managing of change (40)
  • the definitions and formulas used to calculate these cost data and metncs are provided in the detailed desc ⁇ ption which follows.
  • the formulas can be programmed on a computer, such as in a spreadsheet (e g., Excel), to calculate the costs and metncs and display or pnntout reports
  • the cost categories are to be as precise and detailed as possible so that benchmarks from external data providers can be referenced
  • the costs are preferably evaluated on an annual basis, for the BASE costs as well as the ONGOING costs. Each time when necessary the life-cycle and depreciation of capital expenditures will have to be detailed and the global labor costs for a given time pe ⁇ od annuahzed.
  • Base costs include 1) Design; 2) Acquisition Costs; and 3) Installation Costs.
  • Ongoing costs include 1) Direct Costs; 2) Systems management - aligned to MODE'S System's Management
  • the base costs are descnbed m detail below
  • the base costs are identified by "Cost Data" designations CD1 through CD 15 , which are depicted in Fig 1
  • Capital and Expense costs are distinguished, as they are most of the time accounted for separately in the chart of accounts of a company. There are only labor Expenses in the Design and Installation Costs section, whereas the
  • CD1 costs relates to systems research and planning CD1 costs include the labor expenses for identifying infrastructure needs, operations architecture service quality, setting standards, defining organization and support requirements, considenng configuration options, assessing scalability, predict TCO hfecycle, and plan rollout, (MODE functions: service planning).
  • CD2 costs relate to vendor management.
  • CD2 costs include the labor costs and other expenses (e.g., travel, etc.) for working with service vendors. IS labor time spent on meetings, workshops, writing RFPs, reviewing proposals and dealing with vendor issues. Another issue here is to include the Service Level Agreements (SLAs) and Operating Level Agreements (OLAs) Acquisition costs
  • SLAs Service Level Agreements
  • OLAs Operating Level Agreements
  • This cost category refers to the hardware and software purchases. In order to compare these costs to industry averages, these costs are typically Capital Costs which are annuahzed, and we also have to consider the hardware value depreciation according to the life-time of the each component Different
  • CD3 relates to end-stations acquisition CD3 costs include the capital expenditures associated with the purchase of a computer (client, sen. er, net- computer, dumb-terminal, laptop, etc.) This includes. the basic configuration: CPU, monitor, mouse, keyboard, mothercard, memory, with possible bundles. the penpherals- video/sound cards, floppy and CD-ROM drives the possible memory and storage upgrades (RAM+ROM) and devices for databases the network and communication devices modem, network cards "CD4" costs relate to network hardware CD4 costs include the capital expenditures for the network communication devices (hubs, b ⁇ dges. routers, switches), cablmg-dependmg on the transmission medium, optic fiber, coax etc.
  • CD5 costs relate to operations and multimedia devices CD5 costs include the capital expenditures associated with pnnters, scanners, and all the other multimedia devices (digital cameras, microphones, etc )
  • CD6 costs relate to operating system CDT costs include the capital expenditures on operating system licenses This cost is separated from the end- station acquisition cost, even if sometimes the operating system is already installed and there is a bundle p ⁇ ce.
  • CD7 costs relate to application software.
  • CD7 costs include the capital expenditures for business and productivity software. This includes packages such as MS Office, financial and accounting software such as SAP, and all the software related to programming languages that help to build new applications (compilers, test tools, etc.).
  • CD8 costs relate to groupware and communication software.
  • CD8 costs include the capital expenditures on software used to connect users and enable sharing of information across the network. This includes: e-mail and other messaging software, Groupware (Lotus Notes, etc.%) and remote connectivity software.
  • CD9 costs relate to systems management software CD9 costs include the capital expenditures on secunty (virus protection and elimination), performance momto ⁇ ng, production control (file transfer, backup and restore, storage) and failure control (fault detection and recovery) software.
  • Enterpnse Management software is included in this category, and can offer bundles for the previous systems management features.
  • CD 10 costs relate to utility software.
  • CD 10 costs include the capital expenditures for both multimedia software (videoconferencing tools), and end user utilities (screen savers, disk managers, PhotoShop, etc.) which are not productivity enhancing.
  • Other entertainment software audio and video tools are included here
  • CD 11 costs relate to hardware set-up CD11 costs include after labor expenses (internal + external) associated with the deployment of the network and system infrastructure: i.e., put the network devices and the workstations m place, pull down the cables and connect all the workstations to each other. There is also costs to setup the router according to the network topology and all the other network connectivity devices, depending on the protocols used.
  • CD 12 costs relate to operating system installation.
  • CD 12 costs include the labor costs (internal + external) associated with the installation of any operating system (UNIX, Windows NT/95, etc.).
  • CD 13 costs relate to application software.
  • CD 13 costs include the labor costs (internal + external) associated with the installation of all the applications related in the previous section.
  • CD 14 costs relate to groupware and communication software CD 14 costs include the labor costs (internal + external) associated with the installation and configuration of all the messaging software and the databases.
  • CD 15 costs relate to systems management software.
  • CD 15 costs include the labor costs associated (internal + external) with the installation of the network and systems management platform and the anti-virus systems.
  • the ongoing costs are divided into two categones: the direct costs (CD 16-
  • CD39 CD39
  • indirect costs CD40-CD44
  • the direct costs are the budgeted costs to maintain and optimize the availability of key network resources, manage the system and implement the changes, and support the network users.
  • the indirect costs are expenses that are not budgeted and often not accounted for in most of the IT organizations. These hidden costs make the true costs of IS systems underestimated, because the impact of downtime - which is a crucial factor increasing the overall costs - is too often not measured.
  • the catego ⁇ es tend to match the MODE framework.
  • CD 16 costs relate to application management.
  • CD 17 costs relate to storage management.
  • the annual labor expenses internal + external
  • disk and file management optically readable media
  • data access management providing user availability to information: database management, server file access and remote servers access
  • backup and archiving and repository management may include development costs.
  • CD 18 costs relate to traffic management.
  • CD 19 costs relate to event management. The annual labor expenses to log, classify and present event messages on consoles with pre-established filters or thresholds. In case of a fault, the message should be forwarded to those who can correct the fault and do a diagnosis.
  • CD20 costs relate to performance management. The annual labor expenses for interpreting, planning and balancing the performance of servers, networked systems and applications.
  • CD21 costs relate to physical site management.
  • the task operated is a kind of overall maintenance labor.
  • CD22 costs relate to secunty and virus protection The annual labor costs and other expenses (development costs) for preventing from secunty violations; password management, access restnction, virus infection and recovering from such violations or intrusions should they occur
  • Detection is tallied in the momto ⁇ ng section.
  • CD23 costs relate to LAN/WAN troubleshooting and repair.
  • CD24 costs relate to disaster planning and recovery The annual labor expenses for restonng data, building disaster recovery and management plans including backup and restore procedures, record keeping and disaster recovery team organization.
  • CD25 costs relate to hardware maintenance fees.
  • the annual maintenance contracts fees Generally agreed upon in SLAs, these contracts are earned out, monitored and recorded for each asset Changes And Upgrades
  • This cost area refers as well to the ongoing upgrades to the system as to the deeper changes that affect the whole system.
  • CD26 costs relate to change planning. The annual costs associated with management of change planning. These costs are labor costs associated with the development of change control strategies and migration control (move from the development environment to the test and finally the production environment), and outsourced management fees such as strategic and tactical consulting.
  • CD27 costs relate to asset management.
  • Asset management is mventoned here because it is necessary to know what exists before implementing a change.
  • CD28 Cost and labor costs relate to product evaluation and testing The annual labor expenses for evaluation and testing of new technology mate ⁇ als (hardware, software) pnor to purchase. Here are also accounted for the "vendor management” ongoing labor costs (see DESIGN section)
  • CD29 costs relate to products procurement and implementation.
  • the annual expenses for the purchase of new hardware and software, and the labor costs associated with their initial installation and configuration Included here are the labor costs associated with software licensing and distnbution, i.e . metenng the number of available licenses and monitonng their usage (operating systems, applications, and connectivity software)
  • CD30 costs relate to user administration (adds, moves and changes to users).
  • the support costs are the direct labor expenses and fees associated with supporting the network's users.
  • CD31 costs relate to help desk (Tier I support).
  • the Tier I refers to the time spent by phone staff to answer calls and support End-Users without any intervention.
  • Support Services performed at Tier II and III, that implies advanced troubleshooting and failure recovery are recorded in Systems Management.
  • CD32 costs relate to request and problem management and planning.
  • CD33 costs relate to casual learning. The annual labor expenses of IS professional's time spent on independent, self-education and learning outside of formal training programs. Topics include self-education on computers, networks, printers, storage systems, network communication devices, as well as IS utilities and end-user applications
  • CD34 costs relate to training The annual labor expenses and fees for develop, deliver training courses and train as well end users as IS personnel. This includes
  • CD35 The labor expenses for the delivery by trainers of end-user training courses, and the time spent by end-users on computer systems and all application training (incl. the initial framing just after rollout) "CD35" costs relate to operating costs.
  • the travel expenses include as well the travel time to support remote branch offices, attend training sessions, visit vendors as the travel expenditures.
  • CD36 costs are related to communications fees The annual expenses for communication fees such as lease line fees, on-line access-fees, remote access services, WEBTSP hosting fees, and allocated WAN fees.
  • CD37 costs relate to leased asset fees.
  • the annual fees for leased assets including, e.g., servers, printers, hubs, bndges, routers, switches, or client software.
  • CD38 costs relate to IS commodity expenditures.
  • the annuahzed capital fees for computer supplies such as floppy disks, CD-ROM disks, backup tapes, toner cartridges and other expendables
  • CD39 costs relate to insurance.
  • the annual fees for insurance agamst theft, voltage shortage (implying data loss), etc.
  • the indirect costs are those that are not ongmally budgeted because they stem from a productivity loss due either to the end user themselves or to unplanned systems downtime. The majonty of these metrics are sometimes difficult to measure. These costs are identified as CD40-CD44, as shown in FIG.
  • CD40 costs relate to casual learning.
  • CD41 costs relate to peer and self support.
  • These tasks-repair, support, maintenance. installation, framing- are performed extensively by end-users in remote offices not staffed by dedicated IS personnel or covered by support contracts.
  • CD42 costs relate to Futz factor.
  • the annual labor expenses associated with the development and customization of non-busmess applications (Notes scnpts, etc.), the unnecessary changes to their computer or network settings (screen, file organization, folder, sounds, pnnters, etc ), and the time spent on playing games or web surfing
  • Downtime expenses are defined as a potential annual loss due to the unavailability of the IT Infrastructure due to faults, and its impact as measured as loss of productivity.
  • Downtime can be either due to the waiting for a help desk problem to be resolved, to an infrastructure issue (planned maintenance), or unplanned failures (application bugs or inaccessibility, network outages, etc.), for example.
  • CD43 costs relate to planned downtime.
  • CD44 costs relate to unplanned downtime.
  • the unplanned network outages are almost always obtained from end user surveys.
  • the appraisal metncs are intended to be key performance indicators for IT operations as a measurement and assessment tool for the TCO, to evaluate and monitor its effectiveness. Different areas, divided mto sections, have been distinguished to facilitate the comprehension and the use of all the metncs along the analysis. The comparison with available market data should allow then to elaborate best practices.
  • the parameters involved are preferably must be homogeneous, i.e., each parameter has to be measured within the same time penod. The time period is taken to be equal to one year.
  • the metrics are categonzed as follows:
  • metncs are constructed according to the same template.
  • This template defines the name of the metnc and gives it a number, provides the MODE functions that are involved, indicates the parameters that are involved, how to compute them, the objective of each metnc and additional comments.
  • TCO by the budgeted TCO for the last financial year.
  • the actual cost should not go over the budgeted cost, and should not be more than 5% less than the budgeted cost (otherwise the budget would be badly managed).
  • This metnc is actually an aggregation of several metrics, each being a ratio between different areas of the ongoing costs.
  • the areas considered are support, systems management, change and upgrades, and indirect costs.
  • Direct Costs (measure 1) - the sum of all costs related ⁇ (CD16+...+CD39)...$.
  • Indirect Costs (measure 2) - the sum of all costs related ⁇ (CD40+ ... +CD44) ... $ .
  • this metric is an aggregation of two metrics that intend to define the importance of the labor costs for the TCO as well as outsourcing trends.
  • This ratio can be used to compare similar industry companies to determine industry trends in the way that some IT operations are outsourced Sources such as Gartner Group provide information about outsourcmg trends that can be used for benchmarking
  • the metncs in this area measure the performance of the business, focusing on system and operations quality, availability, and efficiency Quality
  • OEEI-A Number of Faults per User
  • This metric e ⁇ understandes the global systems performance required by company business needs.
  • the systems overall performance will be rated from 1 to 5, according to both technology efficiency (bandwidth available, file transfer speed, storage capacity) and fault tolerance and recovery (e.g., banks are very sensitive to downtime); basic technology and great fault tolerance; medium technology and great fault tolerance; medium technology and little fault tolerance; high technology and little fault tolerance; high technology and no fault tolerance.
  • OEE1-C Physical and Logical Security Rating
  • This metric evaluates the performance of the system in terms of security. The rating, going from 1 to 5, allows to indicate how important security is to the company, and then to assess the budget that could be spent on this area. For a given rate and according to the industry sector, benchmarks concerning budgets allocated to security may be available; system not secured; system poorly secured; system globally secured; system well secured; and system highly secured.
  • This metric measures both the call reloggmg rate and abandonment rate at the Help Desk.
  • the average response time metnc determines the average time it takes the support organization to respond to an incident or problem. Normally, response time is defined as the time from the support organization first being aware of the incident or problem to the time at which the first action is taken (usually informing or giving status to users) It may be divided into further metncs based on the cnticality of the requests (low, medium, high, c ⁇ tical).
  • the average resolution time is the measure of the time from an incident or request being reported to the time at which it is resolved.
  • an incident is an occurrence-system error or malfunction-that requires assistance from the support organization, whereas a request refers to an action that a user asks to be performed that is usually related to network/workstation administration or software/hardware changes.
  • metnc can be considered according to the defined cnticality of the incident or request.
  • Metric objective and additional comments This metric measures the average time to deliver desktop services, from the order to the end of the installation, including the delivery and configuration. It allows to determine the flexibility of the system and its ability to administrate the users
  • This metnc measures both the rate of ongoing systems operations covered by SLAs as the actual performance of these operations agamst the SLAs
  • This area looks at the scalability of the infrastructure and at how sustainable the performances are likely to be m the future.
  • This measure rates the upgradeabihty of the system's technology from 1 to 5. depending on the different technologic features of the system, gives the number of different platforms operated and the system ' s like span to assess the system ' s flexibility.
  • the objective could be to determine if the WAN bandwidth utilization is withm a certain range and if it is not. the extent and frequency with which it is out of range This also allows to see the supportable traffic increase on the network
  • IEP2-B End-user Staff Growth or Attrition
  • Support Costs per FTE since the Support Costs are labor costs that are at least partly performed by employees of the company
  • One metric can be similarly influenced by another metnc, i.e.. its value is partly determined by another metric' s value.
  • Two metncs can have a complementary relationship, i.e., their vanations should be correlated.
  • Two metncs can have a trade-off relationship, i.e., if the value of one metnc increases, the value of the other should tend to decrease.
  • metncs For each metnc, the related metncs as well as the nature of their relationships is provided in the Tables below. All the metncs except those related to Infrastructure and Evolution Perspective, i.e., metncs IEP2-B, C and D, have relationships with other metncs, and often there are cross-categories relationships.
  • OEE3-C Help Desk call handling rate Is influenced by OEEl-A
  • the value for the appraisal metrics is in companng them in time v. ith previous calculated metncs for a system, or in comparing them with predetermined benchmarks. For some metrics there are no given benchmarks, but rather expected value ranges, which allows to include values for different industry types in the same table. Of course, other benchmark values may be used for specific industries, and for specific experiences with certain IT organization configurations. In Table 33 below, some exemplary benchmarks are provided.

Abstract

A method for determining the total cost incurred per user of information technology (IT) in a distributed computing environment includes obtaining base costs (10) and ongoing costs (12, 14) of an IT system and applying those costs to a series of metrics (24, 26, 28). The metrics (24, 26, 28) are compared against benchmarks (32) to evaluate and assess where cost efficiencies can be achieved.

Description

METHOD FOR DETERMINING TOTAL COST OF OWNERSHIP
BACKGROUND
This invention generally relates to methods for calculating costs attributed to the use of computing equipment and services. In particular, this invention relates to the costs of providing and maintaining computing services and methods to analyze those costs.
The Total Cost of Ownership (TCO) is defined as the total, per-seat cost incurred across a technology organization through the provision of continuing computing services to its users. It has now become an important metric for Information Technology (IT) to its users and for the IT industry. Organizations can evaluate their TCO either by considering their overall budgets through a top- down or bottom up approach.
As many organizations are under pressure to reduce costs, including of course the TCO for Corporate Systems, vendors and industry observers have predicted various levels of cost savings associated with both technology (e.g., migration from client-server environments to net-centric environments) and process improvements. Unfortunately most of the time their cost-savings claims do not provide the necessary context for decision makers to evaluate them, because the source of savings are not fully specified and the costs associated with the migration from one environment to another are not considered. Therefore, there is a need for an improved method for determining the TCO that provides a detailed analysis for decision makers.
SUMMARY OF THE INVENTION
In one embodiment, the invention includes a method for determining the cost per user of an information technology system. The method includes obtaining base costs, ongoing direct costs, and ongoing indirect costs. The method further includes gathering information relating to user profiles and organizational characteπstics. These costs and information are input mto a computer program to determine the cost for each user.
In a second embodiment, the invention includes a method for analyzing the costs associated with supporting an information technology system. The method includes obtaining cost information and system characteπstics. Appraisal metncs are calculated based on the cost information and system characteπstics. The metncs may be compared against established benchmarks.
This invention defines both metncs used to measure the costs associated with distributed computing when performing a TCO analysis, as well as metncs used to evaluate the operations effectiveness and efficiency Where possible, the metncs are referenced to IT organizational functions in order to define precisely potential added value.
One application of this invention is to provide a TCO framework aligned as far as possible with the Management of Distnbuted Environments (MODE) framework (an IT organizational framework commercially available from
Anderson Consulting, L.L.P., Chicago, Illinois, USA), so that the factors that contπbute to the TCO can be clearly identified and that the "Gap Analysis" could be done according to the MODE functions, which would allow to better assess
MODE'S added value. Of course, this invention is not limited to being earned out with a MODE framework, but can be applied withm other IT organizational frameworks.
Another useful aspect of this invention is a set of metrics that give a holistic view of the TCO. These metncs enable comparative studies and benchmarking, as well as assessing the impact of possible changes and determining improvement opportunities through MODE's best practices implementation.
BRIEF DESCRIPTION OF SEVERAL VIEWS OF THE DRAWINGS
FIG 1 shows a representation of one embodiment of the method of the present invention DETAILED DESCRIPTION OF THE INVENTION
The TCO analysis becomes part of any Information Systems (IS) organization's continuous process of measurement, improvement and resource planning; it enables the simulation of improvement plans for asset changes, best practice implementation and complexity reductions
In order to perform the TCO analysis, a methodology is used that requires both a financial chart of account and appraisal metncs relative to the distnbuted environment.
The initial step is to categonze the costs according to the MODE framework, or any other IT organizational framework implemented m an enterpnse's IT systems. For illustration purposes, this mvention is descnbed m terms of the MODE framework However, the costs may be categorized according to the IT framework which is described in co-pending application No , entitled Organization of Information Technology Functions, by Dove et al . which was filed October 6, 2000, which is herein incorporated by reference. Once the costs have been categonzed, they have to be "standardized," l e., put under a format that allows one to compare the data elements with others and do benchmarking to depict typical values for each data element and metric
It is desirable to factor in key organizational and reference assumptions (e g - company size, number of computers, etc.) when considering benchmarks, and try to point out all the factors of influence that impact the costs Beyond asset and activity based costing, appraisal metrics will tally key staffing ratios, activity person hours, help desk performance metrics, and end user satisfaction metrics to provide the client with a complete perspective of its actual position and potential evolution
Benchmarks are considered to carry out a consistent evaluation of an enterprise's position that also give insight to improvement initiatives Actual and typical values for all the metrics and data elements, with all the relevant assumptions required to understand those values, are developed by experience in evaluating IT systems. The benchmarks are useful for an Opportunity/problem analysis.
Costs Categorization and Metrics Definition
In order to take into account the total costs associated with major investments and changes, BASE COSTS and ONGOING COSTS have been considered and have been adopted to categonze both one off investment and costs incurred through ongoing operations. Only the ONGOING COSTS will be aligned to the MODE framework, since MODE'S added value pnncipally lies m the potential changes that have to be made. The BASE COSTS measure the one off costs of implementing the base
System and Network Infrastructure. These costs consist of the planning costs (labor expenses), the acquisition costs (hardware and software purchase), which are typically Capital costs, and the installation costs (labor expenses).
The ONGOING COSTS measures the total amount of expense since the IT Infrastructure has been running. The costs are categoπzed as direct and indirect costs. The direct costs are the day-to-day operational costs such as maintenance, support, momtonng etc., whereas the indirect costs pertain to the unbudgeted costs that are caused either by downtime or end-user inefficiency at work The Direct Costs, that refers to the Ongoing expenses of running IT operations, are hard factual costs, whereas the Indirect costs are often related as "soft" costs, because they are more subjective (i.e., it is difficult to measure them in a consistent way).
Obviously there are many factors that influence the costs related m the previous categones. Those TCO Dnvers, like Enterpnse profile (industry or business type, world-wide geographic location, enterpnse size, end users type), Technology volume and type (servers, Client computers-mobiles + desktops- peπpherals, network), Management Practices (Technology, Process, People), Complexity (IS organization, IS processes and service, end-user organization, hardware and software) are "tuning" the average typical values collected in benchmarking databases. These factors must be related as assumptions when compaπng data in order not to come to wrong conclusions.
To avoid confusion and compare data more easily, often various parameters are gathered to compute a metπc. Cost metncs can be denved straight forwardly from the costs elements, when associating the costs to another quantities (number of employees, number of desktops, etc.), which allows one to compare the TCO of vanous companies without having to make conversions.
Metncs are also helpful to provide the decision makers with a holistic view of the TCO. There are not only quantitative metncs, but also qualitative metncs, that examine the global performance of a company, and tend to determine its profile. Several appraisal metncs are defined that are categonzed according to three different areas:
• Financial perspective (FP)-Thιs area looks at the organization in terms of its financial performance. • Ability to operate effectively and efficiently the IT Operations and Systems
Infrastructure (OEE)-Thιs area examines the system's performances.
• Infrastructure and evolution perspective (IEP)-Thιs area looks at the system's future and scalability.
For each metric developed, the appropnate MODE function is allocated. category referenced, the parameters descnbed, how to compute it (construction and formula) and possibly its benchmark. Then the different relations that exist between all the appraisal metncs are detailed in order to make their interpretation easier and thus allowing to perform a better opportunity study.
The TCO metncs are aimed at not only reporting the costs of a distnbuted environment, but also give a holistic view of its components. The first step is to measure the costs, and then to see where they stem from, identify the factors of influence for each cost areas, the correlation between the metncs. and try to assess the impacts of change (management, technology) withm the IT organization The completion of this step will allow for assessment of opportunities agamst different scenaπos. One embodiment of the method of the present mvention is represented m Figure 1. In this embodiment, a senes of cost data about a particular aspect of an information technology system is gathered. The cost data includes base costs (10), ongoing direct costs (12), and ongomg indirect costs (14), which are input into a cost data array (16). In addition, a senes of user profile and IT organization characteπstics are obtained. This information and characteπstics are used for calculating a senes of metncs. Financial charactenstics (18) are obtained and input mto the FP metncs array (24). Operating and efficiency charactenstics (20) are input into an OEE metncs array (26). Infrstructure and evolution charactenstics (22) are obtained and input mto an IEP metncs array (28) Specific cost information from the cost data array (16) is input mto the FP metncs array (24) and used for calculating certain FP metrics From the cost data array (16), the data is used to calculate cost information which is used to generate a summary report (30) of the total cost of ownership. The cost data and the metrics are used to generate functional category detail reports and benchmark analyses (32). These reports and analyses break down the cost information and appraisal metncs according to the IT organizational functional categones to which that information corresponds. For example, under a MODE functional organization, the cost detail and appraisal metncs are broken out and provided in separate reports relating to service management (34), systems management (36), service planning (38), and managing of change (40) The definitions and formulas used to calculate these cost data and metncs are provided in the detailed descπption which follows. The formulas can be programmed on a computer, such as in a spreadsheet (e g., Excel), to calculate the costs and metncs and display or pnntout reports
Cost Categories
The cost categories are to be as precise and detailed as possible so that benchmarks from external data providers can be referenced The costs are preferably evaluated on an annual basis, for the BASE costs as well as the ONGOING costs. Each time when necessary the life-cycle and depreciation of capital expenditures will have to be detailed and the global labor costs for a given time peπod annuahzed.
The costs are categonzed as follows: Base costs include 1) Design; 2) Acquisition Costs; and 3) Installation Costs. Ongoing costs include 1) Direct Costs; 2) Systems management - aligned to MODE'S System's Management
Category; 3) Changes and upgrades - with many references to MODE'S Managing Change Category; 4) Support - with references to MODE'S Service Management Category; 5) Other Operational costs; 6) Indirect costs; 7) End User; and 8) Downtime.
Base Costs - Detail
The base costs are descnbed m detail below The base costs are identified by "Cost Data" designations CD1 through CD 15 , which are depicted in Fig 1 Capital and Expense costs are distinguished, as they are most of the time accounted for separately in the chart of accounts of a company. There are only labor Expenses in the Design and Installation Costs section, whereas the
Acquisition Costs section pertains to the Capital expenditures.
Design
"CD1" costs relates to systems research and planning CD1 costs include the labor expenses for identifying infrastructure needs, operations architecture service quality, setting standards, defining organization and support requirements, considenng configuration options, assessing scalability, predict TCO hfecycle, and plan rollout, (MODE functions: service planning).
"CD2" costs relates to vendor management. CD2 costs include the labor costs and other expenses (e.g., travel, etc.) for working with service vendors. IS labor time spent on meetings, workshops, writing RFPs, reviewing proposals and dealing with vendor issues. Another issue here is to include the Service Level Agreements (SLAs) and Operating Level Agreements (OLAs) Acquisition costs
This cost category refers to the hardware and software purchases. In order to compare these costs to industry averages, these costs are typically Capital Costs which are annuahzed, and we also have to consider the hardware value depreciation according to the life-time of the each component Different
Organizations may have different depreciation penod dependent on fiscal accounting practices.
Included are all the mateπal expenses for backup systems and systems management software. But no labor fees are accounted for in this category
Hardware
"CD3" relates to end-stations acquisition CD3 costs include the capital expenditures associated with the purchase of a computer (client, sen. er, net- computer, dumb-terminal, laptop, etc.) This includes. the basic configuration: CPU, monitor, mouse, keyboard, mothercard, memory, with possible bundles. the penpherals- video/sound cards, floppy and CD-ROM drives the possible memory and storage upgrades (RAM+ROM) and devices for databases the network and communication devices modem, network cards "CD4" costs relate to network hardware CD4 costs include the capital expenditures for the network communication devices (hubs, bπdges. routers, switches), cablmg-dependmg on the transmission medium, optic fiber, coax etc. - and the connectivity devices: network cards (ATM, Ethernet, etc ). port adapters withm the network communication devices. "CD5" costs relate to operations and multimedia devices CD5 costs include the capital expenditures associated with pnnters, scanners, and all the other multimedia devices (digital cameras, microphones, etc )
"CD6" costs relate to operating system CDT costs include the capital expenditures on operating system licenses This cost is separated from the end- station acquisition cost, even if sometimes the operating system is already installed and there is a bundle pπce.
"CD7" costs relate to application software. CD7 costs include the capital expenditures for business and productivity software. This includes packages such as MS Office, financial and accounting software such as SAP, and all the software related to programming languages that help to build new applications (compilers, test tools, etc.).
"CD8" costs relate to groupware and communication software. CD8 costs include the capital expenditures on software used to connect users and enable sharing of information across the network. This includes: e-mail and other messaging software, Groupware (Lotus Notes, etc....) and remote connectivity software.
"CD9" costs relate to systems management software CD9 costs include the capital expenditures on secunty (virus protection and elimination), performance momtoπng, production control (file transfer, backup and restore, storage) and failure control (fault detection and recovery) software. Enterpnse Management software is included in this category, and can offer bundles for the previous systems management features.
"CD 10" costs relate to utility software. CD 10 costs include the capital expenditures for both multimedia software (videoconferencing tools), and end user utilities (screen savers, disk managers, PhotoShop, etc.) which are not productivity enhancing. Other entertainment software (audio and video tools) are included here
Installation Costs In the installation phase, it is expected that there will be no further matenal costs but only labor costs. Though these expenses will be both contracted labor costs and m-house labor costs.
After the installation phase is completed, the system is expected to be operational. The following labor categones have been identified "CD 11" costs relate to hardware set-up CD11 costs include after labor expenses (internal + external) associated with the deployment of the network and system infrastructure: i.e., put the network devices and the workstations m place, pull down the cables and connect all the workstations to each other. There is also costs to setup the router according to the network topology and all the other network connectivity devices, depending on the protocols used.
"CD 12" costs relate to operating system installation. CD 12 costs include the labor costs (internal + external) associated with the installation of any operating system (UNIX, Windows NT/95, etc.). "CD 13" costs relate to application software. CD 13 costs include the labor costs (internal + external) associated with the installation of all the applications related in the previous section.
"CD 14" costs relate to groupware and communication software CD 14 costs include the labor costs (internal + external) associated with the installation and configuration of all the messaging software and the databases.
"CD 15" costs relate to systems management software. CD 15 costs include the labor costs associated (internal + external) with the installation of the network and systems management platform and the anti-virus systems.
Ongoing Costs - Detail
The ongoing costs are divided into two categones: the direct costs (CD 16-
CD39) and indirect costs (CD40-CD44). The direct costs are the budgeted costs to maintain and optimize the availability of key network resources, manage the system and implement the changes, and support the network users. The indirect costs are expenses that are not budgeted and often not accounted for in most of the IT organizations. These hidden costs make the true costs of IS systems underestimated, because the impact of downtime - which is a crucial factor increasing the overall costs - is too often not measured. Direct Costs
Systems management
As the overall planning phase of the systems management is assumed to be included m the "design" phase, this part of the labor is not taken into account as a whole here. Nevertheless for some areas an ongoing planning phase will be part of a systems management component.
The categoπes tend to match the MODE framework.
Production Control
"CD 16" costs relate to application management. The annual labor expenses (internal + external) for ongoing management of applications including control and access management, pnnt management and file transfer and control. These costs may include development costs.
"CD 17" costs relate to storage management. The annual labor expenses (internal + external) for disk and file management (optimizing local and server on-line storage and file systems), data access management (providing user availability to information: database management, server file access and remote servers access), backup and archiving and repository management These costs may include development costs.
"CD 18" costs relate to traffic management. The annual labor expenses (internal -t- external) for pro-actively interpreting, planning and balancing the load placed on the network infrastructure.
Monitoring
"CD 19" costs relate to event management. The annual labor expenses to log, classify and present event messages on consoles with pre-established filters or thresholds. In case of a fault, the message should be forwarded to those who can correct the fault and do a diagnosis. "CD20" costs relate to performance management. The annual labor expenses for interpreting, planning and balancing the performance of servers, networked systems and applications.
"CD21" costs relate to physical site management. The annual labor expenses (internal + external) for routine tasks that are performed on a scheduled or interval basis to maintain the accessibility and performance of the whole system. This includes tasks such as routine cycling of applications and databases. The task operated is a kind of overall maintenance labor.
Security Management & Failure Control In this section there are not only labor costs, but also maintenance contract costs.
"CD22" costs relate to secunty and virus protection The annual labor costs and other expenses (development costs) for preventing from secunty violations; password management, access restnction, virus infection and recovering from such violations or intrusions should they occur
Detection is tallied in the momtoπng section.
"CD23" costs relate to LAN/WAN troubleshooting and repair. The annual expenses (internal + external) for technicians and administrators in identifying and resolving advanced support issues including failure, fault, and accessibility problems with the network, computers, printers, operating systems, and applications.
"CD24" costs relate to disaster planning and recovery The annual labor expenses for restonng data, building disaster recovery and management plans including backup and restore procedures, record keeping and disaster recovery team organization.
"CD25" costs relate to hardware maintenance fees. The annual maintenance contracts fees. Generally agreed upon in SLAs, these contracts are earned out, monitored and recorded for each asset Changes And Upgrades
This cost area refers as well to the ongoing upgrades to the system as to the deeper changes that affect the whole system.
"CD26" costs relate to change planning. The annual costs associated with management of change planning. These costs are labor costs associated with the development of change control strategies and migration control (move from the development environment to the test and finally the production environment), and outsourced management fees such as strategic and tactical consulting.
"CD27" costs relate to asset management. The annual labor expenses for asset mventoπes (physical or automatic), asset identification and tracking, asset database management, change recording and/or managing automated asset management systems. Asset management is mventoned here because it is necessary to know what exists before implementing a change.
"CD28" costs relate to product evaluation and testing The annual labor expenses for evaluation and testing of new technology mateπals (hardware, software) pnor to purchase. Here are also accounted for the "vendor management" ongoing labor costs (see DESIGN section)
"CD29" costs relate to products procurement and implementation. The annual expenses for the purchase of new hardware and software, and the labor costs associated with their initial installation and configuration Included here are the labor costs associated with software licensing and distnbution, i.e . metenng the number of available licenses and monitonng their usage (operating systems, applications, and connectivity software)
"CD30" costs relate to user administration (adds, moves and changes to users). The annual labor expenses for controlling user accessibility to network and application resources. Tasks include adding new users and resources, moving users to new groups, password management, or changing users profiles Support
The support costs are the direct labor expenses and fees associated with supporting the network's users.
"CD31" costs relate to help desk (Tier I support). The annual labor expenses for Tier I Help Desk support calls. The Tier I refers to the time spent by phone staff to answer calls and support End-Users without any intervention. Support Services performed at Tier II and III, that implies advanced troubleshooting and failure recovery are recorded in Systems Management.
"CD32" costs relate to request and problem management and planning. The annual labor costs associated with the coordination and control of all activities necessary to fulfill a request from either a user, vendor, or developer, and the prevention from recurring incidents to happen by determining the underlying problems causing these incidents, logging and archiving them Included are also the labor costs associated with the design of the help desk, and the fees for legal counsel in planning and strategic consulting.
"CD33" costs relate to casual learning. The annual labor expenses of IS professional's time spent on independent, self-education and learning outside of formal training programs. Topics include self-education on computers, networks, printers, storage systems, network communication devices, as well as IS utilities and end-user applications
"CD34" costs relate to training The annual labor expenses and fees for develop, deliver training courses and train as well end users as IS personnel. This includes
The labor time spend on training courses development (design, development, testing and maintaining IS and end-user courseware - inci CBTs)
The labor expenses for dehvenng IS courses as well as the time spent by IS personnel in attending courses (both m-house and external courses)
The labor expenses for the delivery by trainers of end-user training courses, and the time spent by end-users on computer systems and all application training (incl. the initial framing just after rollout) "CD35" costs relate to operating costs. The annual fees for support tools (books, etc.) and travel. The travel expenses include as well the travel time to support remote branch offices, attend training sessions, visit vendors as the travel expenditures.
Operational Costs
This category pertains to the costs that are not associated either with maintenance, support, or changes. It is the last category associated with "hard costs," the other indirect costs being more subjective are often referred to as "soft" costs. "CD36" costs are related to communications fees The annual expenses for communication fees such as lease line fees, on-line access-fees, remote access services, WEBTSP hosting fees, and allocated WAN fees.
"CD37" costs relate to leased asset fees. The annual fees for leased assets including, e.g., servers, printers, hubs, bndges, routers, switches, or client software.
"CD38" costs relate to IS commodity expenditures. The annuahzed capital fees for computer supplies such as floppy disks, CD-ROM disks, backup tapes, toner cartridges and other expendables
"CD39" costs relate to insurance. The annual fees for insurance agamst theft, voltage shortage (implying data loss), etc.
Indirect Costs
The indirect costs are those that are not ongmally budgeted because they stem from a productivity loss due either to the end user themselves or to unplanned systems downtime. The majonty of these metrics are sometimes difficult to measure. These costs are identified as CD40-CD44, as shown in FIG.
1. End User
When end-users are diverted onto IT support onented work, it results in a decrease of the global productivity of the company. For example, the higher the salary of an end-user is, the more important it is that they perform their core role and not spend time on self-learning and peer support. These costs are at best calculated estimates.
"CD40" costs relate to casual learning. The annual labor expenses of end users framing themselves in lieu of formal training programs. Time includes reading manuals, using on-line help, tnal and error, and other self-learning methods. Costs can be higher for casual learning than formal learning an inadequate formal training will result in high casual learning expenses
"CD41" costs relate to peer and self support. The annual labor expenses for end users supporting themselves and each other instead of obtaining technical support from help desk or IS personnel. These tasks-repair, support, maintenance. installation, framing- are performed extensively by end-users in remote offices not staffed by dedicated IS personnel or covered by support contracts.
"CD42" costs relate to Futz factor. The annual labor expenses associated with the development and customization of non-busmess applications (Notes scnpts, etc.), the unnecessary changes to their computer or network settings (screen, file organization, folder, sounds, pnnters, etc ), and the time spent on playing games or web surfing
Downtime
Downtime expenses are defined as a potential annual loss due to the unavailability of the IT Infrastructure due to faults, and its impact as measured as loss of productivity.
Most organizations lack accurate direct measurements of downtime, and even often do not track system reliability, therefore it is difficult to quantify the losses in terms of business revenues or productivity Nevertheless, downtime causing lost productivity is considered Downtime can be either due to the waiting for a help desk problem to be resolved, to an infrastructure issue (planned maintenance), or unplanned failures (application bugs or inaccessibility, network outages, etc.), for example.
"CD43" costs relate to planned downtime. The annual productivity losses to end users from planned system maintenance, including downtime for backups or migrations of databases and optimizations.
"CD44" costs relate to unplanned downtime. The annual productivity losses to end users from unplanned outages of the network resources, including client computers, shared servers, pnnters, applications, communication resources, and connectivity. The unplanned network outages are almost always obtained from end user surveys.
Appraisal Metrics
The appraisal metncs are intended to be key performance indicators for IT operations as a measurement and assessment tool for the TCO, to evaluate and monitor its effectiveness. Different areas, divided mto sections, have been distinguished to facilitate the comprehension and the use of all the metncs along the analysis. The comparison with available market data should allow then to elaborate best practices.
When computing the metrics, the parameters involved are preferably must be homogeneous, i.e., each parameter has to be measured within the same time penod. The time period is taken to be equal to one year. The metrics are categonzed as follows:
Financial Perspective (FP): 1) Cost effectiveness; and 2) Budget management and repartition. Ability to operate effectively and efficiently the IT operations and Systems Infrastructure (OEE). 1) Quality; 2) Availability: and
3) Efficiency. Infrasfrucmre and evolution perspective (IEP): 1) Adaptability, and 2) Future requirements and growth. Metrics Template
In order to have standardized metncs, all the metncs are constructed according to the same template. This template defines the name of the metnc and gives it a number, provides the MODE functions that are involved, indicates the parameters that are involved, how to compute them, the objective of each metnc and additional comments.
Financial perspective (FP)- The FP metncs look at the TCO m terms of its financial performance. To achieve this, ratios are computed for different cost metncs, and then organized by topic
Cost Effectiveness
Budget allocation
FPI-A TCO budget ratio
• MODE ftmctιon(s) or Category involved: SERVICE MANAGEMENT/ Administration - Billing & Accounting • Data Elements and Unit of Measurement: The TCO budget \ alue
(measure 1). S; the total business budget value (measure 2) S
• Formula: Measure 1 / Measure 2 * 100%
• Metnc objective and additional comments. This metnc can be used to provide benchmarking and estimating guidelines for TCO and IT budgeting. Here the business budget value considered is equal to the total costs of the entire business including operations and project costs. The larger this rate is, the more the company is technology-onented or its network systems are meaningful to it (if there are many applications cπtical to business, the costs associated with the Corporate system will be higher since the network operations will have to be very effective). Salaries
FP1-B Average Corporate Salary
• MODE functιon(s) or Category involved: SERVICE MANAGEMENT/ Administration - Billing & Accounting. • Data Elements and Unit of Measurement: The sum of all employees yearly salanes (measure 1)...S. The total number of employees (measure 2).
• Formula: Measure 1 / Measure 2.
• Metnc objective and additional comments: This metnc measures how costly the staff employed are in the company. It would be very interesting to know the salary structure too. in order to better assess the indirect costs, since the costs associated to downtime and end-users are directly linked to the salary of the end-users concerned.
Support cost ratio
FP1-C: Support Costs per FTE
• MODE functιon(s) or Category involved- SER VICE MANAGEMENT'
Administration - Billing & Accounting, Help Desk and /Qualm Management - Training.
• Data Elements and Unit of Measurement The total cost of support desk - see TCO "Support category," Σ(CD31 +.. -CD35) (measure 1 ) ..S. The total number of hours a user works on average per year (measure 2).
• Formula: Measure 1 / Measure 2.
• Metric objective and additional comments- The point m measuring this cost on a per user basis is to take mto account the potential changes in the organization: in case of great changes, the aggregate support desk cost may be misleading.
Its objective is to provide a benchmarking device and an estimating guideline, but it can also be used to determine the effectiveness of efforts to reduce the costs or improve the efficiency of the support devices. Ideally, increases of the costs m this area should result in cost decreases in other areas, especially in the other support desk metncs.
Budget Management And Repartition
Budget management
FP2-A Cost Variance from Total Approved Budget
• MODE functιon(s) or Category invoK ed: SERVICE MANAGEMENT/Administration - Billing & Accounting.
• Data Elements & Unit of Measurement. Actual TCO for the previous financial year (measure 1 ) - compute the sum of all costs related Σ(CD1+ . +CD44).. S. Budgeted TCO for the previous financial year
(measure 2)...S.
• Formula: Measure 1 - Measure 2 / Measure 2.
• Metnc objective and additional comments: This metnc measures the effectiveness of management of TCO budgets, showing the variance from total approved budget. It is obtained by dividing the acmal TCO minus the budgeted
TCO by the budgeted TCO for the last financial year.
Ideally, the actual cost should not go over the budgeted cost, and should not be more than 5% less than the budgeted cost (otherwise the budget would be badly managed).
Ongoing costs ratios
This metnc is actually an aggregation of several metrics, each being a ratio between different areas of the ongoing costs. The areas considered are support, systems management, change and upgrades, and indirect costs.
FP2-B. Support to Systems Management Ratio
• MODE functιon(s) or Category involved: SERVICE
MANAGEMENT/Administration - Billing & Accounting, Help Desk and /Quality Management - Training, SYSTEMS MANAGEMENT. • Data Elements and Unit of Measurement: Systems Management Costs (measure 1) - sum of all the costs related Σ(CD16+...+CD25)...$. Support Costs (measure 2) - sum of all the costs related Σ(CD31+...+CD35)...$.
• Formula: Measure 2 / Measure 1 * 100%. • Metnc objective and additional comments. This ratio is an indicator for the rate of reactive to proactive budgeting. It also provides a benchmarking device. A trade-off has to be found between support and systems management.
FP2-C: Changes & Upgrades to Systems Management Ratio
• MODE functιon(s) or Category involved: MANAGING CHANGE. SYSTEMS MAN A GEMENT
• Data Elements and Unit of Measurement. Systems Management Costs (measure 1) - sum of all the costs related Σ(CD16+...+CD25)...S. Changes & Upgrades (measure 2) - sum of the costs related Σ(CD26+...^CD30). S
• Formula: Measure 2 / Measure 1 * 100%. • Metnc objective and additional comments. The importance of change and upgrade cost either reflect a bad planning or a firm policy that encourages frequent changes. The higher the rate is, the shorter the system's life span could be.
FP2-D Indirect Costs to Direct Costs Ratio
• MODE functιon(s) or Category involved: SERVICE
MANAGEMENT/Administration - Billing & Accounting. SYSTEMS MAN AGEMENT/F allure control - Fault Management. SERVICE PIANNINGS/Service Management Planning - Training Planning.
• Data Elements and Unit of Measurement. Direct Costs (measure 1) - the sum of all costs related Σ(CD16+...+CD39)...$. Indirect Costs (measure 2) - the sum of all costs related Σ(CD40+ ... +CD44) ... $ .
• Formula: Measure 2 / Measure 1 * 100%. • Metric objective and additional comments. This ratio provides a benchmarking device for the cost estimations. There is a great point in reducing the ratio between the indirect costs and the total of direct costs, as direct costs are more easily measured and thus predictable. As the indirect costs are depending strongly on the performance of the two last related MODE functions, this rate indicates also how well downtime and peer support can be avoided.
FP2-E: Ongoing to Base Cost Ratio
• MODE functιon(s) or Category involved: SER VICE MAN A GEMENT Administration - Billing & Accounting. SYSTEMS PIANNINGS/MODE
Strategic Planning
• Data Elements and Unit of Measurement. The Ongoing costs (measure 1) the sum of costs related Σ(CD16+...+CD44)...S. The Base Costs (measure 2) - the sum of all costs related Σ(CDl+...+CD 15 )...$. • Formula: Measure 1 / Measure 2.
• Metric objective and additional comments. This ratio allows to give an overview of the manageability and the complexity of an organization and the reliability of the technology and matenals used. Depending on the life cycle of the system-the longer the better- it can be useful to have a small ratio
labor costs Ratios
Again this metric is an aggregation of two metrics that intend to define the importance of the labor costs for the TCO as well as outsourcing trends.
FP2-F: Ratio of External to Internal Labor Costs
• MODE functιon(s) or Category involved: SER VICE MAN A GEMENT/ Administration - Billing & Accounting and Contract Management.
• Data Elements and Unit of Measurement. The Internal labor costs (measure 1) ...$. The External labor costs (measure 2) ...5.
• Formula: Measure 2 / Measure 1. • Metric objective and additional comments As there are many metncs gathenng both internal and external labor costs, it is not possible to reference metncs in order to computer this ratio To compute it, it is assumed that the external labor costs are made up by both service contracts and contractors, and the sum of all these external labor costs are divided by all the internal labor costs
This ratio can be used to compare similar industry companies to determine industry trends in the way that some IT operations are outsourced Sources such as Gartner Group provide information about outsourcmg trends that can be used for benchmarking
FP2-G Ratio of Labor Costs to Other Costs
• MODE functιon(s) of Category invoked SERVICE MANAGEMENT Administration - Billing & Accounting and SERVICE PLANNIN 7./ODE
St ategic Planning
• Data Elements & Unit of Measurement 1 ) The Internal labor costs (measure 1) $, 2) The External labor costs (measure 2) $, and 3) The TCO for the last fiscal year (measure 3) S
• Formula (Measure 1 + Measure 2) / (Measure 3 - Measure 1 - Measure 2)
• Metric Objective & Additional Comments This ratio allows to detect if a technology improvement is needed, e g in the systems management field where momtonng and asset management can be automated The results of the previous metnc allows to determine the overall labor costs For each cost element used to calculate the total TCO, the labor costs are indicated
Ability to operate effectively and efficiently the IT operations and Systems Infrastructure (OEE)
The metncs in this area measure the performance of the business, focusing on system and operations quality, availability, and efficiency Quality
System's reliability
OEEI-A: Number of Faults per User
• MODE functιon(s) or Category involved: SER VICE MAN A GEMENT/ Quality - Quality. SYSTEMS MAN AGEMENT/Failure control - Fault
Management.
• Data Elements and Unit of Measurement. The total number of incidents presented Tier 2 service Desk (measure 1) The total number of users (measure 2). • Formula: Measure 1 / Measure 2.
• Metric objective and additional comments This metric measures the reliability of the technology implemented withm the system It is obtained by dividing the total number of incidents presented to Tier 2 service Desk by the total number of users of the whole systems during the past year. The higher this rate is, the less reliable is the technology used, and this could dramatically increase the costs associated with troubleshooting and repair
System 's performance rating
Those two aggregated metrics measure the system global performance and security.
OEE1-B System 's Performance Demand
• MODE functιon(s) or Category involved' SERVICE MANAGEMENT/Productwn control - Production Scheduling.
• Data Elements and Unit of Measurement: System's performance demand rating Rate from 1 to 5. • Formula: No formula needed.
• Metric objective and additional comments This metric e\ aluates the global systems performance required by company business needs. The systems overall performance will be rated from 1 to 5, according to both technology efficiency (bandwidth available, file transfer speed, storage capacity) and fault tolerance and recovery (e.g., banks are very sensitive to downtime); basic technology and great fault tolerance; medium technology and great fault tolerance; medium technology and little fault tolerance; high technology and little fault tolerance; high technology and no fault tolerance.
OEE1-C: Physical and Logical Security Rating
• MODE functιon(s) or Category involved: SYSTEMS MANAGEMENT/Monitoring - Physical Site Management and / Security Management
• Data Elements and Unit of Measurement: Physical and logical security rating... Rate from 1 to 5.
• Formula: No formula needed.
• Metric objective and additional comments. This metric evaluates the performance of the system in terms of security. The rating, going from 1 to 5, allows to indicate how important security is to the company, and then to assess the budget that could be spent on this area. For a given rate and according to the industry sector, benchmarks concerning budgets allocated to security may be available; system not secured; system poorly secured; system globally secured; system well secured; and system highly secured.
Availability
Network availability
OEE-2A: Downtime Rate
• MODE functιon(s) or Category involved: SER VICE MAN A GEMENT/Quality Management and SYSTEMS MAN A GEMENT /Failure control. • Data Elements and Unit of Measurement: The total network downtime (measure 1)....Hours; and The total number of hours a user works on average per year (measure 2)...Hours.
• Formula: Measure 1 /Measure 2 • Metnc objective and additional comments. This metnc measures unavailability of the network, either due to planned interruptions, or to technology failures during the past year. Included in downtime is time a user waits for a problem to be resolved. The productivity loss should be taken into account as an indirect cost when setting the TCO budget, and it is important to notice that the support team's efficiency can dramatically decrease downtime
Call Rates
This metric measures both the call reloggmg rate and abandonment rate at the Help Desk.
OEE2-B Call Relogging Rate
• MODE functιon(s) or Category involved: SERVICE MANAGEMENT/
Quality Management and Help Desk
• Data Elements & Unit of Measurement. The number of calls that have been relogged by the Help Desk (measure 1) The total number of calls presented to the Help Desk (measure 2) • Formula: Measure 1 /Measure 2
• Metric objective and additional comments. This measurement, obtained by dividing the total number of relogged calls by the total number of calls presented to the Help Desk dunng the past year, check the availability of Help Desk people. A high percentage value for this metnc indicates a poor success rate at resolving the underlying causes of problems.
OEE2-C Call Abandonment Rate
• MODE functιon(s) or Category involved SER VICE MAN A GEMENT/ Quality Management and Help Desk • Data Elements and Unit of Measurement- The total number of calls abandoned pnor to closure (measure 1). The total number of calls presented to the Help Desk (measure 2).
• Formula: Measure 1 /Measure 2. • Metnc objective and additional comments This rate assesses the capability of the Help Desk to handle the received calls. In case of a high rate here, the end user downtime or peer/self support could increase, which results in a productivity loss. The higher the result for this metnc the lower the ability of IT Operations to provide a fault resolution service; on the other hand a low value for this metric indicates a sufficient call taking capacity for the Service Desk
EJfϊcienn
Average response and resolution time
These two metncs correspond to two consecutive steps in the resolution of a problem: first reporting, and then solving.
OEE3-A Average Response Time
• MODE functιon(s) or Category involved- SER VICE MAN A GEMENT/ Quality Management and Failure Control
• Data Elements and Unit of Measurement The time it has taken to the support organization to respond to all incidents or problems (measure 1 ) - see m the Monitoring section of Systems Management ..Hours The Number of incident problems tallied (measure 2).
• Formula. Measure 1 /Measure 2
• Metnc objective and additional comments- The average response time metnc determines the average time it takes the support organization to respond to an incident or problem. Normally, response time is defined as the time from the support organization first being aware of the incident or problem to the time at which the first action is taken (usually informing or giving status to users) It may be divided into further metncs based on the cnticality of the requests (low, medium, high, cπtical).
OEE3-B Average Resolution Time
• MODE functions) or Category involved: SER VICE MAN A GEMENT/ Quality Management and Failure Control.
• Data Elements and Unit of Measurement. The time it has taken to the support organization to resolve problems as soon as requests were reported (measure 1) - see LAN/WAN troubleshooting & repair...Hours Number of Incident/problems tallied (measure 2) Hours. • Formula- Measure 1 /Measure 2.
• Metnc objective and additional comments The average resolution time is the measure of the time from an incident or request being reported to the time at which it is resolved One can distinguish the "incident" and "request" categones: an incident is an occurrence-system error or malfunction-that requires assistance from the support organization, whereas a request refers to an action that a user asks to be performed that is usually related to network/workstation administration or software/hardware changes. Again further subdivision of the metnc can be considered according to the defined cnticality of the incident or request.
It is interesting to compare these metrics in order to assess the support organization's efficiency, and define the SLAs
Help Desk Call Handling rate & staffing ratio
These two correlated metncs measure the efficiency of the Help Desk staff.
OEE3-C Help Desk Call Handling Rate
• MODE functιon(s) or Category involved SERVICE MANAGEMENT/
Quality Management and Help Desk
• Data Elements and Unit of Measurement -The number of calls presented to the Help Desk (measure 1).. one; -The total number of Help Desk Tier I staff (measure 2)...None -The average number of days worked by Help Desk Tier I staff (measure 3)... None. • Formula: Measure 1 /Measure 2/Measure 3
• Metric objective and additional comments. By dividing the total number of calls received by the Help Desk first line support staff by the average total number of Tier I support staff and by the average number of days worked during the past year, one can determine the productivity rate of the Tier I Help Desk staff.
OEE3-D: Help Desk Staffing Ratio
• MODE functιon(s) or Category involved: SERVICE MANAGEMENT/Help Desk.
• Data Elements and Unit of Measurement: The total number of Help Desk Tier I staff (measure 1 ) ... The total number of users (measure 2 ) .
• Formula: Measure 2/Measure 1
_ • Metric objective and additional comments. By dividing the total number of end users by the number of Help Desk personnel one have a good indication of the effectiveness of the Help Desk. The two metncs (OEE3-C and OEE3-D) are conelated. because if the percentage associated to one metric increases, the other percentage associated to the second metnc should also increase. Nevertheless, by multiplying those two rates, the number of calls that are presented to the Help Desk per employee is obtained, which is another interesting metric. Desktop services delivery
OEE3-E- Average Time to Deliver a PC to Desk
• MODE functιon(s) or Category involved: MANAGING CHANGE/ 'Implementing - Procurement. • Data Elements and Unit of Measurement: The aggregate time to deliver all PCs accepted dunng the previous year (measure 1). Days. The number of PCs ordered dunng the last year (measure 2).
• Formula: Measure 1 /Measure 2.
• Metric objective and additional comments This metric measures the average time to deliver desktop services, from the order to the end of the installation, including the delivery and configuration. It allows to determine the flexibility of the system and its ability to administrate the users
SLAs management
This metnc measures both the rate of ongoing systems operations covered by SLAs as the actual performance of these operations agamst the SLAs
OEE3-F SLA 's Operations Coverage Ratio
• MODE functιon(s) or Category involved: SER VICE MANAGEMENT/SLA Management
• Data Elements and Unit of Measurement: The number of Operations that are covered by SLAs (measure 1) The total number of Operations (measure
2). None.
• Formula Measure 1 /Measure 2 * 100%
• Metric objective and additional comments- This metnc shows how the operations are covered by SLAs. According to best practices, the SLAs should cover 100% of Operations to ensure that services rendered are according to requirements and any discrepancies can be easily identified and rectified as needed. OEE3-G Operations Performance against SLA 's
• MODE functιon(s) or Category involved: SERVICE MANAGEMENT/SLA Management - Reporting and Quality Management - Quality Management • Data Elements and Unit of Measurement: The total number of
Operations Performance Measures that are covered by SLAs (measure 1). The number of Operations Performance Measures that fail to meet SLAs requirements (measure 2)
• Formula: Measure 2/Measure 1 * 100% • Metric objective and additional comments The result allows to show the performance of the system compared to the established targets. The SLAs can thus be corrected if necessary, and/or the systems performance improved Infrastructure and evolution perspective (IEP)
This area looks at the scalability of the infrastructure and at how sustainable the performances are likely to be m the future.
Adaptability
System 's scalability
This measure rates the upgradeabihty of the system's technology from 1 to 5. depending on the different technologic features of the system, gives the number of different platforms operated and the system's like span to assess the system's flexibility.
IEP I- A Svstem 's Upgradability and Life Span
• MODE functιon(s) or Category involved: MANAGING CHANGE/Controlling - Asset Management and SERVICE PLANNING/MODE Strategic Planning.
• Data Elements and Unit of Measurement. The number of platforms operated. The systems life span.
• Formula: No formula is required The metric is a rating from 1 to 5 that results from the values of the measures above • Metnc objective and additional comments This rating allows to evaluate the system's complexity, scalability, and durability (1 = not scalable, short life span, 2 =httle scalable, short to medium life span, 3 = scalable but complex, medium life span; 4 = scalable and not very complex, medium to long life span, and 5 = very scalable, long life span)
WAN bandwidth utilization
This metnc measures the percentage of bandwidth used
IEP1-B WAN Bandwidth Utilization
• MODE functιon(s) or Category involved SYSTEMS MAN A GEMENT /Monitoring - Performance Management
• Data Elements and Unit of Measurement The bandwidth that is used (measure 1) Mb The total available bandwidth (measure 2) Mb
• Formula Measure 1 /Measure 2 * 100%
• Metnc objective and additional comments Bandwidth utilization is to be measured at a peak time with utilization duration greater than five minutes
In addition, the percentage of time that use falls between a specified range is also measured, the objective could be to determine if the WAN bandwidth utilization is withm a certain range and if it is not. the extent and frequency with which it is out of range This also allows to see the supportable traffic increase on the network
NB Information about bandwidth utilization is usually given as part of standard reports from WAN providers
Training
IEPXC Average Training Hours Delivered per FTE
• MODE functιon(s) or Category involved SER VICE MANAGEMENT /Quality Management - Training • Data Elements and Unit of Measurement The aggregate number of training hours delivered last year (measure 1)...Hours; The total number of hours a user works on average per year (measure 2) ..None
• Formula: Measure 1 /Measure 2 • Metnc objective and additional comments This metnc measures the capability of the human resources to tram people As a result, a more highly trained staff is likely to be more flexible as everyone is then more likely to fulfill a vanety of roles.
Change IEP1-D Average Time to Implement a Change
• MODE functιon(s) or Category involved MANAGING CHANGE
• Data Elements and Unit of Measurement The aggregate time that it took to the company to implement registered changes (measure 1) and The number of changes that have been implemented (measure 2) None • Formula: Measure 1 /Measure 2
• Metnc objective and additional comments This measure indicates how long it takes in average to the company to carry change related projects It provides a good benchmark for the potential changes that were foreseen
Future Requirements and Growth Planning
This metnc measures the length of planning horizon m cuπent long term operational plan. It is cmcial to have access to this data in order to assess the effectiveness of the organization
IEP2-A Length of Planning Horizon
• MODE functιon(s) or Category involved SERVICE
PLANNING/MODE Strategic Planning
• Data Elements and Unit of Measurement Length of planning honzon in current long term operation plan Years • Formula: None
• Metnc objective and additional comments. In general the longer the length of IT Operations planning honzon the more effective that organization is going to be at predicting future demand. However, some caution should be applied as any detailed planning is unlikely to be feasible beyond a year planning honzon and even more generalized planning is likely to become less useful beyond 3 years. An IT Operations function that has horizon of 3 years or more, can be considered 'capable' in terms of this metric. Growth perspective This metnc is an aggregation of three separate metncs that tend to indicate the organization's orientations.
IEP2-B: End-user Staff Growth or Attrition
• MODE functιon(s) or Category involved: SER VICE PLANNING MODE Strategic Planning • Data Elements and Unit of Measurement: The number of new joiners expected (measure 1). The number of persons that are expected to leave the company (measure 2). The total current number of employees (measure 3).
• Formula: (Measure 1 + Measure 2)/Measure 3
• Metnc objective and additional comments. The end-user staff growth or attrition rate has consequences on all the metrics that deal with labor costs, so it is interesting to predict the changes in order to assess the overall new budget.
IEP2-C: Budget Estimation
• MODE functιon(s) or Category involved: SERVICE PLANNING/Service Management Planning - Service Pricing and Costing • Data Elements and Unit of Measurement: The expected TCO budget for next year (measure 1) The current TCO budget (measure 2).
• Formula: (Measure 1 - Measure 2)/Measure 1 • Metnc objective and additional comments. The vanance of the next budget compared to the current budget is related to an overall planning of operations, changes, and technology orientations. As a result, many metncs will be affected by the budget onentations that are reflected in this metnc.
IEP2-D' Performance Expectations
• MODE functιon(s) or Category involved: SER VICE PLANNING/Managing Change Planning
• Data Elements and Unit of Measurement: The performance improvement expectation (measure 1) ... Rate from 1 to 5 • Formula: Measure 1
• Metric objective and additional comments This metric indicates how the performances of the system should improve: no improvement needed: little improvement needed; medium improvements needed: great improvements needed; overall cntical improvements required.
Appraisal Metrics Interrelationships
The relationships that exist between the different appraisal metncs defined m the previous section are descnbed in more detail below. The information can be used as a starting point in the interpretation of both cost data and appraisal metncs before beginning the benchmark study. Interrelationships Overview
The relationships between the metrics can be summarized in a symmetnc matrix featunng different types of relations:
- One metric can influence another metric, i.e., its value has direct consequences on the another metnc 's value. Example: The average Corporate salary of a Company influences the
Support Costs per FTE, since the Support Costs are labor costs that are at least partly performed by employees of the company
- One metric can be similarly influenced by another metnc, i.e.. its value is partly determined by another metric' s value. - Two metncs can have a complementary relationship, i.e., their vanations should be correlated.
Example: If the FTE downtime rate increases, the Cost vanance from total approved budget should also increase since FTE downtime begets Indirect costs that are not predicable. In this case, we have a kind of "indirect influence" between the first and the second metnc.
- Two metncs can have a trade-off relationship, i.e., if the value of one metnc increases, the value of the other should tend to decrease.
Example: There is a trade-off between the Help Desk staffing ratio and the Call relogg g rate. If the Help Desk support staff increases, more calls could be handled and thus the Call reloggmg rate would decrease.
Interrelationships Profiles
For each metnc, the related metncs as well as the nature of their relationships is provided in the Tables below. All the metncs except those related to Infrastructure and Evolution Perspective, i.e., metncs IEP2-B, C and D, have relationships with other metncs, and often there are cross-categories relationships.
One has to be careful when considenng the metrics associated with time, because a "complementary relationship" can either tend to increase or decrease its value For those types of metncs, the influence of other metrics on the time and the inverse of the time that indicates the performance for this type of metric ments close analysis.
Table 1
Figure imgf000037_0001
Table 2
Figure imgf000038_0001
Table 3
Figure imgf000038_0002
Table 4
Figure imgf000038_0003
Table 5
Figure imgf000038_0004
Table 6
FP2-C
Changes & Upgrades to Systems Management
Related Metrics Nature of the Relationship to FP2-C
FP2-F Ratio of extemal to internal costs Complementary relationship IEP1-A System's upgradeability and life span Trade-off relationship IEP1-D Average time to implement a change Trade-off relationship
Table 7
Figure imgf000039_0001
Table 8
Figure imgf000039_0002
Table 9
Figure imgf000039_0003
Table 10
FP2-G
Ratio of Labor Costs to Other Costs
Related Metrics Nature of the Relationship to FP2-G
FPl-B Average corporate Salary Influences FP2-G FPl-C Support costs per FTE Complementary relationship FP2-E Ongoing to base costs ratio Complementary relationship Table 11
OEEl-A
Number of Faults per FTE
Related Metrics Nature of the Relationship to OEE1- •A
FPl-C Support Costs per FTE Trade-off relationship
OEE1-B System's Performance Demand Trade-off relationship
OEE2-A FTE downtime rate Is influenced by OEEl-A
OEE2-B Call reloggmg rate Complementary relationship
OEE2-C Call abandonment rate Complementary relationship
OEE3-C Help Desk call handling rate Is influenced by OEEl-A
IEP1-B WAN bandwidth utilisation Influences OEEl-A
Table 12
Figure imgf000040_0001
Table 13
Figure imgf000040_0002
Table 14
Table 15
OEE2-B
Call Relogging Rate
Related Metrics Nature of the Relationship to OEE2 -B
FPl-C Support Costs per FTE Trade-off relationship
OEEl-A Number of faults per user Complementary relationship
OEEl-B System's performance demand Trade-off relationship
OEE2-A FTE downtime rate Complementary relationship
OEE3-A Average response time Complementary relationship
OEE3-C Help Desk call handlmg rate Complementary relationship
OEE3-D Help Desk staffing ratio Trade-off relationship
Table 16
OEE2-C
Call Abandonment Rate
Related Metrics Nature of the Relationship to OEE2-C
FPl-C Support costs per FTE Trade-off relationship OEEl-A Number of faults per user Complementary relationship OEEl-B System's performance demand Trade-off relationship OEE2-A FTE downtime rate Complementary relationship OEE3-A Average response time Complementary relationship OEE3-C Help Desk call handlmg rate Complementary relationship OEE3-D Help Desk staffing ratio Trade-off relationship
Table 17
Figure imgf000041_0002
0EE2-B Call reloggmg rate Complementary relationship 0EE2-C Call abandonment rate Complementary relationship QEE3-F SLA's operation coverage ration Complementary relationship to 1/QEE3-A
Table 18
Figure imgf000042_0001
Table 19
Figure imgf000042_0002
Table 20
Figure imgf000042_0003
Table 21
Figure imgf000042_0004
Table 22
Figure imgf000043_0001
Table 23
Figure imgf000043_0002
Table 24
Figure imgf000043_0003
Table 25
Figure imgf000043_0004
Table 26
Figure imgf000043_0005
Table 27
Table 28
Figure imgf000044_0002
Table 29
Figure imgf000044_0003
Table 30
Figure imgf000044_0004
Table 31
Figure imgf000044_0005
Table 32
Figure imgf000044_0006
The value for the appraisal metrics is in companng them in time v. ith previous calculated metncs for a system, or in comparing them with predetermined benchmarks. For some metrics there are no given benchmarks, but rather expected value ranges, which allows to include values for different industry types in the same table. Of course, other benchmark values may be used for specific industries, and for specific experiences with certain IT organization configurations. In Table 33 below, some exemplary benchmarks are provided.
Table 33
Figure imgf000045_0001
While this invention has been shown and described in connection with the embodiments described, it is apparent that certain changes and modifications, in addition to those mentioned above may be made from the basic features of this invention. Many types of organizations may benefit from the use of this invention, e.g., any organization wishing use an information technology system. In addition, there are many different types of computer systems, and computer software and hardware, that may be utilized in practicing the invention, and the invention is not limited to the examples given above. Accordingly, it is the intention of the applicants to protect all variations and modifications within the valid scope of the present invention. It is intended that the invention be defined by the following claims, including all equivalents.

Claims

1. A method for determining the cost for each user of an information technology system, the method compnsing: obtaining base costs; obtaining ongoing direct costs; obtaining ongoing indirect costs; gathenng information relating to user profiles and organizational characteπstics; and inputting said costs and information mto a computer program to determine the cost for each user.
2. The method of claim 1, wherein said base costs include design costs, acquisition costs, and installation costs.
3. The method of claim 1 , wherein said ongoing direct costs include production control costs, monitoring costs, security management and failure control costs, changes in upgrade costs, support costs, and operational costs.
4. The method of claim 1 , wherein said ongoing indirect costs include end-user costs and downtime costs.
5. The method of claim 1, wherein at least one of said costs corcespond to at least one information technology function, and the cost for each user is broken down according to said information technology function.
6. A method for analyzing the costs associated with supporting an information technology system, the method compnsmg: obtaining cost information; obtaining system charactenstics; calculating appraisal metrics based on said cost information and said system characteπstics; and comparing said appraisal metrics with established benchmarks.
7. The method of claim 6, wherein said cost information includes base costs, ongoing direct costs and ongoing indirect costs.
8. The method of claim 7, wherein the base costs include design costs, acquisition costs, and installation costs.
9. The method of claim 7, wherein the ongoing direct costs include production control costs, momtonng costs, secunty management and failure control costs, changes m upgrade costs, support costs, and operational costs.
10. The method of claim 7, wherein the ongoing indirect costs include end-user costs and downtime costs.
11. The method of claim 6, wherein said system charactenstics include financial charactenstics, operating and efficiency characteristics, and infrastmcture and evolution characteristics.
12. The method of claim 6, wherein said appraisal metrics include financial perspective metncs, operate effectively and efficiently metncs, and infrastmcture and evolution perspective metncs.
13. The method of claim 12, wherein said financial perspective metncs are based on said financial charactenstics and said cost information
14. The method of claim 13, wherein said appraisal metrics and said cost information correspond to a plurality of information technology function categones.
15. The method of claim 14, wherein said cost information and said appraisal metrics are reported according to said categones.
16. The method of claim 14, wherein said metrics are used to determine cost improvement opportunities through best practices implementation for said category.
PCT/US2000/027518 1999-10-06 2000-10-06 Method for determining total cost of ownership WO2001026005A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
AU78618/00A AU7861800A (en) 1999-10-06 2000-10-06 Method for determining total cost of ownership

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
US15825999P 1999-10-06 1999-10-06
US60/158,259 1999-10-06

Publications (1)

Publication Number Publication Date
WO2001026005A1 true WO2001026005A1 (en) 2001-04-12

Family

ID=22567316

Family Applications (12)

Application Number Title Priority Date Filing Date
PCT/US2000/027803 WO2001026013A1 (en) 1999-10-06 2000-10-06 Method and estimator for providing service level management
PCT/US2000/027629 WO2001026008A1 (en) 1999-10-06 2000-10-06 Method and estimator for event/fault monitoring
PCT/US2000/027796 WO2001026010A1 (en) 1999-10-06 2000-10-06 Method and estimator for production scheduling
PCT/US2000/027593 WO2001026028A1 (en) 1999-10-06 2000-10-06 Method and estimator for providing change control
PCT/US2000/027592 WO2001026007A1 (en) 1999-10-06 2000-10-06 Method and estimator for providing business recovery planning
PCT/US2000/027518 WO2001026005A1 (en) 1999-10-06 2000-10-06 Method for determining total cost of ownership
PCT/US2000/027857 WO2001025877A2 (en) 1999-10-06 2000-10-06 Organization of information technology functions
PCT/US2000/027802 WO2001026012A1 (en) 1999-10-06 2000-10-06 Method and estimator for providing storage management
PCT/US2000/027801 WO2001026011A1 (en) 1999-10-06 2000-10-06 Method and estimator for providing operation management strategic planning
PCT/US2000/027856 WO2001025970A1 (en) 1999-10-06 2000-10-06 Method and estimator for providing operations maturity model assessment
PCT/US2000/027795 WO2001025876A2 (en) 1999-10-06 2000-10-06 Method and estimator for providing capacity modeling and planning
PCT/US2000/027804 WO2001026014A1 (en) 1999-10-06 2000-10-06 Method and estimator for providing service control

Family Applications Before (5)

Application Number Title Priority Date Filing Date
PCT/US2000/027803 WO2001026013A1 (en) 1999-10-06 2000-10-06 Method and estimator for providing service level management
PCT/US2000/027629 WO2001026008A1 (en) 1999-10-06 2000-10-06 Method and estimator for event/fault monitoring
PCT/US2000/027796 WO2001026010A1 (en) 1999-10-06 2000-10-06 Method and estimator for production scheduling
PCT/US2000/027593 WO2001026028A1 (en) 1999-10-06 2000-10-06 Method and estimator for providing change control
PCT/US2000/027592 WO2001026007A1 (en) 1999-10-06 2000-10-06 Method and estimator for providing business recovery planning

Family Applications After (6)

Application Number Title Priority Date Filing Date
PCT/US2000/027857 WO2001025877A2 (en) 1999-10-06 2000-10-06 Organization of information technology functions
PCT/US2000/027802 WO2001026012A1 (en) 1999-10-06 2000-10-06 Method and estimator for providing storage management
PCT/US2000/027801 WO2001026011A1 (en) 1999-10-06 2000-10-06 Method and estimator for providing operation management strategic planning
PCT/US2000/027856 WO2001025970A1 (en) 1999-10-06 2000-10-06 Method and estimator for providing operations maturity model assessment
PCT/US2000/027795 WO2001025876A2 (en) 1999-10-06 2000-10-06 Method and estimator for providing capacity modeling and planning
PCT/US2000/027804 WO2001026014A1 (en) 1999-10-06 2000-10-06 Method and estimator for providing service control

Country Status (4)

Country Link
EP (2) EP1226523A4 (en)
AU (12) AU7996100A (en)
CA (1) CA2386788A1 (en)
WO (12) WO2001026013A1 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP1959325A2 (en) 2003-07-10 2008-08-20 Daimler AG Method and device for reducing failure frequency
US8572003B2 (en) * 2003-07-18 2013-10-29 Sap Ag Standardized computer system total cost of ownership assessments and benchmarking

Families Citing this family (37)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2002048935A1 (en) * 2000-12-11 2002-06-20 Skill Development Associates Ltd Integrated business management system
US7937281B2 (en) 2001-12-07 2011-05-03 Accenture Global Services Limited Accelerated process improvement framework
US7035809B2 (en) * 2001-12-07 2006-04-25 Accenture Global Services Gmbh Accelerated process improvement framework
WO2004040409A2 (en) 2002-10-25 2004-05-13 Science Applications International Corporation Determining performance level capabilities using predetermined model criteria
US8566147B2 (en) * 2005-10-25 2013-10-22 International Business Machines Corporation Determining the progress of adoption and alignment of information technology capabilities and on-demand capabilities by an organization
EP1808803A1 (en) * 2005-12-15 2007-07-18 International Business Machines Corporation System and method for automatically selecting one or more metrics for performing a CMMI evaluation
US8457297B2 (en) 2005-12-30 2013-06-04 Aspect Software, Inc. Distributing transactions among transaction processing systems
US8355938B2 (en) 2006-01-05 2013-01-15 Wells Fargo Bank, N.A. Capacity management index system and method
US7523082B2 (en) * 2006-05-08 2009-04-21 Aspect Software Inc Escalating online expert help
WO2008105825A1 (en) * 2007-02-26 2008-09-04 Unisys Corporation A method for multi-sourcing technology based services
US20100312612A1 (en) * 2007-10-25 2010-12-09 Hugh Carr Modification of service delivery infrastructure in communication networks
US8326660B2 (en) 2008-01-07 2012-12-04 International Business Machines Corporation Automated derivation of response time service level objectives
US8320246B2 (en) * 2009-02-19 2012-11-27 Bridgewater Systems Corp. Adaptive window size for network fair usage controls
US8200188B2 (en) * 2009-02-20 2012-06-12 Bridgewater Systems Corp. System and method for adaptive fair usage controls in wireless networks
US9203629B2 (en) 2009-05-04 2015-12-01 Bridgewater Systems Corp. System and methods for user-centric mobile device-based data communications cost monitoring and control
US8577329B2 (en) 2009-05-04 2013-11-05 Bridgewater Systems Corp. System and methods for carrier-centric mobile device data communications cost monitoring and control
US20110066476A1 (en) * 2009-09-15 2011-03-17 Joseph Fernard Lewis Business management assessment and consulting assistance system and associated method
US20110231229A1 (en) * 2010-03-22 2011-09-22 Computer Associates Think, Inc. Hybrid Software Component and Service Catalog
CN103154978B (en) 2010-10-27 2018-03-30 慧与发展有限责任合伙企业 For dispatching the system and method changed
US11172022B2 (en) 2014-02-21 2021-11-09 Hewlett Packard Enterprise Development Lp Migrating cloud resources
US10148757B2 (en) 2014-02-21 2018-12-04 Hewlett Packard Enterprise Development Lp Migrating cloud resources
WO2015153988A1 (en) * 2014-04-03 2015-10-08 Greater Brain Group, Inc. Systems and methods for increasing capability of systems of businesses or other entities through maturity evolution
US10044786B2 (en) 2014-11-16 2018-08-07 International Business Machines Corporation Predicting performance by analytically solving a queueing network model
US9984044B2 (en) 2014-11-16 2018-05-29 International Business Machines Corporation Predicting performance regression of a computer system with a complex queuing network model
US10460272B2 (en) * 2016-02-25 2019-10-29 Accenture Global Solutions Limited Client services reporting
CN106682385B (en) * 2016-09-30 2020-02-11 广州英康唯尔互联网服务有限公司 Health information interaction system
MX2020010922A (en) * 2018-04-16 2021-01-08 Cloudblue Llc System and method for matching revenue streams in a cloud service broker platform.
US11481711B2 (en) 2018-06-01 2022-10-25 Walmart Apollo, Llc System and method for modifying capacity for new facilities
WO2019232411A1 (en) 2018-06-01 2019-12-05 Walmart Apollo, Llc Automated slot adjustment tool
US11483350B2 (en) 2019-03-29 2022-10-25 Amazon Technologies, Inc. Intent-based governance service
CN110096423A (en) * 2019-05-14 2019-08-06 深圳供电局有限公司 A kind of server memory capacity analyzing and predicting method based on big data analysis
US11119877B2 (en) 2019-09-16 2021-09-14 Dell Products L.P. Component life cycle test categorization and optimization
MX2022005750A (en) * 2019-11-11 2022-08-17 Snapit Solutions Llc System for producing and delivering information technology products and services.
US11288150B2 (en) 2019-11-18 2022-03-29 Sungard Availability Services, Lp Recovery maturity index (RMI)-based control of disaster recovery
US20210160143A1 (en) 2019-11-27 2021-05-27 Vmware, Inc. Information technology (it) toplogy solutions according to operational goals
US11501237B2 (en) 2020-08-04 2022-11-15 International Business Machines Corporation Optimized estimates for support characteristics for operational systems
US11329896B1 (en) 2021-02-11 2022-05-10 Kyndryl, Inc. Cognitive data protection and disaster recovery policy management

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0652518A1 (en) * 1993-11-04 1995-05-10 Microsoft Corporation Operating system based performance monitoring of programs
JPH08320855A (en) * 1995-05-24 1996-12-03 Hitachi Ltd Method and system for evaluating system introduction effect
US5745880A (en) * 1994-10-03 1998-04-28 The Sabre Group, Inc. System to predict optimum computer platform
US5771179A (en) * 1991-12-13 1998-06-23 White; Leonard R. Measurement analysis software system and method
US5793632A (en) * 1996-03-26 1998-08-11 Lockheed Martin Corporation Cost estimating system using parametric estimating and providing a split of labor and material costs
US5960417A (en) * 1996-03-19 1999-09-28 Vanguard International Semiconductor Corporation IC manufacturing costing control system and process
US6157916A (en) * 1998-06-17 2000-12-05 The Hoffman Group Method and apparatus to control the operating speed of a papermaking facility

Family Cites Families (28)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4827423A (en) * 1987-01-20 1989-05-02 R. J. Reynolds Tobacco Company Computer integrated manufacturing system
JPH03111969A (en) * 1989-09-27 1991-05-13 Hitachi Ltd Method for supporting plan formation
US5233513A (en) * 1989-12-28 1993-08-03 Doyle William P Business modeling, software engineering and prototyping method and apparatus
US5701419A (en) * 1992-03-06 1997-12-23 Bell Atlantic Network Services, Inc. Telecommunications service creation apparatus and method
US5586021A (en) * 1992-03-24 1996-12-17 Texas Instruments Incorporated Method and system for production planning
US5646049A (en) * 1992-03-27 1997-07-08 Abbott Laboratories Scheduling operation of an automated analytical system
US5978811A (en) * 1992-07-29 1999-11-02 Texas Instruments Incorporated Information repository system and method for modeling data
US5630069A (en) * 1993-01-15 1997-05-13 Action Technologies, Inc. Method and apparatus for creating workflow maps of business processes
US5819270A (en) * 1993-02-25 1998-10-06 Massachusetts Institute Of Technology Computer system for displaying representations of processes
CA2118885C (en) * 1993-04-29 2005-05-24 Conrad K. Teran Process control system
AU7207194A (en) * 1993-06-16 1995-01-03 Electronic Data Systems Corporation Process management system
US5724262A (en) * 1994-05-31 1998-03-03 Paradyne Corporation Method for measuring the usability of a system and for task analysis and re-engineering
US5563951A (en) * 1994-07-25 1996-10-08 Interval Research Corporation Audio interface garment and communication system for use therewith
JP3315844B2 (en) * 1994-12-09 2002-08-19 株式会社東芝 Scheduling device and scheduling method
EP0770967A3 (en) * 1995-10-26 1998-12-30 Koninklijke Philips Electronics N.V. Decision support system for the management of an agile supply chain
US5875431A (en) * 1996-03-15 1999-02-23 Heckman; Frank Legal strategic analysis planning and evaluation control system and method
US5960200A (en) * 1996-05-03 1999-09-28 I-Cube System to transition an enterprise to a distributed infrastructure
US5673382A (en) * 1996-05-30 1997-09-30 International Business Machines Corporation Automated management of off-site storage volumes for disaster recovery
US5864483A (en) * 1996-08-01 1999-01-26 Electronic Data Systems Corporation Monitoring of service delivery or product manufacturing
US5974395A (en) * 1996-08-21 1999-10-26 I2 Technologies, Inc. System and method for extended enterprise planning across a supply chain
US5930762A (en) * 1996-09-24 1999-07-27 Rco Software Limited Computer aided risk management in multiple-parameter physical systems
US6044354A (en) * 1996-12-19 2000-03-28 Sprint Communications Company, L.P. Computer-based product planning system
US5903478A (en) * 1997-03-10 1999-05-11 Ncr Corporation Method for displaying an IT (Information Technology) architecture visual model in a symbol-based decision rational table
US6028602A (en) * 1997-05-30 2000-02-22 Telefonaktiebolaget Lm Ericsson Method for managing contents of a hierarchical data model
US6106569A (en) * 1997-08-14 2000-08-22 International Business Machines Corporation Method of developing a software system using object oriented technology
US6092047A (en) * 1997-10-07 2000-07-18 Benefits Technologies, Inc. Apparatus and method of composing a plan of flexible benefits
US6131099A (en) * 1997-11-03 2000-10-10 Moore U.S.A. Inc. Print and mail business recovery configuration method and system
US6119097A (en) * 1997-11-26 2000-09-12 Executing The Numbers, Inc. System and method for quantification of human performance factors

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5771179A (en) * 1991-12-13 1998-06-23 White; Leonard R. Measurement analysis software system and method
EP0652518A1 (en) * 1993-11-04 1995-05-10 Microsoft Corporation Operating system based performance monitoring of programs
JPH07182209A (en) * 1993-11-04 1995-07-21 Microsoft Corp Method and system for monitoring of performance of operating system-based program
US5485574A (en) * 1993-11-04 1996-01-16 Microsoft Corporation Operating system based performance monitoring of programs
US5745880A (en) * 1994-10-03 1998-04-28 The Sabre Group, Inc. System to predict optimum computer platform
JPH08320855A (en) * 1995-05-24 1996-12-03 Hitachi Ltd Method and system for evaluating system introduction effect
US5960417A (en) * 1996-03-19 1999-09-28 Vanguard International Semiconductor Corporation IC manufacturing costing control system and process
US5793632A (en) * 1996-03-26 1998-08-11 Lockheed Martin Corporation Cost estimating system using parametric estimating and providing a split of labor and material costs
US6157916A (en) * 1998-06-17 2000-12-05 The Hoffman Group Method and apparatus to control the operating speed of a papermaking facility

Non-Patent Citations (4)

* Cited by examiner, † Cited by third party
Title
COMMUNICATIONS OF THE ACM, vol. 29, no. 3, March 1986 (1986-03-01), pages 212 - 217 *
DATABASE INSPEC [online] SIRCAR ET AL.: "The relationship between benchmark tests and microcomputer price", XP002935927, Database accession no. 02660085 *
DATABASE INSPEC [online] TAKAHASHI: "Network planning for transportation business", XP002935926, Database accession no. 4481017 *
JOURNAL OF THE INSTITUTE OF ELECTRONICS, INFORMATION AND COMMUNICATIONS ENGINEERS, vol. 76, no. 2, February 1993 (1993-02-01), pages 126 - 128 *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP1959325A2 (en) 2003-07-10 2008-08-20 Daimler AG Method and device for reducing failure frequency
US7627452B2 (en) 2003-07-10 2009-12-01 Daimler Ag Method and device for predicting a failure frequency
US8572003B2 (en) * 2003-07-18 2013-10-29 Sap Ag Standardized computer system total cost of ownership assessments and benchmarking

Also Published As

Publication number Publication date
WO2001026010A1 (en) 2001-04-12
WO2001025877A2 (en) 2001-04-12
AU1431701A (en) 2001-05-10
AU1193601A (en) 2001-05-10
WO2001025876A2 (en) 2001-04-12
WO2001026008A1 (en) 2001-04-12
WO2001025877A3 (en) 2001-09-07
AU1193801A (en) 2001-05-10
WO2001026011A1 (en) 2001-04-12
AU8001800A (en) 2001-05-10
WO2001026014A1 (en) 2001-04-12
AU7756600A (en) 2001-05-10
AU1653901A (en) 2001-05-10
AU7996000A (en) 2001-05-10
CA2386788A1 (en) 2001-04-12
EP1226523A1 (en) 2002-07-31
WO2001026028A8 (en) 2001-07-26
AU7866600A (en) 2001-05-10
WO2001025876A3 (en) 2001-08-30
AU8001700A (en) 2001-05-10
WO2001025970A1 (en) 2001-04-12
AU7861800A (en) 2001-05-10
EP1222510A2 (en) 2002-07-17
WO2001026007A1 (en) 2001-04-12
WO2001026012A1 (en) 2001-04-12
WO2001026013A1 (en) 2001-04-12
EP1226523A4 (en) 2003-02-19
WO2001026028A1 (en) 2001-04-12
EP1222510A4 (en) 2007-10-31
WO2001025970A8 (en) 2001-09-27
AU1431801A (en) 2001-05-10
AU7996100A (en) 2001-05-10

Similar Documents

Publication Publication Date Title
US7020621B1 (en) Method for determining total cost of ownership
WO2001026005A1 (en) Method for determining total cost of ownership
US8886551B2 (en) Centralized job scheduling maturity model
US6738736B1 (en) Method and estimator for providing capacacity modeling and planning
US7707015B2 (en) Methods for capacity management
US8856646B2 (en) Asset transition project management
US10380079B1 (en) Information technology configuration management
US8589196B2 (en) Knowledge management system
US7752437B1 (en) Classification of data in data flows in a data storage infrastructure for a communication network
US7865380B2 (en) Automated information technology management system
US20100274616A1 (en) Incident communication interface for the knowledge management system
US7480734B1 (en) Class of service analysis for data flows in a data storage infrastructure for a communication network
US20040088411A1 (en) Method and system for vendor management
US20100274814A1 (en) Academy for the knowledge management system
US8595051B2 (en) Metrics capability self assessment
US20060112317A1 (en) Method and system for managing information technology systems
US8510429B1 (en) Inventory modeling in a data storage infrastructure for a communication network
US7788302B1 (en) Interactive display of a data storage infrastructure for a communication network
US7801973B1 (en) Classification of information in data flows in a data storage infrastructure for a communication network
US7895295B1 (en) Scoring data flow characteristics to assign data flows to storage systems in a data storage infrastructure for a communication network
US7797395B1 (en) Assignment of data flows to storage systems in a data storage infrastructure for a communication network
Davis Systems analysis for data communications networks at an electric utility
Parker et al. A fool with a tool is still a fool
Sujatmiko OPTIMIZATION OF IT SERVICE DESK RESOURCE ALLOCATION IN AN OIL AND GAS COMPANY (PT. X) USING WORKLOAD ANALYSIS METHOD
Welgama AN EMPIRICAL MODEL TO ESTIMATE ITSERVICE OUTAGE COSTS

Legal Events

Date Code Title Description
AK Designated states

Kind code of ref document: A1

Designated state(s): AE AG AL AM AT AU AZ BA BB BG BR BY BZ CA CH CN CR CU CZ DE DK DM DZ EE ES FI GB GD GE GH GM HR HU ID IL IN IS JP KE KG KP KR KZ LC LK LR LS LT LU LV MA MD MG MK MN MW MX MZ NO NZ PL PT RO RU SD SE SG SI SK SL TJ TM TR TT TZ UA UG UZ VN YU ZA ZW

AL Designated countries for regional patents

Kind code of ref document: A1

Designated state(s): GH GM KE LS MW MZ SD SL SZ TZ UG ZW AM AZ BY KG KZ MD RU TJ TM AT BE CH CY DE DK ES FI FR GB GR IE IT LU MC NL PT SE BF BJ CF CG CI CM GA GN GW ML MR NE SN TD TG

121 Ep: the epo has been informed by wipo that ep was designated in this application
DFPE Request for preliminary examination filed prior to expiration of 19th month from priority date (pct application filed before 20040101)
REG Reference to national code

Ref country code: DE

Ref legal event code: 8642

122 Ep: pct application non-entry in european phase
NENP Non-entry into the national phase

Ref country code: JP