WO2006075863A1 - Long-span temporary bridge using cross beam having through-holes - Google Patents

Long-span temporary bridge using cross beam having through-holes Download PDF

Info

Publication number
WO2006075863A1
WO2006075863A1 PCT/KR2006/000103 KR2006000103W WO2006075863A1 WO 2006075863 A1 WO2006075863 A1 WO 2006075863A1 KR 2006000103 W KR2006000103 W KR 2006000103W WO 2006075863 A1 WO2006075863 A1 WO 2006075863A1
Authority
WO
WIPO (PCT)
Prior art keywords
cross beam
main beams
cross
long
holes
Prior art date
Application number
PCT/KR2006/000103
Other languages
French (fr)
Inventor
Sung Kim
Original Assignee
Leton Bridge Co., Ltd.
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Leton Bridge Co., Ltd. filed Critical Leton Bridge Co., Ltd.
Publication of WO2006075863A1 publication Critical patent/WO2006075863A1/en

Links

Classifications

    • GPHYSICS
    • G10MUSICAL INSTRUMENTS; ACOUSTICS
    • G10KSOUND-PRODUCING DEVICES; METHODS OR DEVICES FOR PROTECTING AGAINST, OR FOR DAMPING, NOISE OR OTHER ACOUSTIC WAVES IN GENERAL; ACOUSTICS NOT OTHERWISE PROVIDED FOR
    • G10K1/00Devices in which sound is produced by striking a resonating body, e.g. bells, chimes or gongs
    • G10K1/06Devices in which sound is produced by striking a resonating body, e.g. bells, chimes or gongs the resonating devices having the shape of a bell, plate, rod, or tube
    • G10K1/08Details or accessories of general applicability
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2/00Bridges characterised by the cross-section of their bearing spanning structure
    • E01D2/02Bridges characterised by the cross-section of their bearing spanning structure of the I-girder type
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2101/00Material constitution of bridges
    • E01D2101/30Metal
    • E01D2101/32Metal prestressed

Definitions

  • the present invention relates to a temporary bridge, and more particularly, to a long-span temporary bridge using cross beams having through-holes, in which tension members are connected between cross beams having a plurality of through-holes to apply prestress and to reduce positive moment such that a span can widen.
  • a temporary bridge is installed and used for various purposes such as ensuring of a detour upon road repairing, detour crossing of vehicles upon bridge repairing, building of a pedestrian bridge on a busy road, or building of a work bridge in port facilities.
  • a conventional temporary bridge uses an I-beam and a deck plate and has a short span and a complicated shape, a construction cost and a construction period excessively increase and thus construction performance significantly deteriorates.
  • a float material may be caught on a short-span temporary bridge so that the river overflows or the bridge may upset due to a lateral load having a high flow rate. Accordingly, there is a need for installing a long-span temporary bridge.
  • the above-mentioned constructing method can increase the span up to about 30 meters. However, since this span includes the widths of the bridge posts, the span is actually about 28 meters. If the span is greater than 28 meters, the temporary bridge is structurally dangerous.
  • the temporary bridge is used for various purposes such as a detour bridge, a construction bridge, or a permanent bridge
  • the length and the width of the temporary bridge become longer and the use period of the temporary bridge becomes longer. Accordingly, a method of constructing a structurally stable temporary bridge while addressing the problems of the conventional long-span temporary bridge and ensuring the longer span is increasingly required.
  • the present invention is contrived to solve the above-mentioned problems, and an object of the present invention is to provide a long-span temporary bridge using cross beams having through-holes, in which cross beams having a plurality of through-holes are installed and tension members are connected through the through-holes such that a long span can be realized using the plurality of tension members.
  • Another object of the present invention is to provide a long-span temporary bridge using cross beams having through-holes, in which tension members are installed at positions corresponding to the main beams as well as portions between main beams such that a force is distributed to prevent the force from being concentrated on the main beams.
  • a long-span temporary bridge having a plurality of bridge posts, a plurality of main beams installed on the bridge posts, and a plurality of deck plates installed on the main beams, including: a first cross beam which is installed on the lower surfaces of the plurality of main beams between the bridge posts to cross the plurality of main beams and has a plurality of through-holes formed therein; a second cross beam which is installed on the lower surfaces of the plurality of main beams to cross the plurality of main beams and to be spaced apart from the first cross beam and has a plurality of through-holes formed therein; a plurality of tension members which is connected between the first cross beam and the second cross beam and of which the both ends pass through the through-holes formed in the first cross beam and the second cross beam and are protruded from the first cross beam and the second cross beam; and a plurality of fixing members which is installed at one sides of the first cross beam and the second cross beam to fix the both
  • the long-span temporary bridge may further include a third cross beam which is installed on the lower surfaces of the main beams at an intermediate portion between the first cross beam and the second cross beam to cross the plurality of main beams, and saddles which are installed on the lower surface of the third cross beam and in which the tensions member are positioned.
  • the number of the through-holes formed in the first cross beam and the second cross beam at positions between the main beams may be at least one.
  • the through-holes may be formed in the first and second cross beams at position corresponding to the main beams.
  • the long-span temporary bridge may further include a reinforcement frame attached to one sides of the first cross beam and the second cross beam and the lower surfaces of the main beams.
  • connection slabs The both ends of the main beams may be seated on connection slabs.
  • FlG. 1 is a front view of a long-span temporary bridge using cross beams having through-holes according to the present invention
  • FlG. 2 is a lateral cross-sectional view taken along line A-A of FlG. 1 according to a first embodiment of the present invention
  • FlG. 3 is a lateral cross-sectional view taken along line B-B of FlG. 1 according to the first embodiment of the present invention
  • FlG. 4 is a plan view of the long-span temporary bridge illustrated in FlG. 1 according to the first embodiment of the present invention
  • FlG. 5 is a lateral cross-sectional view taken along line A-A of FlG. 1 according to a second embodiment of the present invention
  • FlG. 6 is a lateral cross-sectional view taken along line B-B of FlG. 1 according to the second embodiment of the present invention
  • FlG. 7 is a plan view of the long-span temporary bridge illustrated in FlG. 1 according to the second embodiment of the present invention.
  • FlG. 8 is a partially enlarged front view illustrating the structure of a fixing member
  • FlG. 9 is a partially enlarged lateral cross-sectional view illustrating the structure of the fixing member.
  • FlG. 10 is a partial enlarged front view illustrating a structure in which a reinforcement frame is attached to one side of the cross beam and the lower surface of a main beam.
  • FIG. 1 is a front view of a long-span temporary bridge using cross beam having through-holes according to the present invention.
  • a cable-stayed girder bridge type long-span bridge according to the present invention includes bridge posts 1, main beams 2, deck plates 3, first through third cross beams 4-1 through 4-3, saddles 5, fixing members 6, and connection slabs 8.
  • Each bridge post 1 is a steel material in which a plurality of H-beams is installed and is installed on the surface of land.
  • the main beams 2 are installed on the bridge posts 1.
  • a plurality of deck plates 3 made of a steel material is installed on the main beams 2.
  • the first cross beam 4-1 is installed on the lower surfaces of the plurality of main beams 2 between the bridge posts 1 to cross the plurality of main beams 2.
  • the first cross beam 4-2 is installed on the lower surfaces of the plurality of main beams 2 to cross the plurality of main beams 2 and to be spaced apart from the first cross beam 4-1 at a predetermined distance. Furthermore, a plurality of through-holes
  • the fixing members 6 for fixing tension members 7 are installed at the outsides of the first cross beam 4-1 and the second cross beam 4-2.
  • the third cross beam 4-3 is installed on the lower surfaces of the main beams 2 at an intermediate portion between the first cross beam 4-1 and the second cross beam
  • the saddles 5 are installed on the lower surface of the third cross beam 4-3.
  • the first through third cross beams 4-1 through 4-3 are installed on the lower surfaces of the plurality of main beams 2 to prevent the temporary bridge from sagging. Furthermore, by inserting the plurality of tension members 7, it is possible to reduce positive moment applied to the span of the temporary bridge.
  • the tension members 7 are connected between the first cross beam 4-1 and the second cross beam 4-2 across the saddles 5 installed on the lower surface of the third cross beam 4-3 and are fixed by the fixing members 6.
  • the tension members 7 are sloped downward from the first and second cross beams 4-1 and 4-2 to the third cross beam 4-3.
  • an upward load is applied to the saddles 5 and the third cross beam 4-3 such that a sagging phenomenon can be efficiently removed.
  • FlG. 2 is a lateral cross-sectional view taken along line A-A of FlG. 1 according to a first embodiment of the present invention
  • FlG. 3 is a lateral cross-sectional view taken along line B-B of FlG. 1 according to the first embodiment of the present invention
  • FlG. 4 is a plan view of the long-span temporary bridge illustrated in FlG. 1 according to the first embodiment of the present invention.
  • the tension members 7 are connected between the first cross beam 4-1 and the second cross beam 4-2 at positions between the main beams 2.
  • the through-holes are formed in the first cross beam
  • the saddles 5 are attached to the lower surface of the third cross beam 4-3 at positions corresponding to the through-holes of the first cross beam 4-1 and the second cross beam 4-2.
  • one through-hole is formed at the position between the main beams 2
  • the present invention is not limited to this embodiment. At least two through-holes may be formed at the positions between the main beams 2 and a plurality of tension members may be installed in correspondence with the through- holes. Thus, it is possible to realize a long span of 30 m by applying more prestress and to uniformly distribute a force.
  • FlG. 5 is a lateral cross-sectional view taken along line A-A of FlG. 1 according to a second embodiment of the present invention
  • FlG. 6 is a lateral cross-sectional view taken along line B-B of FlG. 1 according to the second embodiment of the present invention
  • FlG. 7 is a plan view of the long-span temporary bridge illustrated in FlG. 1 according to the second embodiment of the present invention.
  • the tension members 7 are connected between the first cross beam 4-1 and the second cross beam 4-2 at positions between the main beams 2 and positions corresponding to the main beams 2.
  • the through-holes are formed in the first cross beam
  • the saddles 5 are attached to the lower surface of the third cross beam 4-3 at positions corresponding to the through-holes of the first cross beam 4-1 and the second cross beam 4-2.
  • one through-hole is formed at the position between the main beams 2
  • the present invention is not limited to this embodiment.
  • At least two through-holes may be formed at the position between the main beams 2 and a plurality of tension members may be installed in correspondence with the through- holes.
  • more tension members can be installed, it is possible to realize a long span and to uniformly distribute a force by applying more prestress.
  • FlG. 8 is a partially enlarged front view illustrating the structure of the fixing member 6
  • FlG. 9 is a partially enlarged lateral cross-sectional view illustrating the structure of the fixing member.
  • the fixing member 6 is installed at the outside of the cross beam 4-1 to fix the tension member 7 passing through the through-hole of the cross beam 4-1 using a bolt or the like.
  • the tension member 7 is installed to be slightly sloped inward, the fixing member 6 is also installed to be slightly sloped.
  • FlG. 10 is a partial enlarged front view illustrating a structure in which a reinforcement frame 9 is attached to one side of the cross beam 4-1 and the lower surface of the main beam 2.
  • the reinforcement frame 9 is attached to the inside of the cross beam 4-1 and the lower surface of the cross beam 2 using a fastening member 10 such as a bolt to distribute forces applied to both the cross beams 4-1 and 4-2 by the tension forces of the plurality of tension members 7, thereby realizing a more stable support structure.
  • a fastening member 10 such as a bolt
  • a long-span temporary bridge using cross beams having through-holes can apply to a temporary support for installing a bridge slab or a structure having a long-span bridge function as well as a simple temporary bridge.

Abstract

Provided is a long-span temporary bridge having a plurality of bridge posts, a plurality of main beams installed on the bridge posts, a plurality of deck plates installed on the main beams, cross beams having through-holes and tension members are connected through the through-holes such that a long span can be realized using the plurality of tension members.

Description

Description
LONG-SPAN TEMPORARY BRIDGE USING CROSS BEAM
HAVING THROUGH-HOLES
Technical Field
[1] The present invention relates to a temporary bridge, and more particularly, to a long-span temporary bridge using cross beams having through-holes, in which tension members are connected between cross beams having a plurality of through-holes to apply prestress and to reduce positive moment such that a span can widen. Background Art
[2] A temporary bridge is installed and used for various purposes such as ensuring of a detour upon road repairing, detour crossing of vehicles upon bridge repairing, building of a pedestrian bridge on a busy road, or building of a work bridge in port facilities.
[3] Since a conventional temporary bridge uses an I-beam and a deck plate and has a short span and a complicated shape, a construction cost and a construction period excessively increase and thus construction performance significantly deteriorates. In addition, in the rainy season, a float material may be caught on a short-span temporary bridge so that the river overflows or the bridge may upset due to a lateral load having a high flow rate. Accordingly, there is a need for installing a long-span temporary bridge.
Disclosure of Invention Technical Problem
[4] Up to Now, several constructing methods for realizing a long span have been suggested. Among them, a constructing method of attaching vertical and horizontal reinforcement members to an H-beam and attaching a deviator to the center of the lower surface of the H-beam, installing a fixing member on the both ends of the deviator, and applying prestress using a high-strength steel rod is widely being used.
[5] By structural computation, the above-mentioned constructing method can increase the span up to about 30 meters. However, since this span includes the widths of the bridge posts, the span is actually about 28 meters. If the span is greater than 28 meters, the temporary bridge is structurally dangerous.
[6] In addition, in this constructing method, since the high-strength steel rod is installed on the lower surface of the H-beam, a force is concentrated on a main beam.
[7] Recently, as the temporary bridge is used for various purposes such as a detour bridge, a construction bridge, or a permanent bridge, the length and the width of the temporary bridge become longer and the use period of the temporary bridge becomes longer. Accordingly, a method of constructing a structurally stable temporary bridge while addressing the problems of the conventional long-span temporary bridge and ensuring the longer span is increasingly required.
Technical Solution
[8] The present invention is contrived to solve the above-mentioned problems, and an object of the present invention is to provide a long-span temporary bridge using cross beams having through-holes, in which cross beams having a plurality of through-holes are installed and tension members are connected through the through-holes such that a long span can be realized using the plurality of tension members.
[9] Another object of the present invention is to provide a long-span temporary bridge using cross beams having through-holes, in which tension members are installed at positions corresponding to the main beams as well as portions between main beams such that a force is distributed to prevent the force from being concentrated on the main beams.
[10] According to an aspect of the present invention, there is provided a long-span temporary bridge having a plurality of bridge posts, a plurality of main beams installed on the bridge posts, and a plurality of deck plates installed on the main beams, including: a first cross beam which is installed on the lower surfaces of the plurality of main beams between the bridge posts to cross the plurality of main beams and has a plurality of through-holes formed therein; a second cross beam which is installed on the lower surfaces of the plurality of main beams to cross the plurality of main beams and to be spaced apart from the first cross beam and has a plurality of through-holes formed therein; a plurality of tension members which is connected between the first cross beam and the second cross beam and of which the both ends pass through the through-holes formed in the first cross beam and the second cross beam and are protruded from the first cross beam and the second cross beam; and a plurality of fixing members which is installed at one sides of the first cross beam and the second cross beam to fix the both ends of the tension members.
[11] The long-span temporary bridge may further include a third cross beam which is installed on the lower surfaces of the main beams at an intermediate portion between the first cross beam and the second cross beam to cross the plurality of main beams, and saddles which are installed on the lower surface of the third cross beam and in which the tensions member are positioned.
[12] The number of the through-holes formed in the first cross beam and the second cross beam at positions between the main beams may be at least one.
[13] The through-holes may be formed in the first and second cross beams at position corresponding to the main beams.
[14] The long-span temporary bridge may further include a reinforcement frame attached to one sides of the first cross beam and the second cross beam and the lower surfaces of the main beams.
[15] The both ends of the main beams may be seated on connection slabs.
Advantageous Effects
[16] According to the present invention, it is posssible to provide a long-span temporary bridge using cross beams having through-holes, in which cross beams having a plurality of through-holes are installed and tension members are connected through the through-holes such that a long span can be realized using the plurality of tension members.
[17] In addition, it is possible to provide a long-span temporary bridge using cross beams having through-holes, in which tension members are installed at positions corresponding to the main beams as well as portions between main beams such that a force is distributed to prevent the force from being concentrated on the main beams. Brief Description of the Drawings
[18] The above and other features and advantages of the present invention will become more apparent by describing in detail exemplary embodiments thereof with reference to the attached drawings in which:
[19] FlG. 1 is a front view of a long-span temporary bridge using cross beams having through-holes according to the present invention;
[20] FlG. 2 is a lateral cross-sectional view taken along line A-A of FlG. 1 according to a first embodiment of the present invention;
[21] FlG. 3 is a lateral cross-sectional view taken along line B-B of FlG. 1 according to the first embodiment of the present invention;
[22] FlG. 4 is a plan view of the long-span temporary bridge illustrated in FlG. 1 according to the first embodiment of the present invention;
[23] FlG. 5 is a lateral cross-sectional view taken along line A-A of FlG. 1 according to a second embodiment of the present invention;
[24] FlG. 6 is a lateral cross-sectional view taken along line B-B of FlG. 1 according to the second embodiment of the present invention;
[25] FlG. 7 is a plan view of the long-span temporary bridge illustrated in FlG. 1 according to the second embodiment of the present invention;
[26] FlG. 8 is a partially enlarged front view illustrating the structure of a fixing member;
[27] FlG. 9 is a partially enlarged lateral cross-sectional view illustrating the structure of the fixing member; and
[28] FlG. 10 is a partial enlarged front view illustrating a structure in which a reinforcement frame is attached to one side of the cross beam and the lower surface of a main beam.
[29] <Reference Numerals>
[30] 1 : Bridge post 2: Main beam
[31] 3: Deck plate 4: Cross beam
[32] 5: Saddle 6: Fixing member
[33] 7: Tension member 8: Connection slab
[34] 9: Reinforcement frame 10: Reinforcement plate
Best Mode for Carrying Out the Invention [35] Hereinafter, exemplary embodiments of the present invention will be described in detail with reference to the attached drawings such that the present invention can be easily put into practice by those skilled in the art. [36] FIG. 1 is a front view of a long-span temporary bridge using cross beam having through-holes according to the present invention. [37] A cable-stayed girder bridge type long-span bridge according to the present invention includes bridge posts 1, main beams 2, deck plates 3, first through third cross beams 4-1 through 4-3, saddles 5, fixing members 6, and connection slabs 8. [38] Each bridge post 1 is a steel material in which a plurality of H-beams is installed and is installed on the surface of land. The main beams 2 are installed on the bridge posts 1. In addition, a plurality of deck plates 3 made of a steel material is installed on the main beams 2. [39] The first cross beam 4-1 is installed on the lower surfaces of the plurality of main beams 2 between the bridge posts 1 to cross the plurality of main beams 2.
Furthermore, a plurality of through-holes (not shown) is formed in the first cross beam
4-1. [40] The first cross beam 4-2 is installed on the lower surfaces of the plurality of main beams 2 to cross the plurality of main beams 2 and to be spaced apart from the first cross beam 4-1 at a predetermined distance. Furthermore, a plurality of through-holes
(not shown) is formed in the first cross beam 4-2. [41] The fixing members 6 for fixing tension members 7 are installed at the outsides of the first cross beam 4-1 and the second cross beam 4-2. [42] The third cross beam 4-3 is installed on the lower surfaces of the main beams 2 at an intermediate portion between the first cross beam 4-1 and the second cross beam
4-2 to cross the plurality of main beams 2. The saddles 5 are installed on the lower surface of the third cross beam 4-3. [43] The first through third cross beams 4-1 through 4-3 are installed on the lower surfaces of the plurality of main beams 2 to prevent the temporary bridge from sagging. Furthermore, by inserting the plurality of tension members 7, it is possible to reduce positive moment applied to the span of the temporary bridge.
[44] The tension members 7 are connected between the first cross beam 4-1 and the second cross beam 4-2 across the saddles 5 installed on the lower surface of the third cross beam 4-3 and are fixed by the fixing members 6. As the tension member 7, a high-strength steel rod or a high-strength steel wire is mainly used. By attaching the saddles 5 to the lower surface of the third cross beam 4-3, the tension members 7 are sloped downward from the first and second cross beams 4-1 and 4-2 to the third cross beam 4-3. Thus, an upward load is applied to the saddles 5 and the third cross beam 4-3 such that a sagging phenomenon can be efficiently removed.
[45] The both ends of the main beams 2 are seated on L-shaped connection slabs 8, and thus the temporary bridge is evenly connected to the road of land and becomes more stable.
[46] FlG. 2 is a lateral cross-sectional view taken along line A-A of FlG. 1 according to a first embodiment of the present invention, FlG. 3 is a lateral cross-sectional view taken along line B-B of FlG. 1 according to the first embodiment of the present invention, and FlG. 4 is a plan view of the long-span temporary bridge illustrated in FlG. 1 according to the first embodiment of the present invention.
[47] As shown in FIGS. 2 through 4, in the first embodiment, the tension members 7 are connected between the first cross beam 4-1 and the second cross beam 4-2 at positions between the main beams 2.
[48] Referring to FIGS. 2 through 4, the through-holes are formed in the first cross beam
4-1 and the second cross beam 4-2 at positions between the main beams 2, and the tension members 7 pass through the through-holes formed in the first cross beam 4-1 and the second cross beam 4-2 and are fixed by the fixing members 6 installed at the outsides of the cross beams 4-1 and 4-2.
[49] The saddles 5 are attached to the lower surface of the third cross beam 4-3 at positions corresponding to the through-holes of the first cross beam 4-1 and the second cross beam 4-2.
[50] Although, in the first embodiment, one through-hole is formed at the position between the main beams 2, the present invention is not limited to this embodiment. At least two through-holes may be formed at the positions between the main beams 2 and a plurality of tension members may be installed in correspondence with the through- holes. Thus, it is possible to realize a long span of 30 m by applying more prestress and to uniformly distribute a force. Mode for the Invention
[51] FlG. 5 is a lateral cross-sectional view taken along line A-A of FlG. 1 according to a second embodiment of the present invention, FlG. 6 is a lateral cross-sectional view taken along line B-B of FlG. 1 according to the second embodiment of the present invention, and FlG. 7 is a plan view of the long-span temporary bridge illustrated in FlG. 1 according to the second embodiment of the present invention.
[52] As shown in FIGS. 5 through 7, in the second embodiment, the tension members 7 are connected between the first cross beam 4-1 and the second cross beam 4-2 at positions between the main beams 2 and positions corresponding to the main beams 2.
[53] Referring to FIGS. 5 through 7, the through-holes are formed in the first cross beam
4-1 and the second cross beam 4-2 at positions between the main beams 2 and positions corresponding to the main beams 2, and the tension members 7 pass through the through-holes formed in the first cross beam 4-1 and the second cross beam 4-2 and are fixed by the fixing members 6 installed at the outsides of the cross beams 4-1 and 4-2.
[54] The saddles 5 are attached to the lower surface of the third cross beam 4-3 at positions corresponding to the through-holes of the first cross beam 4-1 and the second cross beam 4-2.
[55] Although, in the second embodiment, one through-hole is formed at the position between the main beams 2, the present invention is not limited to this embodiment. At least two through-holes may be formed at the position between the main beams 2 and a plurality of tension members may be installed in correspondence with the through- holes. In the second embodiment, since more tension members can be installed, it is possible to realize a long span and to uniformly distribute a force by applying more prestress.
[56] FlG. 8 is a partially enlarged front view illustrating the structure of the fixing member 6, and FlG. 9 is a partially enlarged lateral cross-sectional view illustrating the structure of the fixing member.
[57] Referring to FIGS. 8 and 9, the fixing member 6 is installed at the outside of the cross beam 4-1 to fix the tension member 7 passing through the through-hole of the cross beam 4-1 using a bolt or the like.
[58] As shown in FlG. 8, the tension member 7 is installed to be slightly sloped inward, the fixing member 6 is also installed to be slightly sloped.
[59] FlG. 10 is a partial enlarged front view illustrating a structure in which a reinforcement frame 9 is attached to one side of the cross beam 4-1 and the lower surface of the main beam 2.
[60] As shown in FlG. 10, the reinforcement frame 9 is attached to the inside of the cross beam 4-1 and the lower surface of the cross beam 2 using a fastening member 10 such as a bolt to distribute forces applied to both the cross beams 4-1 and 4-2 by the tension forces of the plurality of tension members 7, thereby realizing a more stable support structure. [61] When the reinforcement frame 9 is attached to the cross beam 4-1, a reinforcement plate 10 is adhered to the inside of the cross beam 4-1 and the reinforcement member 10 and the reinforcement frame 9 are then fastened using a fastening member such as a bolt.
[62] Although the exemplary embodiments and the modified examples of the present invention have been described, the present invention is not limited to the embodiments and examples, but may be modified in various forms without departing from the scope of the appended claims, the detailed description, and the accompanying drawings of the present invention. Therefore, it is natural that such modifications belong to the scope of the present invention. Industrial Applicability
[63] A long-span temporary bridge using cross beams having through-holes according to the present invention can apply to a temporary support for installing a bridge slab or a structure having a long-span bridge function as well as a simple temporary bridge.

Claims

Claims
[1] A long-span temporary bridge having a plurality of bridge posts, a plurality of main beams installed on the bridge posts, and a plurality of deck plates installed on the main beams, comprising: a first cross beam which is installed on the lower surfaces of the plurality of main beams between the bridge posts to cross the plurality of main beams and has a plurality of through-holes formed therein; a second cross beam which is installed on the lower surfaces of the plurality of main beams to cross the plurality of main beams and to be spaced apart from the first cross beam and has a plurality of through-holes formed therein; a plurality of tension members which is connected between the first cross beam and the second cross beam and of which the both ends pass through the through- holes formed in the first cross beam and the second cross beam and are protruded from the first cross beam and the second cross beam; and a plurality of fixing members which is installed at one sides of the first cross beam and the second cross beam to fix the both ends of the tension members.
[2] The long-span temporary bridge according to claim 1, further comprising: a third cross beam which is installed on the lower surfaces of the main beams at an intermediate portion between the first cross beam and the second cross beam to cross the plurality of main beams; and saddles which are installed on the lower surface of the third cross beam and in which the tensions member are positioned.
[3] The long-span temporary bridge according to claim 2, wherein the number of the through-holes formed in the first cross beam and the second cross beam at p ositions between the main beams is at least one.
[4] The long-span temporary bridge according to claim 2 or 3, wherein the through- holes are formed in the first and second cross beams at position corresponding to the main beams.
[5] The long-span temporary bridge according to claim 1, further comprising a reinforcement frame attached to one sides of the first cross beam and the second cross beam and the lower surfaces of the main beams.
[6] The long-span temporary bridge according to claim 1, wherein the both ends of te main beams are seated on connection slabs.
PCT/KR2006/000103 2005-01-11 2006-01-10 Long-span temporary bridge using cross beam having through-holes WO2006075863A1 (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
KR10-2005-0002501 2005-01-11
KR1020050002501A KR100572860B1 (en) 2005-01-11 2005-01-11 A Long-distance-pier temporary bridge Using Cross Beam Having Through-holes

Publications (1)

Publication Number Publication Date
WO2006075863A1 true WO2006075863A1 (en) 2006-07-20

Family

ID=36677868

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/KR2006/000103 WO2006075863A1 (en) 2005-01-11 2006-01-10 Long-span temporary bridge using cross beam having through-holes

Country Status (2)

Country Link
KR (1) KR100572860B1 (en)
WO (1) WO2006075863A1 (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100732701B1 (en) * 2005-12-13 2007-06-27 (주)씨디텍엔지니어링 Temporary Construction System Using a Steel Pipe Structure
KR100733720B1 (en) * 2006-02-15 2007-07-04 (주)핸스건설 Droop prevention structure of steel pipe strut and main girder

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4620400A (en) * 1980-11-25 1986-11-04 Bouygues Prestressed concrete structure, a method of producing this structure, and elements for implementing the method
US5425152A (en) * 1992-08-14 1995-06-20 Teron International Building Technologies Ltd. Bridge construction
US5867855A (en) * 1996-04-08 1999-02-09 Kim; Sun Ja Method for connecting precast concrete girders
KR20040086238A (en) * 2004-09-21 2004-10-08 김성 Long-distance-pier temporary bridge using stayed cable
KR20050002746A (en) * 2004-12-13 2005-01-10 김성 Cable-Stayed Girder Bridge Type Long-distance-pier temporary bridge

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4620400A (en) * 1980-11-25 1986-11-04 Bouygues Prestressed concrete structure, a method of producing this structure, and elements for implementing the method
US5425152A (en) * 1992-08-14 1995-06-20 Teron International Building Technologies Ltd. Bridge construction
US5867855A (en) * 1996-04-08 1999-02-09 Kim; Sun Ja Method for connecting precast concrete girders
KR20040086238A (en) * 2004-09-21 2004-10-08 김성 Long-distance-pier temporary bridge using stayed cable
KR20050002746A (en) * 2004-12-13 2005-01-10 김성 Cable-Stayed Girder Bridge Type Long-distance-pier temporary bridge

Also Published As

Publication number Publication date
KR100572860B1 (en) 2006-04-26
KR20050012863A (en) 2005-02-02

Similar Documents

Publication Publication Date Title
KR100569028B1 (en) Box-type temporary bridge
KR101203978B1 (en) upper structure of bridge
KR100891924B1 (en) Variable section u-type girder for temporary bridge
KR100985139B1 (en) Reinforcement method and apparatus for upper concrete structure by using reinforcement members having reinforcement fibers thereon
KR101924092B1 (en) Temporary structure and constructing method for the same
KR200400051Y1 (en) The fabricated temporary bridge
KR100893876B1 (en) A lever rule prestressing segment girder and its construction method
KR100758994B1 (en) Reinforced beam with vertical h-steel or i-steel for stiffness, the construction structure and bridge construction method using the same
KR20060051577A (en) Hollow prestressed concrete (hpc) girder and spliced hollow prestressed concrete girder (s-hpc) bridge construction method
WO2006065041A1 (en) Temporary bridge of a cable-stayed girder bridge type with a long span
JP2010189918A (en) Form for floor slab and floor slab construction method
KR100592196B1 (en) large number bracket in which supporter was installed is used and it is a bridge, multiplex point installed so that support might be carried out support bracket and its installation method
KR100977855B1 (en) Prestressed steel girder
WO2006075863A1 (en) Long-span temporary bridge using cross beam having through-holes
KR200381696Y1 (en) A Long-distance-pier temporary bridge Using Cross Beam Having Through-holes
KR101545329B1 (en) Temporary bridge
KR102057323B1 (en) Attached or mounted extended footbridge
JP3394519B2 (en) Viaduct concrete continuous arch structure
KR20060053030A (en) Net type external prestress strengthening apparatus and method for slab bridges
KR101618200B1 (en) Girder bridge construction method using temporary support member and tendon and the girder bridge therewith
KR100458046B1 (en) Struture for continuing intermediate support of compositive girder bridge
KR102546655B1 (en) Precast type modular girder
KR101109128B1 (en) Footbridge having reinforcement structure
KR200458728Y1 (en) temporary installation bridge having external reinforcement and prestressing
KR200422998Y1 (en) Temporary Bridge having Circular Steel Piers and Prestressing Structure

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application
NENP Non-entry into the national phase

Ref country code: DE

122 Ep: pct application non-entry in european phase

Ref document number: 06700136

Country of ref document: EP